Opinion
Rеgional Steel Corporation (Regional) appeals judgment entered in favor of its insurer, Liberty Surplus Insurance Corporation (Liberty). The trial court found that Liberty had no duty to defend Regional against claims brought by JSM Construction, Inc. (JSM), arising out of Regional’s installation of defective steel framing in an apartment building JSM was constructing. We affirm.
FACTUAL BACKGROUND AND PROCEDURAL HISTORY
1. The Florentine Project
JSM Florentine, LLC (JSM Florentine), is the owner of an apartment building, the Florentine Apartments, under construction in North Hollywood in 2004 (Florentine Project). The Florentine Project complex consists of 14 stories, including retail space on the ground floor, four floors of parking, and 180 residential units on the upper floors. JSM was the general contractor on *1382 the project. Regional was a subcontraсtor engaged pursuant to a June 4, 2004 subcontract to provide reinforcing steel to the Florentine Project’s columns, walls, and floors. Webcor Construction LP (Webcor) was engaged to supply and pour concrete to encase Regional’s rebar skeleton.
From May through September 2004, Regional prepared and submitted shop drawings that used both 90-degree and 135-degree seismic tie hooks in shear walls. JSM and the structural engineer for the project, Babayan & Associates (Babayan), approved the drawings. In October 2004, Regional began construction on the project, using both the 90-degree and 135-degree seismic hooks as approved in the shop drawings. Webcor poured concrete enсasing the rebar and tie hooks.
In January 2005, a city building inspector issued a correction notice requiring the exclusive use of 135-degree hooks. In April 2005, JSM became aware of the problem and informed Regional that it needed to use 135-degree hooks. On May 3, 2005, JSM stopped the pouring of concrete pending resolution of the hook issue. Regional immediately began to fabricate 135-degree hooks. In June 2005, the city notified JSM that garage levels one through three, and some on level four, had defective tie hooks and required repair. JSM refused to pay Regional’s invoices and withheld $545,000.
2. The Policy 1
In August 2005, JSM purchased a commercial liability policy from Liberty (Policy) with an effective date of August 5, 2005. Liberty added Regional as an аdditional named insured, effective as of October 5, 2005. The Policy consists of various standard, preprinted ISO (Insurance Services Organization) forms, as well as several endorsements, including a wrap endorsement (Wrap Endorsement) converting the Policy into a “wrap” policy specific to the Florentine Project. The Policy provides in relevant part that Liberty will “pay those sums the insured becomes legally obligated to pay as damages because of . . . ‘property damage’ to which this insurance applies.” The Policy applies to “ ‘property damage’ ” caused by an “ ‘occurrence’ ” that takes place on or after the policy’s “Retroactive Date” of August 5, 2005. Through a series of endorsements, the Policy was extended to November 5, 2008.
*1383 The Policy excludes coverage for “ ‘[property damage’ ” to “ ‘impaired property’ ” or property that “has not been physically injured, arising out of . . . ffl . . . [a] defect, deficiency, inadequacy or dangerous condition in ‘your product’ or ‘your work.’ ” “ ‘Property damage’ ” is defined as “[physical injury to tangible property, including all resulting loss of use of that property. . . . [(J[] . . . Loss of use of tangible property that is not physically injured . . . shall be deemed to occur at the time of the ‘occurrence’ that caused it.” “ ‘Impaired Property’ ” is defined as “tangible property, other than ‘your product’ or ‘your work’ that cannot be used or is less useful because . . . [j[] . . . [i]t inсorporates ‘your product’ or ‘your work’ that is known or thought to be defective, deficient, inadequate, or dangerous [f] . . . [f] if such property can be restored to use by . . . [f] . . . the repair, replacement, adjustment or removal of ‘your product’ or ‘your work.’ ” An “ ‘[occurrence’ ” is defined as “an accident, including continuous or repeated exposure to substantially the same general harmful condition.” 2
The Wrap Endorsement modified the ISO form by providing that “[tjhis insurance applies only to . . . ‘property damage’ . . . that occurs at a Project Site . . . and arises solely out of that portion of operation performed: [f] . . . by ... an Additional Named Insured; [f] . . . that are within the scope of a Designated Project listed in the Designated Project Schedule; and [f] ... at the Project Site listed for that Designated Project.”
