Case Information
*1 Before STEWART, Chief Judge, and REAVLEY, and DAVIS, Circuit Judges.
REAVLEY, Circuit Judge:
This case reaches the Fifth Circuit for a second time. And, though the litigation has been pending for five years, we are asked for a second time to reverse an order denying a motion to compel arbitration. We previously found that defendant National Oilwell Varco Norway (“NOV Norway”) had a contractual right to arbitration before the International Chamber of Commerce (“ICC”). See generally Al Rushaid v. Nat’l Oilwell Varco, Inc. , 757 F.3d 416 (5th Cir. 2014). The remaining defendants, nonsignatories to that agreement, contend that they, too, are entitled to arbitration.
I.
Our prior opinion sets forth the relevant facts of this case.
See Al
Rushaid
,
Despite the NOV LP arbitration clause, the defendants did not seek to compel arbitration and instead proceeded to discovery and set a trial date. When NOV Norway was served, however, it promptly sought to compel arbitration based on a price quotation issued by NOV Norway to ARPD. The district court denied the motion, ruling that the NOV Norway arbitration clause was not a part of the parties’ agreement and that, in any event, NOV Norway had waived its right to arbitrate. Id. On appeal, we disagreed on both counts but expressly noted that our decision did “not, however, necessarily require the district court to compel any of the other parties to arbitrate their dispute or to stay proceedings.” Id. at 424.
On remand, the defendants jointly moved to compel arbitration. The motion was based on both arbitration clauses—the one found in NOV Norway’s price quotation and the one found in NOV LP’s price quotation. While NOV LP asserted an arbitration clause to which it was a signatory, the other defendants (hereinafter, the “Nonsignatory Defendants”) conceded they are not signatories to either arbitration clause. With respect to the NOV Norway arbitration clause, all defendants (including NOV LP) argued an entitlement to arbitration based on principles of equitable estoppel. With respect to the NOV LP arbitration clause, which was asserted in the alternative, NOV LP asserted a contractual right to arbitration while the Nonsignatory Defendants again relied on equitable estoppel. [1]
The district court rejected all arguments based on equitable estoppel, but found that NOV LP was contractually entitled to arbitration. Because that arbitration clause did not specify a forum, the district court ordered arbitration within the Southern District of Texas. All defendants have appealed. To sum up, if left undisturbed, the proceedings have fragmented. Claims against NOV Norway will be arbitrated before the ICC. Claims against NOV LP will be arbitrated within the Southern District of Texas. And claims against the Nonsignatory Defendants will be litigated in Texas state court.
II.
The district court’s order was interlocutory in nature, and our appellate jurisdiction is therefore circumscribed. We may review orders denying the compulsion of arbitration and, therefore, undisputedly have jurisdiction over the appeal as it pertains to the Nonsignatory Defendants. 9 U.S.C. § 16(a)(1). NOV LP, however, is another matter. Its motion to compel arbitration was granted. We do not have jurisdiction to review interlocutory orders compelling arbitration. 9 U.S.C. § 16(b)(3). Appellants, however, point out that the order granting NOV LP’s motion to compel arbitration within the Southern District of Texas also denied NOV LP’s motion to compel arbitration before the ICC. Given these circumstances, Appellants argue we have appellate jurisdiction under section 16 of the Federal Arbitration Act (“FAA”) or the collateral order doctrine. Alternatively, Appellants contend we should exercise pendent appellate jurisdiction over the matter.
The FAA functions “to move the parties to an arbitrable dispute out of
court and into arbitration as quickly and easily as possible” and represents a
“statutory policy of rapid and unobstructed enforcement of arbitration
agreements.”
Moses H. Cone Mem’l Hosp. v. Mercury Constr. Corp.
, 460 U.S.
1, 22,
In light of the foregoing, the Second Circuit has held that “a party cannot
appeal a district court’s order unless, at the end of the day, the parties are
forced to settle their dispute other than by arbitration.”
Augustea Impb Et
Salvataggi v. Mitsubishi Corp.
, 126 F.3d 95, 99 (2d Cir. 1997). Under
circumstances somewhat similar to those present here, the Ninth Circuit
agreed.
