OPINION
I. Introduction
Appellee Southwest Stainless, L.P. (Stainless) sued Redland Insurance Company (Redland) on a payment bond Red-
II. Factual Background
Prior to trial, Stainless and Redland stipulated to the amount in dispute, the amount of attorney’s fees that should be awarded, and to the fact that Stainless’s April 15, 2003, May 15, 2003, June 13, 2003, and July 15, 2003 certified mail, return receipt requested notices to Redland constituted sufficient notice to Redland under Chapter 2253 of Stainless’s claim on the bond. Stainless copied Sibert with its notices to Redland, mailing the copies to Sibert by regular mail. The parties likewise stipulated that Sibert received at least two of these copies, the May 15, 2003 letter and the July 15, 2003 letter. Red-land nonetheless contends that the trial court erred by entering judgment for Stainless because it contends Stainless was required to send the copies it sent to Si-bert by certified mail, return receipt requested. Redland contends in two issues that Stainless’s failure to mail the copies to Sibert by certified mail, return receipt requested precludes Stainless’s recovery on Redland’s payment bond.
III. Notice Under Government Code Chapter 2253
A governmental entity that enters into a public works contract with a general contractor must under certain circumstances require the contractor to execute performance and payment bonds before work begins. Tex. Gov’t Code Ann. § 2253.021(a) (Vernon Supp.2005). The purpose of the payment bond is to protect claimants who provide labor or materials in the construction of public works because public property is protected from forced sale and therefore may not be made the subject of a mechanic’s lien.
Capitol Indem. Corp. v. Kirby Rest. Equip. & Chem. Supply Co.,
Because the McGregor Act is remedial in nature, “it is to be given the most comprehensive and liberal construction possible.”
Featherlite Bldg. Prods. Corp. v. Constructors Unlimited, Inc.,
IV. Application of the Law to the Facts
The parties stipulated that the notices received by Redland from Stainless complied with the statutory requisites. See Tex. Gov’t Code Ann. § 2253.041(a), (c). Redland argues, however, that the statute required Stainless to also provide notice to the prime contractor — Sibert—by certified mail, return receipt requested. Lisa McClung, the area credit manager for Stainless, testified that copies of each of the notices sent to Redland were sent to Sibert by first-class regular mail on the same date they were mailed to Redland; she “actually, personally, put those in the mail.” Terry Barker, testified that he was employed by Stainless as a credit manager during the relevant period, and that the notices mailed to Sibert by first-class mail were not returned to Stainless based on any nondeliverability.
According to Redland, however, the notice provisions of the Act are to be strictly construed so that Stainless’s mailing of copies of the notices to Sibert by regular mail precludes Stainless’s recovery from Redland on the payment bond — despite McClung’s testimony that she personally placed in the mail the notices addressed to Sibert, despite Barker’s testimony that Si-bert’s copies of the notices were not returned to Stainless for any reason, and despite the parties’ stipulation that Sibert received two of the notices. We cannot agree. Numerous courts, including this court, have held that the Act is remedial in nature and that its provisions, including its notice provisions, are to be liberally construed.
Ramex Constr. Co.,
The cases cited by Redland do not compel an opposite holding.
See, e.g., Wesco Distribution, Inc. v. Westport Group, Inc.,
V. Conclusion
Having overruled the two issues presented by Redland, we affirm the trial court’s judgment.
Notes
. Chapter 2253 of the Texas Government Code is also called the McGregor Act. It was previously codified in the Texas Revised Civil Statutes.
See Green Int'l, Inc. v. Solis,
