66 N.J.L. 218 | N.J. | 1901
The opinion of the court was delivered by
This was a suit brought by the plaintiffs in error against the two railroad companies named as defendants in error.- The action is in tort. At the trial in the Circuit the court directed a verdict for the defendants, on the ground that the receipt of January 9th, 1882, hereinafter referred to, was a conclusive acquittance of the .damages sued for. The judgment entered upon that verdict was affirmed in the Supreme Court, from which judgment of affirmance the plaintiffs brought this writ of error.
The construction of the railroad in question was contracted for by the Paterson Extension Railroad Company, which, pending the construction of the railroad, was consolidated, with other companies, into the New York, Susquehanna and Western Railroad Company. In 1881 the road was located,
*222 “Jan. 9, 1882.
“Received from G. A. Hobart, Pt. Pat. Extension, one thousand dollars in full settlement and discharge of all damages done by Railroad Go. against our church. Railroad Oo. to pay for all work in process.
“H. A. Collins,
“$1000.00. Treas."
This receipt was unquestionably a discharge of all damages sustained by the church up to its date.
The cut in the rear of the church is nineteen feet in depth, and the wall built by the railroad company is nineteen feet high, and is tapering, being eight feet wide at the bottom and eighteen inches at the top. At the top of the wall the face is clear of the church property, but at the bottom it is five feet upon the church property, leaving the wall at the base three feet in width on the property of the railroad company.
In the early part of 1886 further damage to the church ' building was sustained, which, as appears by the correspondence between Mr. Hobart and Mr. Wurts, ended in the payment by the company of $100. Mr. Hobart, in his letter of March 22d, 1886, says that Mr. Potts, the president of the company, “would like to know in some definite shape that the payment which I proposed, $100,- would be the end of their being called upon hereafter to pay for such repairs. I told him I would see you in reference to the matter again.” A blank form of release was prepared by the railroad company and sent to the church. The vestry, by resolution, declined to execute the release, and under date of April 21st, 1886, Mr. Wurts wrote to Mr. Hobart as follows: “I enclose you a copy of resolution of vestry. I do not find any signs of settlement or damages since the last repairs, for which we now seek reimbursement, were made several months ago, and I think we are safe. Except in the event of some, formidable damage or collapse, which we do not in the least anticipate, we shall not trouble the company again.”
In 1881 the south wall of the church had settled about eight inches, the floors had gone down and the gables had
It will be observed that the proposition of the church authorities to the railroad company was for the settlement of all damages, present and prospective, for $3,500; and that proposition was declined by the company, and instead of it the agreement was for the doing by the railroad company of certain specified work, and that the receipt given to Mr. Hobart is expressly made to be in full settlement and discharge of all damages done by the railroad company. Interpreted by the language of the receipt itself, as well as in view of the negotiations that preceded the giving of it, the receipt will not bear the construction that it was intended to cover damages to be sustained thereafter. Such a construction could be made possible only by inserting words in the body of the receipt. Furthermore, the. acts of the company in making payments for subsequent damages, and the correspondence between Mr. Hobart and Mr. Wurts, in April, 1886, are in conformity with the construction that the receipt of January 9th, 1882, applied only to damages up to that time sustained.
