delivered the opinion of the court.
Reagan sued Matthew H. Ryan and John Powers, before a justice of tbe peace, by attachment, and garnished tbe Pacific
Matthew H. Ryan and John Powers were contractors of the Pacific Railroad Company, under special contract to do the graduation and masonry on sections seven and eight of said road. This contract was made by them in the name of Matthew H. Ryan & Co. The contract was partly in writing and partly in print, and contained numerous specifications, or, more properly, sections under the general head of specifications. Some of these will be noticed as of importance, and others not, in this opinion.
“Sec. 40. Should the contractor, at anytime after sixty days from the beginning of the contract, not be found to pro - ceed with all or any sections of his work, in such a manner as to secure, in the opinion of the engineer, the entire completion of the work, on the said section or sections, within the time allowed by this contract, it shall be the duty of the engineer so to notify him; and should he not then, within ten days of the date of the said communication, make the necessary exertions and arrangements to compensate, in the opinion of the engineer, for previous negligence or inactivity, and to insure the fulfillment of his contract in due season, the engineer shall notify the president of the company and the first party to that effect, and the contract shall then be declared and considered null and void, and the engineer shall be at liberty to employ other persons to fulfill the contract, and finish all or any parts of the work of graduation, masonry or otherwise, on said section or sections, and the contractor shall be liable for any damage, or for any extra expense caused by his neglect to fulfill his engagements,” &c.
“ Sec. 41. In case of failure to fulfill the contract, the
“ Sec. 51. It is understood and agreed, that said Matthew H. Ryan & Co. shall take ten per cent, of the amount that shall become due and payable under this contract, in stock of the Pacific Railroad.”
“ Sec. 52. Payments, conditional on the true and faithful performance of this contract, will be made monthly, as the work advances, at the estimate of the engineer, reserving ten per cent, until the completion of the contract. These payments refer only to work completed, and it will be entirely discretionary with the company to make payments on account of materials delivered, but not applied permanently to the work ¡for which they may be intended.”
This contract was dated 24th December, 1851. The bill of 'exceptions shows that there was but one witness examined. He -was the chief engineer of the Pacific Railroad Company. From 'his testimony, it appears that Ryan was the acting man ; that about the time of payment of July 10th, 1852, Ryan received ’the monthly estimate and something in advance, and disappeared from the work ; that the work stopped on account of Ryan’s going away ; that Powers, Ryan’s partner, came to the witness and offered to go on with the contract, if the ten per cent, retained, as per contract, was paid him. The witness agreed to give him the ten per cent, if he would apply it to the payment of the wages due the laborers for their last month’s work on the sections contracted for by M. H. Ryan & Co. Witness also says that he required security for this. This was not agreed to, and the work was not resumed. Witness stated that .he then considered the contract forfeited or abandoned. Another contract was afterwards made with other parties, at an
Upon this statement, substantially, of the facts, many instructions were given by the law commissioner. We shall notice only one or two of them.
The 4th, as numbered by the record, as being asked by plaintiff, and given by the court, is as follows :
“ The Pacific Railroad is bound to show that the terms of the contract between it and Ryan & Co. were not complied with, before they were empowered to forfeit that contract, and the said road is bound to show that said contract was forfeited exactly in the manner provided therein, before they can withhold any moneys due Ryan & Co. on account of said contract.”
This instruction is erroneous ; it does not place before the jury the law of this case properly. We presume the money here alluded to by the court below was the amount of the ten per cent, retained by the Railroad Company out of the monthly assessments. Was it the intention of the plaintiff below, in asking this instruction, to have the court below declare that this contract could only be declared forfeited in the manner pointed out in t'he 40th section ? Did that section provide against the contingency of Ryan’s receiving the monthly estimates and something in advance thereto, and then absconding ? Or does not Ryan’s absconding and deserting his work put an end to the contract, so far as he is concerned ? It surely put a stop
This instruction, too, requires tbe court to tell tbe jury that tbe Railroad Company cannot retain tbe ten per cent, on the monthly estimates, (for there was by tbe testimony before tbe court no other money in tbe hands of tbe company, in any manner due or belonging to Ryan & Co., on account of this contract, except this ten per eentage,) unless tbe Railroad Company shall prove that tbe contract was forfeited exactly in tbe manner provided therein.
A few plain principles can settle this case. Ryan & Co. have been sued by Reagan, and tbe Pacific Railroad Company garnished as a debtor of Ryan & Co. Now, tbe testimony discloses a contract on tbe part of Ryan & Co. with tbe garnishee to do certain work on tbe railroad, according to a special agreement, embracing various stipulations. Now, unless tbe Pacific Railroad Company are liable to Ryan & Co., and unless tbe facts in proof would sustain an action in favor of Ryan & Co., against the Railroad Company, that company cannot be liable when garnished as a debtor of Ryan & Co. ; and tbe proof is on tbe part of those who would subject tbe company to this proceeding.
There is nothing worthy of notice on tbe record, in regard to tbe offer of Powers to go on with tbe contract, if tbe company would alter tbe terms of it, by advancing to bim tbe ten per cent, retained by virtue of tbe original contract. He bad a right to complete the contract; not to change it.
Tbe judgment of the court below is reversed, and tbe cause remanded ; tbe other judges concurring.