266 F. 272 | 6th Cir. | 1920
(after-stating the facts as above).
The appellant’s argument is that the lien statute refers only to things done and furnished “pursuant to a contract” with the owner; that, when the section providing for the verified statement refers to “the materials” which “shall have been furnished,” it must refer to those materials furnished pursuant to the contract, without which the lien, cannot exist; that, unless there is a definite, mutual obligation, there can be no contract, within accepted definitions; and that, if each successive purchase stands only upon the separate contract therefor, each gives rise to a separate right of lien, which right in turn is, after 60 days, exhausted, if not exercised.
The language of the statute regarding a contract is very broad— “express or implied, written or unwritten”; but it is not easy to see how this expands the scope of the term so as to reach, for example, a proposition which had never been accepted or a tentative arrangement to be performed if the parties should thereafter reach an agreement as to details, although, in these cases, there would often be an acceptance or an acquiescence which would raise the necessary implication. The statute cannot intend to require in all cases an otherwise valid contract, because it plainly covers contracts which might be invalid under the statute of frauds; but the interest of the owner in the property is not reached by lien, unless the owner has made a contract. The Supreme Court of Michigan,, in Woods v. Ayres, 39 Mich. 345, 33 Am. Rep. 396, says:
“To constitute either [an express or implied contract], the parties must occupy to each other a contract status, and there must be that connection, mutuality of will, and interaction of parties, generally expressed, though not ’ very clearly, by the term ‘privity.’ ”
For this reason there is difficulty in thinking that a mere indefinite arrangement and expectation that purchases will be made — as, for example, an arrangement that the merchant will supply materials for the job from time to time, if the parties can from time to time agree upon prices and conditions — would be such a contract as the statute contemplates, if- a precedent general contract were essential as a binder for the different items. Whether this difficulty would be insuperable we do not decide. When we have to do with such a succession of such contracts as there is here (interpreting the facts according to appellant’s contention), it is clear that there- was an express contract by the owner with the materialman as to each purchase, and therefore the
It is open to contention that, since clause (d), as we have arranged the statute above, covers the case of a materialman furnishing materials to a contractor or a subcontractor, clause (b) must refer to the furnishing of materials directly to the owner, and since clause (b) does not contain the condition “in pursuance of any contract,” either directly or by strict grammatical construction, the whole basis of appellant’s argument therefore fails. However, this may be an overnice construction, and it is impossible to conceive a case where materials which are furnished to and accepted by the owner are not taken pursuant to at least an implied contract. We are inclined to disregard this distinction, and to assume that “in pursuance of any contract,” etc., applies to all the various lienors contemplated by the statute.
In the provision that one furnishing the “materials for repairing” shall have a lien therefor on condition that he files his claim within a fixed time after the “last of the materials” was furnished, there is the necessary implication that all the items are held together by some common tie, but nothing to indicate that this tie must be a contract creating, at the beginning, a mutual obligation lasting until the end, and we think all requirements inherent in the language or principle of the statute are met when all the items are ordered from time to time by the owner from the materialman, and all pertain to and are procured for one matter of building or repairing, which has not been either finished or abandoned, and when there was an initial offer to furnish, for this one matter, all materials which might be ordered, though no general acceptance making a definite mutual obligation. We see no reason for requiring, as between owner and materialman, any stricter construction; nor for saying that the lien statement will not reach back to an item more than 60 days old, unless the owner was, at the earlier date, under legal obligation to buy the later item. Whenever the owner, at the later stages of the transaction, gives further specific orders for material, he is in effect consenting that these items come in under the one general transaction, and is extending the time within which statement of lien may be filed, and it seems apparent that the owner may, if he wishes, do this, as against his own interests and those of any one who steps into his shoes.
When we come to consider the case of a mortgage, given as this one was, the same reason prevails. The mortgagee, on January 2d, was bound to know that a repair job was in progress, and would have learned, upon inquiry, that materials had been furnished in December, and that further material must be had. Before the 60 days had expired from the first order, the owner had given further orders, and those had kept alive or extended the right to file the lien, and on January 2d that right in the materialman was absolute. The mortgagee took with notice of this fact, and, as to the materials furnished before that date, it cannot be seriously prejudicial to the mortgagee that the owner, instead of compelling the immediate filing of the statement of lien by refusing or neglecting to make further specific orders, has given these orders and thus kept alive the same right which existed on January 2d.