The Wrap Endorsement did not specify a retroactive date or an occurrence date.
3. The Underlying Action
In August 2007, Regional filed an action against JSM for payment of $545,201.31.
On or about September 18, 2007, JSM filed a cross-complaint against Regional and other subcontractor entities, including Babayan, Webcor (the concrete subcontractor), and Quality Assurance International, Inc. (the quality inspection consultant), asserting claims against each entity for breach of contract and breach of express and implied warranties. JSM contended that Regional failed to comply with the subcontract and the building code when it *1384 installеd horizontal reinforcement for the parking garage by installing 90-degree tie hooks, and as a result JSM was required by the city to make repairs that required it to open up numerous locations in the concrete walls, weld reinforcements to the steel placed by Regional, and otherwise strengthen the inadequate installation.
JSM’s claims against Webcor alleged that Webcor poured its concrete in and around Regional’s reinforcing steel, which did not contain the required 135-degree hooks, and JSM alleged that Babayan permitted Regional to install the defective hooks and failed to prevent Webcor from pouring concrete around the defective hooks, and further that Quality Assurance permittеd Webcor to pour concrete without first verifying that the proper tie hooks were used. JSM alleged that it was damaged because completion of the project was delayed, resulting in loss of use, loss of rental income, and other damages. On July 14, 2008, JSM filed a first amended cross-complaint in the underlying action (FACC) adding claims based upon theories of negligence, negligent interference with economic advantage, and asserted claims against the parties’ performance bonds.
In August 2009, Webcor .filed an FACC seeking indemnity, contribution, and declaratory relief against JSM, Regional and Babayan. Webcor’s allegations were conclusory in nature: Webcor alleged its fault was passive and secondary and sought to hold Regional liable for any and all damages for which Webcor might be liable to JSM.
4. Regional’s March 2008 and August 2009 Tenders
By letter dated March 11, 2008, Regional tendered the defense of JSM’s cross-complaint in the underlying action to Liberty. Liberty acknowledged the tender and by letter dated April 25, 2008, declined coverage. Liberty asserted that no damage to property was alleged, and the purely economic losses caused by the need to reopen the poured concrete to correct the tie hook problem did not constitute property damage within the meaning of the Policy. Further, the tie hook problem did not constitute an “occurrence” within the meaning of the Policy because the alleged damage was nоt caused by an accident. After receiving no response from Regional, Liberty closed the file on the claim on June 5, 2008.
On August 26, 2009, Regional again tendered its claim to Liberty. The new tender was based on Regional’s assertion that Webcor believed that JSM was asserting claims based upon the out-of-level concrete floors and resulting cracks in the slabs at levels PI through P3, and that was the basis on which Webcor sought indemnity in its FACC. In support, Regional submitted discovery consisting of three deposition excerpts regarding cracking of the concrete floors poured by Webcor.
*1385 Liberty reviewed the tender (which also included the subcontract, JSM’s FACC, Webcor’s proposed FACC) and saw no evidence that JSM was asserting claims for out-оf-level floors. Liberty submitted the tender to outside counsel for further evaluation, and Liberty obtained an opinion from ■independent counsel (Ropers Majesky Kohn Bentley) that the second tender did not state a claim. Neither JSM nor its outside counsel was able to confirm a claim for out-of-level floors based upon a review of the pleadings and motions from the underlying action, as well as the discovery.
On February 4, 2010, Liberty denied Regional’s second tender. Liberty asserted that it never received any evidence from Regional that supported its claim that it was seeking damages for uneven floors, cracked concrete, or concrete edge curl. Rather, the tender described concrete that set improperly and other problems with the floors, but did not mention a claim by JSM against Regional for the cost of repairing out-of-level floors or the tie hook problem.
Sometime in October 2009, Regional, JSM, Webcor and Babayan settled the underlying action. In the settlement agreement (to which Liberty was not a party), the recitals set forth that Regional “caused or was responsible for damage to, and loss of use of, tangible property at the PROJECT, including but not limited to out-of-level, cracked or otherwise damaged floors” and that the parties released all claims ¿gainst Regional, including those for “damage to and/or loss of use of tangible property at the PROJECT, out-of-level, cracked or otherwise damaged floors.”
