REGINELLA CONSTRUCTION COMPANY, LTD, Appellant v. TRAVELERS CASUALTY & SURETY COMPANY OF AMERICA.
No. 13-3756.
United States Court of Appeals, Third Circuit.
June 11, 2014.
568 Fed. Appx. 174
SMITH, Circuit Judge.
Submitted Pursuant to Third Circuit L.A.R. 34.1(a) May 13, 2014.
Indeed, our review of the deposition testimony of Principal McDonough, Brinkos, and the HR specialists Dunlop and Mitchell reveals that each of these individuals tacitly acknowledged that Roney had expressed an interest in any other open position. And each of these individuals disclaimed any responsibility or involvement in the decision not to rehire her. Principal McDonough, Dunlop, and Mitchell were each aware that Roney was pregnant. Principal McDonough indicated it was HR‘s responsibility to advise who could fill any empty positions in the school. Mitchell testified that Principal McDonough and Dunlop would have worked together to staff the positions. Dunlop, however, denied knowing why Roney was not rehired. Although the reason initially proffered was that Roney had not applied, Brinkos affirmed he had no idea why Roney wasn‘t rehired. Yet he went on to explain that Roney was not rehired because the AIU did not actually have a copy of her child abuse clearance and that “[i]f [he] had it in hand, [AIU] would have considered rehiring her.” This is a classic Fuentes v. Perskie inconsistency. Roney has adduced sufficient inconsistencies and contradictions to discredit AIU‘s proffered reason for its failure to rehire her.
This is a close case. Nonetheless, drawing all reasonable inferences in Roney‘s favor, we are compelled to reverse the judgment of the District Court and remand for further proceedings. Whether Roney will be able to prove at trial that her pregnancy was a determinative factor in AIU‘s decision is best left to a jury to resolve.
OPINION
SMITH, Circuit Judge.
Plaintiff Reginella Construction Company, Ltd. appeals two orders of the District Court: (1) the order dismissing its complaint; and (2) the order denying its motion to alter or amend judgment or, in the alternative, for leave to file an amended complaint. For the reasons that follow, we will affirm.
Joseph L. Luciana, III, Esq., James S. Malloy, Esq., Dingess, Foster, Luciana, Davidson & Chleboski, Pittsburgh, PA, for Plaintiff-Appellant.
W. Alan Torrance, Jr., Esq., Dickie, McCamey & Chilcote, Pittsburgh, PA, for Defendant-Appellee.
Before: SMITH, VANASKIE, and SHWARTZ, Circuit Judges.
I.
Reginella is a Pittsburgh-based construction company that performs multimillion dollar public construction projects and has been in business for over twenty-five years. In 2010-2011, Reginella entered into contracts with (1) the Moon Area School District (“MASD“), for conversion of a high school into a middle school, (“Moon Project“) and (2) the Ohio Turnpike Commission (“OTC“), for reconstruction of two service plazas (“Ohio Project“). Defendant Travelers Casualty and Surety Company of America provided bonding for both projects.
Travelers signed these bonding contracts against the backdrop of a General Indemnification Agreement (“GIA“) it had entered into with Reginella in June 2009. The GIA provided that if certain triggering events occurred—such as Reginella defaulting on any contract bonded by Travelers, or Reginella breaching the GIA itself—Reginella would transfer a number of rights to Travelers, including, inter alia, the right to take possession of the work under any bonded contract, to take possession of Reginella‘s property, and to take possession of funds owed to Reginella under any bonded contract.
On April 26, 2012, Travelers sent a letter to MASD demanding payments owed to Reginella on the Moon Project. Travelers urged MASD that it was contractually
During the same time period, problems arose on the Ohio Project. In November 2011, Reginella terminated a subcontractor for failing to perform its contractual obligations, and this subcontractor filed a lien against the Ohio Project. In response, OTC withheld payment from Reginella in the amount of the lien until Reginella provided a lien-over bond from a surety. Reginella asked Travelers to provide this lien-over bond, arguing that it had a continuing obligation to do so under the Ohio Project‘s contract bond. Travelers disagreed and refused to provide the bond, arguing that OTC should release payment without the lien-over bond or that Reginella should obtain this bond from another surety. Negotiations stalled, and as OTC continued to withhold payment from Reginella, Reginella became unable to pay its subcontractors, causing delays in the project. On May 22, 2012, OTC terminated Reginella from the Ohio Project.
On July 26, 2012, Reginella filed a complaint against Travelers in the United States District Court for the Western District of Pennsylvania. With respect to the Moon Project, the complaint alleges four tort claims: (1) intentional interference with the Moon Project construction contract; (2) intentional interference with the Moon Project subcontracts; (3) breach of fiduciary duty; and (4) bad faith. With respect to the Ohio Project, the complaint alleges two tort claims: (1) breach of fiduciary duty; and (2) bad faith. The complaint does not allege any breach of contract claims and makes no reference to the GIA between Travelers and Reginella.
Travelers filed a motion to dismiss, which the District Court granted on May 30, 2013. The District Court dismissed Reginella‘s claims for breach of fiduciary duty because it found that no fiduciary relationship existed between Travelers and Reginella. The District Court dismissed Reginella‘s claims for intentional interference with contractual relations and bad faith on the basis of the “gist of the action” doctrine, which it invoked sua sponte.
On June 28, 2013, Reginella moved to alter or amend the judgment or, in the alternative, to amend its complaint to include breach of contract claims. The District Court denied this motion on September 5, 2013. This timely appeal followed.
II.1
We agree with the District Court that Pennsylvania law controls the disposition1 of this case. There is no doubt that Pennsylvania law applies to Reginella‘s claims relating to the Moon Project. These claims arise from business relationships entered into and carried out in Pennsylvania for the benefit of a Pennsylvania municipal entity. With respect to Reginella‘s two claims relating to the Ohio Project, we also agree that there is no actual conflict between Pennsylvania and Ohio law on the issue of whether Reginella can assert a breach of fiduciary duty or bad faith claim against Travelers.2 Accordingly, for the sake of convenience, this opinion will apply only Pennsylvania law.
Further, we agree with the District Court that Reginella‘s claims for intentional interference with contractual relations and bad faith are barred by Pennsylvania‘s “gist of the action” doctrine.4 Upon consideration of the bonding contracts and the GIA,5 it is clear that Travelers‘s allegedly
Finally, we conclude that the District Court did not abuse its discretion by denying Reginella‘s motion to amend its complaint. It was within the District Court‘s discretion to determine that granting Reginella‘s motion would reward undue delay by encouraging Reginella‘s “wait-and-see” tactics. Further, Reginella is presently pursuing breach of contract counterclaims against Travelers in the Allegheny County Court of Common Pleas. Travelers Cas. and Sur. Co. of Am. v. Reginella Constr. Co., Ltd., et al., GD No. 12-012196.
III.
For the reasons stated, we will affirm the judgment of the District Court.
UNITED STATES of America v. Robert McKNIGHT a/k/a Tweety Bird, Robert McKnight, Appellant.
Nos. 11-1072, 12-4510.
United States Court of Appeals, Third Circuit.
June 12, 2014.
568 Fed. Appx. 178
Submitted Under Third Circuit LAR 34.1(a) April 10, 2014.