Two questions were presented on the argument of this case and in the opinion of the Supreme Court — first, whether the damages sustained in 1887 were compensated for by the payment of 1882, as evidenced by the receipt to Mr. Hobart, and secondly,' the application of the statute of limitations to this cause of action. Both of these questions, though apparently
The damages sued for in this case did not result from an unlawful act of the defendants in making the excavation in 1881. The digging out of the cut was the occasion for requiring the erection of a wall for- the protection of the church propertjq but was not the cause of the injury which was subsequently sustained. Hor did the damages result from the building of the wall, which was, done by agreement between the parties. The agreement was-that the company was to build the wall at' its own expense and make it safe. The wall contracted for was for the protection of the church property in the future, and not a mere temporary expedient. The location, dimensions and construction of the wall and the character of its foundation were committed to the exclusive control of the railroad company. The church officers did not in' any way participate in or supervise the work of construction. It is manifest that the company assumed responsibility for the protection of the church edifice from injury which might follow from the running of its trains. The first proposition in the course of negotiations was made by the officers of. the church, offering for the sum of $3,500 to release the railroad company from all responsibility for present repairs and future damages by reason of constructing and operating the railroad. The company declined that proposition, and instead chose to resort to the erection of a wall of the dimensions and construction that, in the judgment of its officials, would be sufficient to accomplish the purpose, paying the church for past injury to its property not a penny beyond
The wall did not become the property of the plaintiffs; it was part of a retaining wall, extending beyond the church property a considerable distance in both directions. No action could have been maintained by the plaintiffs to recover damages by reason of its defective construction until damage actually occurred. For neither negligence, nor fraud, nor other wrong or immoral conduct or intent, will give rise to a cause of action unless it has resulted in illegal damage. 1 .Encycl. L. & Pro. 667. It is a fundamental principle of law, applicable alike to breaches of contract and to torts, that, in order to found a right of action, there must be a wrongful act done and a loss resulting from that wrongful act. Warwick v. Hutchinson, 16 Vroom 61. The injury sustained by reason of the defective construction of the wall, as it was located, was a continuing injury. It is quite clear that if a suit had been brought in 1882, the plaintiffs could not have recovered in such a suit for the damages which would be sustained in 1887. It would have been impossible at that time to have anticipated the future deterioration in the wall and the damages arising therefrom, and to have made an estimate of the amount thereof as the basis of computation. Compensation in such a suit must be sought after the dam
In the leading case of Backhouse v. Bonomi, reported in the Exchequer Chamber in El., B. & E. 622, and in the House of Lords in 9 H. L. Cas. 502, and also in 16 Eng. Rul. Cas. 216, the plaintiff was- the owner of certain houses standing on land which was surrounded by the lands of B, G and D. E was the owner of mines running underneath the lands of all these persons^ He worked the mines in such a manner (without actual negligence) that the lands of B, C and D sank in; and after more than six years’ interval their sinking occasioned an injury to the houses of A. It was held that a right of action accrued to A when this injury actually occurred, and that his right was not barred by the statute of limitations. This case was decided in the House of Lords by the concurrence of every member of the •court, upon the unanimous opinion of the judges who were in attendance, for the reasons that were given in the judgment of the Court of Exchequer Chamber. The grounds of decision were stated by the Lord Chancellor in these words: “I think it is abundantly clear, both upon principle and authority, that when the enjoyment of the house is interfered with by the actual, occurrence of the mischief, the cause of action then arises, and that the action may then be maintained.” Lord Cranworth said.: “The right of the plaintiff is the right to the ordinary enjoyment of his land, and till that ordinary enjoyment is interfered with, he has nothing
In Darley Main Colliery Co. v. Mitchell, 11 App. Cas. 127, the defendant had, by mining, taken away the substratum supporting the plaintiff’s land, with some cottages on it. A subsidence having taken place, the defendant, by agreement, repaired the damage. This was in or about 1871. No further working was done, but in 1882 a further subsidence took place, causing further injury. In an action brought for the damage in 1882 the defendant pleaded the statute of limitations. It was held in the House of Lords, by Lord Halsbury, Lord Bramwell and Lord Fitzgerald, dissentiente, Lord Blackburn, affirming the judgment of the Court of Appeal, that a fresh cause of action arose when the further damage occurred in 1882, ahd that the action for this was not barred, although more than six years had elapsed since the damage first caused by the defendant’s workings, and although more than six years had elapsed since the last workings by the defendant. The decision of the court was based upon the principle that every new subsidence, although proceeding from the same original act or omission of the defendant, was a new cause of action, for which damages may be recovered. In the course of his opinion Lord Fitzgerald used