5. Regional’s Complaint Against Liberty
Regional’s complaint against Liberty filed June 23, 2011, alleged claims for breach of contract, breach of the implied covenant of good faith and fair dealing (duty to defend), and breach of the implied covenant of good faith and fair dealing (duty to settle).
6. Liberty’s Motion for Summary Judgment
On June 28, 2012, Liberty filed its motion for summary judgment or in the alternative summary adjudication of issues against Regional. Liberty asserted that the Policy’s insuring clause for property damage did not cover intangible economic loses or nonperformance of contractual obligations based on a defective product or diminution in value of the project caused by the defective tie hooks; damages from the tie hooks did not arise from an “occurrence” as defined in the Policy because an occurrence could not arise from the deliberate act of an insured; and even if Regional’s intentional placement of improper 90-degree seismic hooks in the shear walls constitute *1386 “property damage” caused by an “occurrence,” the Policy’s exclusions for damage to impaired property or property not physically injured eliminated any potential for coverage.
Regional responded that JSM’s FACC asserted claims for damage to property and loss of use of tangible property based on JSM’s allegations that it needed to repair damage to the garage by opening walls and floоrs to install support columns. Regional relied on
Armstrong World Industries, Inc.
v.
Aetna Casualty & Surety Co.
(1996)
In support of its opposition, Regional submitted deposition testimony where JSM questioned Jeffrey West of Webcor in deposition about floor repair. West testified that there were two areas where the floor needed repair because “the concrete went off.” Webcor “bushed” it and “chipped” it, and put a material on top of it. West believed the cause of the problem was that the concrete “set up too” fast. One area of the concrete had set faster than another. There was a problem with the out-of-level floors where thе concrete had set in some places but not others. Scott Lansburg of JSM testified in deposition that some of the slab in level P2 of the garage was cracked. He was asked about repair procedure, which involved a “common procedure called epoxy injection.” Lansburg did not observe any cracking in the walls on P2.
7. Trial Court Ruling
The trial court found that Liberty had no duty to defend Regional. The court found that the parties’ papers revealed there were no disputed material facts and thus any evidentiary objections were overruled. 3 The court found the Policy excluded coverage for property damage arising out of a defect, *1387 deficiency, inadequacy or dangerous condition оf the insured’s work, or a delay or failure by an insured to perform a contract in accordance with its terms. Further, coverage was excluded for impaired property because such property was defined as tangible property, other than the insured’s work known or thought to be defective, deficient, inadequate or dangerous, “if such tangible property [could] be restored to use by repair, replacement, adjustment or removal of the insured’s product or work, or the insured fulfilling the terms of the contract.”
The court found the JSM FACC only alleged facts arising out of the damage caused by the defective seismic hooks and did not allege any facts of any other damage attributable to Regional. Under the terms of the Policy, the seismic hook issue and JSM’s costs to repair it did not constitute property damage under F & H Construction, supra, 118 Cal.App.4th at pages 371-373. The court disagreed that the Wrap Endorsement removed the conditions regarding “occurrence” and “Retroactive Date” because the Policy was to be construed as a whole. With respect to the Webcor FACC, the court found that the JSM FACC asserted damages attributable to Webcor’s concrete, which was not asserted against Regional, and thus the Webcor FACC did not establish that JSM asserted covered damages against Regional.
The court acknowledged that while the JSM FACC was broad enough to allege facts apart from the seismic issue, the insured could not spеculate about unpleaded third party claims to manufacture coverage. Further, the deposition testimony did not establish that JSM asserted claims against Regional based upon faulty concrete. Finally, the court observed there was no evidence that the settlement agreement was ever submitted to Liberty.
DISCUSSION
Regional contends that the Wrap Endorsement replaced the requirement that property damage result from an occurrence prior to the retroactive date with the requirement that the property damage occur “at a Project Site” and “arise[] solely out of that portion of operation performed.” Second, Regional contends that the incorporatiоn of its seismic hooks into the Florentine Project constituted property damage and was an occurrence within the meaning of the Policy and gave rise to the duty to defend, principally relying on
Shade Foods, Inc.
v.
Innovative Products Sales & Marketing, Inc.
(2000)
I. Standard of Review
In a motion for summary judgment, the moving party “bears the burden of persuasion that there is no triable issue of material fact and that he is entitled to judgment as a matter of law.”
