Regional Gravel Products, Inc. v. StantonRegional Gravel Products, Inc. v. Stanton
— Order and judgment unanimously affirmed without costs. Memorandum: Plaintiff Regional Gravel Products, Inc. (RGP) agreed to purchase 74 acres of vacant land from defendant Stanton. The printed contract provided that RGP intended to use the property for the mining of sand and gravel and made the sale contingent upon RGP "obtaining any and all required approvals” for such intended use. The addenda to the contract allowed RGP to obtain the required approvals within a specified time and permitted RGP to purchase up to three extensions of 90 days each, which it did, the last period expiring on June 20, 1986. The contract also required RGP to make additional payments to reduce the mortgage if more than a specified quantity of gravel was mined each month. These additional payments were separate from the payments RGP was obligated to make to Stanton pursuant to the terms of the mortgage.
When RGP realized it could not obtain the required approvals within the time limits set out in the contract, it notified Stanton five days before the expiration of the last extension that RGP would remove all contingencies and close the deal. Stanton, having this information, terminated the contract and sold the land to defendant Polvino. Polvino, at the time of the purchase, was aware that RGP had filed a lis pendens against the property and had commenced the instant action against Stanton for specific performance and related relief. Accordingly, Polvino agreed to indemnify Stanton for any costs and damages incurred in the litigation.
Special Term properly granted RGP partial summary judgment on the cause of action for specific performance. Since the mining approval permit contingency was for the sole benefit of RGP, RGP could waive it without Stanton’s consent (BPL Dev. Corp. v Cappel,
Special Term also properly denied Stanton’s motion to resettle the order by deleting reference to her default and properly refused to vacate the default because Stanton’s defense to the contract lacked merit (Charbonneau Custom Logging v Belanger,