See Bushley v. Credit Suisse First Boston
,
Here, as in Bushley , we are asked to consider the appeal of a party whose motion to compel was granted, “albeit not in the ‘first-choice’” forum. See id. Consistent with the purpose of Section 16 and with every circuit that has considered this issue, we hold that Section 16 forbids appellate review.
We also lack jurisdiction under the collateral order doctrine. The
collateral order doctrine is a “‘narrow’ exception” that “should stay that way
and never be allowed to swallow the general rule.”
Digital Equip. Corp. v.
Desktop Direct, Inc
.,
For similar reasons, without deciding whether pendent appellate
jurisdiction may properly be exercised in this context, we decline to do so.
Cf.
IDS Life Ins. Co. v. SunAmerica, Inc.
,
We lack jurisdiction over NOV LP’s appeal. Additionally, despite having nothing to appeal, NOV Norway was listed as an appellant within the defendants’ notice of appeal. The appeals brought by NOV LP and NOV Norway must be dismissed.
III.
Generally, we review de novo the denial of a motion to compel arbitration. Auto Parts Mfg. Miss., Inc. v. King Constr. of Houston, LLC , 782 F.3d 186, 196 (5th Cir. 2015). “We review for abuse of discretion a district court’s determination of whether equitable estoppel may be invoked to compel arbitration.” Id. A decision based on a mistake of law or on a clearly erroneous assessment of the evidence constitutes an abuse of discretion. Id.
“[U]nder the FAA, traditional principles of state law may allow an
arbitration contract to be enforced by or against nonparties to the contract
through a number of state-contract-law theories, including equitable estoppel.”
Crawford Prof’l Drugs, Inc. v. CVS Caremark Corp.
,
Appellants advance both “concerted misconduct” estoppel and “direct
benefit” estoppel. The concerted misconduct estoppel theory is foreclosed by
In
re Merrill Lynch Trust
and
G.T. Leach Builders
.
See Glassell Producing Co. v.
Jared Res., Ltd
.,
We “look to the pleadings to determine the nature of [the] claims.”
G.T.
Leach Builders, LLC
,
IV.
Appellants warn that permitting the district court’s decision to stand
means plaintiffs’ claims will “be split into three proceedings—two arbitrations
and one state court proceeding, an outcome the NOV Parties have tried to avoid
since the outset of the case.” This is an inevitable and permissible consequence
where one of multiple defendants asserts a right to arbitrate.
See Dean Witter
Reynolds, Inc. v. Byrd
,
The appeals brought by NOV LP and NOV Norway are DISMISSED, and the district court’s order is AFFIRMED. Accordingly, the claims against defendants National Oilwell Varco, Inc.; NOW Oilfield Services, LLC; Grant Prideco, LP; and Grant Prideco Holding, LLC, are REMANDED to the District Court sitting in Harris County, Texas, 165th Judicial District.
Notes
[1] Certain of the Nonsignatory Defendants also argued that, by its terms, NOV LP’s arbitration clause applied to them. That argument was rejected by the district court and has not been advanced on appeal.
[2] On appeal, defendants claim for the first time that “a question exists as to whether
international commercial arbitration agreements should be” analyzed under federal common
law rather than state law. Having not been raised before the district court, that argument
is waived.
See NCDR, L.L.C. v. Mauze & Bagby, P.L.L.C.
,
[3] We do not overlook the plaintiffs’ breach of contract claims. To the extent the
plaintiffs seek to hold the defendants liable for their respective alleged breaches of the
respective contracts, the signatory/nonsignatory distinction ably sorts the claims. The
Nonsignatory Defendants are not allegedly in breach of the NOV Norway or NOV LP
agreements. Rather, they are allegedly in breach of their own separate agreements.
See G.T.
Leach Builders, LLC
,
[4] On appeal, Appellants contend for the first time that the claims against National Oilwell Varco, Inc. and NOW Oilfield Services, LLC are subject to arbitration under the NOV LP contract because the claims “are derivative of, and rest on the identical allegations asserted against . . . NOV LP.” This argument was not raised before the district court and has therefore been waived.