(Aguilar v. Atlantic Richfield Co.
(2001)
II. Duty to Defend
An insurer has a duty to defend an insured if it becomes aware of, or if the third party lawsuit pleads, facts giving rise to the potential for coverage
*1389
under the insuring agreement.
(Waller
v.
Truck Ins. Exchange, Inc.
(1995)
Whether the insurer owes a duty to defend usually is made by comparing the allegations of the complaint with the terms of the poliсy.
(Waller, supra,
“Interpretation of an insuranсe policy is a question of law and follows the general rules of contract interpretation.”
(MacKinnon v. Truck Ins. Exchange
(2003)
An insurance policy provision is considered to be ambiguous when it is capable of at least two reasonable constructions. If we cannot eliminate an ambiguity “ ‘by the language and context of the policy, [we] invoke the principle that ambiguities are generally construed against the party who caused the uncertainty to exist (i.e., the insurer) in order to protect the insured’s reasonable expectation of coverage.’ ”
(County of San Diego v. Ace Property & Casualty Ins. Co., supra,
To that end, an insurance policy’s coverage provisions must be interpreted broadly to afford the insured the greatest possible protection, while a policy’s exclusions must be interpreted narrowly against the insurer.
(MacKinnon, supra,
III. Construction Insurance
A. Wrap Endorsement Did Not Eliminate the Requirement That the Claim Occur During the Retroactive Period
Regional contends that the Wrap Endorsement replaced the requirement that property damage result from an occurrence before the “Retroactive Date” with the requirement that the property damage occur “at a Project Site” and “arise[] solely out of that portion of operation performed.” Liberty responds *1391 that JSM did not allege an occurrence because Regional installed the tie hooks intentionally, not by accident.
Here, the alleged damage occurred outside of the Policy’s undisputed effective date of August 5, 2005, because the city discovered the tie hook problem in January 2005. The Wrap Endorsement does not modify this requirement; rather, it only modifies and/or sets forth the six еnumerated items (who is an insured, insuring agreement amendment, products exclusion, products completed operations, other insurance, and additional named insured schedule) that specifically modified the Policy. The remaining provisions of the Policy were unchanged by the Wrap Endorsement. “Endorsements on an insurance policy form a part of the insurance contract [citation], and the policy of insurance with the endorsements and riders thereon must be construed together as a whole [citation].”
(Narver v. California State Life Ins. Co.
(1930)
B. Defective Tie Hooks Do Not Constitute “Property Damage” for Purposes of Coverage Analysis
The law is in conflict on whether construction defects that are incorporated into a whole property constitute property damage for purposes of a commercial general liability (CGL) policy. One line of cases states the basic rule and denies coverage for the cost of removing and replacing defective work or material, and considers such costs as economic loss, not physical injury to the property. (See, e.g.,
F & H Construction, supra,
118 Cal.App.4th at pp. 372-373; see also
St. Paul Fire & Marine Ins. Co. v. Coss
(1978)
In a case adopting the view of no coverage,
F & H Construction, supra,
On the other hand, other cases hold that where the defective work or material must be removed or repaired to comply with building code or health and safety standards, its presence constitutes physical injury to the building— the physical linking of the defective material to the building is the physical injury. In
Armstrong, supra,
However,
Armstrong, supra,
Here, however, Armstrong and Shade Foods are inapposite because they involved contamination by hazardous materiаls that were incorporated into a whole, and did not involve the incorporation of defective workmanship into a construction project. California cases consistently hold that coverage does not exist where the only property “damage” is the defective construction, and damage to other property has not occurred. Under that thesis, there is no coverage for Regional’s use of defective tie hooks. Indeed, Regional’s attempts to bring the allegedly cracking concrete floors within the definition of “other” property in order to obtain coverage fail because JSM made no allegations that Regional’s installation of the tie hooks, rather than Webcor’s pouring of the concrete, was the cause of out-of-level floors. The only allegations JSM made against Regional were that it failed to install the proper tie hooks, and its failure to do so necessitated demolition and repair of the affected areas—allegations squarely within the ambit of the rule of F & H Construction that this type of repair work is not covered under a CGL policy. Further, in its cross-complaint, Webcor nowhere alleged indemnity against Regional based upon out-of-level floors; rather, its allegations were conclusory and sought indemnity based upon JSM’s FACC that alleged claims for demolition, repair, and lost use based on the faulty tie hooks. For the same reason Regional’s attempts to bring thе defective work within the “loss of use” provisions of the Policy fails; any loss of use was occasioned by the necessity of repairing Regional’s defective tie hooks, a risk not covered by the CGL Policy. Finally, any recitals in the settlement agreement between JSM, Webcor, Babayan and Regional in the underlying litigation that characterize the construction defects as including the out-of-level floors cannot transform JSM’s construction defect claim against Regional into property damage for purposes of the Policy where there is no evidence that Liberty was aware of the settlement and concurred in this characterization.