In Lamb v. Walker, 3 Q. B. Div. 389, the Court of Queen’s Bench, by a majority (Mellor and Manisty), decided that where the foundations of the plaintiffs land and buildings had been undermined by the removal of lateral support through-mining operations carried on by the defendant on his own land adjoining, and damage had manifested itself, a cause of action had completely arisen, both for apparent damage and for all future damage that might ensue from the original act. This decision was based upon the assumption that no fresh cause of action would arise when fresh damages might arise. This judgment was dissented from by Chief Justice Cockburn, who contended that the decision in Backhouse v. Bonomi, in the Exchequer Chamber and the House of Lords, established conclusively that it is not the withdrawal of the support previously afforded by the adjacent strata, but the actual disturbance of the plaintiff’s enjoyment of his property, which constitutes a wrong and gives a legal ground of complaint, and the damage being the gist of the action, only the damage actually accrued could be recovered in the action, and any further damage must be recovered when it actually accrued in a subsequent action. The views of the Lord Chief Justice were approved in Darley Main Colliery Co. v. Mitchell, and Lamb v. Walker was there expressly overruled. In Lamb v. Walker, supra, Lord Chief Justice Cockburn says: “Of course, I do not lose sight of the rule that damages resulting from one and the same cause of action must be assessed and recovered once for all. But
Following the Darley Main Colliery case, in the subsequent case of Crumbie v. Wallsend Local Board, 1 Q. B. Div. 503 (Court of Appeal, 1891), an excavation was made by the local authorities under a street for the purpose of laying a sewer; it was not properly filled in, and in consequence subsidence of the plaintiff’s land, with injury to houses, took place thereon, which began at a period more than six months before (that being the period of limitation of such an action), and went on continuously to the commencement of an action by the plaintiff in respect of such subsidence. It was held that the further subsidence which took place within the six months before action constituted a distinct cause of action, in respect of which the action was maintainable. Lord Esher, Master of the Eolls, in delivering the opinion of the court, said: “There is no cause of action for any such damage to the plaintiff’s property until it has occurred. When a certain amount of such damage has occurred, there is only a cause of action in respect of that amount. After-wards other damage may occur — that is to say, more of such damage may occur. There is no cause of action in respect of such further damage until it has occurred.”
Numerous cases to the same effect as the cases above cited are cited in 16 Eng. Bul. Gas. 215, 250.
The cases in the courts of this state are in line with the decisions of the English courts on this subject. The leading case is Delaware and Raritan Canal Co. v. Wright, which is reproduced in Delaware and Earitan Canal Co. v. Lee. The facts in that litigation were these: Wright was the owner of a tract of land over which the canal company located and constructed its canal. For the land taken for that purpose Wright was paid, and, by a deed, conveyed the same to the canal company. Beyond the line of the tract so conveyed the company had constructed a culvert over Watson’s creek.
The building of this retaining wall by the company was a lawful act. So far as the foundation rested upon the church property, it had the consent of the church. The duty of making it safe for the protection of the church, and also of reparation, devolved upon the company. The church had no power or duty in that respect; nor had it power to control the running of trains on the adjacent track. The wall gave evidence of deterioration shortly after it was built, and its incapacity to answer the purpose which it was designed to fulfill was demonstrated as early as 1886. Damage from time to time resulting to the church property from the condition of the wall, a new cause of action arose, which gave the plaintiffs the right to maintain an action and recover such damages as had arisen within six years. No steps were taken by the defendants to remedy the defects or to strengthen the wall. Adopting and applying to this case the language of Lord Fitzgerald, in Darley Main Colliery Co. v. Mitchell, supra, "There was a complete cause of action when the first ■subsidence took place, in respect cf which compensation was given; but there was a liability to further disturbance. The defendant permitted the state of things to continue, without taking any steps to prevent the occurrence -of any future injury. A fresh subsidence took place, causing a new and further disturbance of the plaintilFs enjoyment, which gave him a new and distinct cause of action.”
The direction of a verdict for the defendants was erroneous. The case made by the plaintiffs should have gone to the jury. . For this error the judgment should be reversed.
For affirmance — Van Stckel, Gummerb, Fort, Garret-son, Hendrickson. 5.
For reversal — The Chibe Justice, Bogert, Adams, Vred-ENBURGH, VOORIiEES, VROOM. 6.