We are not required to consider a case where the 60 days had expired when the mortgage was given, and where, therefore, the right to the lien was gone, unless the owner, at his option, bought more materials. In such a case, it would depend upon the future discretion or whim of the owner whether the right to lien should be restored, and the mortgagee could not know or learn the condition of the title in this respect. The intervention of the mortgage interest after the material-man had lost all right to impose the lien would raise a somewhat different question; the common tie, the unify of purpose, might be thought broken; on the other hand, a mortgagee, chargeable with notice when he takes his mortgage that a repair job is in progress, is subject, generally, to the equities existing against his mortgagor. We do not undertake to pass upon the question so presented.
It is to be remembered that there is no statutory requirement for unity of contract; unity of purpose well satisfies every theory of unity necessarily implied from the statute; and it has been natural to look for a single contract covering all items, because that would demonstrate unity of purpose. There is analogy, too, in the rule that a time limitation on a right of action runs from the last item in a running account. While this is or may be statutory, it illustrates that a series of specific contracts may, for some purposes, be construed as one transaction.
Our conclusion is in general accord with the results reached by the Supreme Court of Michigan in the two cases that most resemble this: Smalley v. Gearing, 121 Mich. 190, 79 N. W. 1114, 80 N. W. 797; Union Trust Co. v. Casserly, 127 Mich. 183, 86 N. W. 545. True, each-case carries more or less implication that an entire contract was necessary, but whatever contract was essential was found to exist; and if is not easy to see that there was any greater obligation upon Casserly to order the later items of lumber than there was upon the paper company to give the February order which it did give. The criterion quoted in 127 Mich. at page 185, 86 N. W. at page 546, from Phillips on Mechanics’ Liens, is not, as counsel say, solely whether the whole should “form one matter of settlement.” That was an alternative. The other was, “if the several parts form an entire whole'.” -However, we are better satisfied to rely also upon our study of the principles of the statute rather than to rely alone upon these two decisions.
Noye Co. v. Thread Co., 110 Mich. 161, 67 N. W. 1108, is not inconsistent. There was a formal and complete contract, and the court
It is familiar knowledge that large quantities of building materials are furnished by dealers therein and used in the erection or repair of buildings, etc., merely upon specific from day to day orders and without any agreement which would prevent collection of the price of each item as if it were wholly separate from the others, but pursuant to a general offer to provide the whole as and if specifically ordered. In these so-called running accounts, it may often happen, and perhaps is usually true, that there is no obligation of any kind upon either party relating thereto preceding the giving and accepting of the order for each item. If appellants are correct, the materialman, in such a case, cannot allow more than 60 days to expire after the first item before filing claim of lien therefor, and each item must have corresponding treatment. We think such a construction would be against the spirit of the Michigan act, is not required by the Michigan decisions, and would be against the analogy of those decided cases which are best considered and arise under the most similar statutes. Jones v. Swan, 21 Iowa, 181; Premier v. McElwaine Co., 144 Ind. 614, 621, 43 N. E. 876; State v. Norwegian, etc., 45 Minn. 254, 255, 47 N. W. 796; O’Neill v. Taylor, 59 W. Va. 370, 379, 53 S. E. 471; Big Horn v. Davis, 14 Wyo. 455, 458 et seq., 84 Pac. 900, 85 Pac. 1048, 7 Ann. Cas. 940; Hensel v. Johnson, 94 Md. 729, 733, 51 Atl. 575; Joplin v. Oklahoma, etc., 36 Okl. 547, 552 et seq., 129 Pac. 40.
What has been said fully covers the appeal of the Murray W. Sales Company. Appellant’s theory is there more difficult to sustain, in that we would hesitate to find the absence in fact of an entire contract which would be sufficient even under appellant’s theory.
The order of priority in each case is affirmed.