C. Policy Exclusions
Regional argues the impaired property exclusion, on its face, only applies if JSM is able to conclusively establish that (1) no other property was damaged, and that (2) the insured’s product was in fact defective. Liberty *1394 responds that neither the pleadings nor evidence support Regional’s contention that ISM alleged a claim to property other than Regional’s own work, and the deposition excerpts do not trigger a duty to defend.
“[I]nsurers often limit coverage in exclusions despite broad general coverage provisions.”
(Westoil Terminals Co., Inc. v. Industrial Indemnity Co.
(2003)
The Policy excludes “ ‘[property damage’ to ‘your product’ arising out of it or any part of it” and also provides, “[d]amage to Impaired Property or Property not Physically Injured,” excludes “ ‘[property damage’ to ‘impaired property’ or property that has not been physically injured, arising out of: [f] (1) [a] defect, deficiency, inadequacy or dangerous condition in ‘your product’ or ‘your work.’ ” The policies define “[y]our product” to mean “[a]ny goods or products . . . manufactured, sold, handled, distributed or disposed of’ by the insured or those it controls. “ ‘Impaired property’ ” means “tangible property, other than ‘your product’. . . that cannot be used or is less useful” because it “incorporates ‘your product’ . . . that is known or thought to be defective, deficient, inadequate or dangerous [][]... [f] if such property can be restored to use” by the “repair, replacement, adjustment or removal of ‘your product’ or ‘your work.’ ”
The “Impaired Property” exclusion bars the possibility of coverage. Under that exclusion, there is no coverage for property damage to “property that has not been physically injured” arising out of the Regional’s negligent failure to perform its contractual obligations based on installation of defective tie hooks. JSM’s action alleged that Regional negligently installed improper tie hooks and thus the underlying suit arose from deficiencies in Regional’s performance of its work or from Regional’s failure to perform a contract in accordance with its terms, or both.
(Watts Industries, Inc. v. Zurich American Ins. Co.
(2004)
*1395 DISPOSITION
The judgment is affirmed. Respondent is to recover its costs on appeal.
Chaney, Acting P. J., and Miller, J., * concurred.
Notes
Wrap policies are used to insure large-scale construction projects. “Wrap programs protect all the parties involved in the project (e.g., owner, general contractor, subcontractors, architects and other design professionals) and thus provide coverage for the entire project. [Citation.] HO • ■ ■ fill • • • Wrap programs are designed to make insurance of construction projects more equitable, uniform and efficient. Because everyone is covered under the same policies, these programs reduce potential disputes among the contracting parties. These programs eliminate the cost of overlapping and duplicative coverage that otherwise would be provided by different members of the project team.” (Croskey, et al., Cal. Practice Guide: Insurance Litigation (The Rutter Group 2013) H 7:1490 to 7:1491, p. 7E-51 (rev. # 1, 2013).)
The Policy also excludes at parаgraph 2, subsection (j) “(5) [t]hat particular part of real property on which you or any contractors or subcontractors working directly or indirectly on your behalf are performing operations, if the ‘property damage’ arises out of those operations; or ['][] (6) [t]hat particular part of any property that must be restored, repaired, or replaced because ‘your work’ was incorrectly performed on it.” The applicability of this exclusion is not at issue in this appeal.
Neither party has raised on appeal any contentions with respect to the trial court’s evidentiary rulings.
Judge of the Los Angeles Superior Court, assigned by the Chief Justice pursuant to article VI, section 6 of the California Constitution.
