Raytone Plumbing Specialities, Inc. v. Sano Construction Corp.Raytone Plumbing Specialities, Inc. v. Sano Construction Corp.
The plaintiff‘s complaint, verified by its attorney, alleges that the defendant failed to pay for plumbing services the plaintiff rendered to the defendant and asserts causes of action, inter alia, to recover damages pursuant to
In an action involving, inter alia, the “performing of labor or services,”
Here, the plaintiff annexed two invoices to its complaint, listing approximately 50 different addresses, with amounts due beside each listed address and reflecting a total outstanding balance due of $152,134.60. The complaint asserts, but the invoices do not reflect, that this work was performed over a period of approximately two years. Despite the outstanding sum reflected on the invoices, the complaint seeks damages on the first cause of action in the sum of $158,584.50.
“To meet the requirements of
The plaintiff also failed to meet its prima facie burden with respect to the second cause of action, which sought to recover on an account stated. The plaintiff alleges that an account was stated in the sum of $158,584.60, but the only invoices before the Supreme Court reflect an outstanding balance of $152,134.60. The plaintiff failed to demonstrate that the parties came to “an agreement with respect to the amount of the balance due” (Cameron Eng‘g & Assoc., LLP v JMS Architect & Planner, P.C., 75 AD3d 488, 489 [2010]), an essential element of an account stated (see Landau v Weissman, 78 AD3d 661 [2010]). Where, as here, there are no facts showing that the defendant retained the billing statements for an unreasonable period of time without objecting to them, the plaintiff failed to meet its prima facie burden (see American Express Centurion Bank v Cutler, 81 AD3d 761 [2011]).
The plaintiff‘s remaining contentions are without merit.
Accordingly, the Supreme Court properly denied the plaintiff‘s