delivered the opinion of the court:
This аppeal arose from the petition, filed by petitioner, Rapid Settlements, Ltd., pursuant to the Structured Settlement Protection Act (Act) (215 ILCS 153/1 et seq. (West 2004)), for court approval of a transfer of a portion of Mary Foreman’s structured settlement payment rights. Respondents, Symetra Life Insurance Company and Symetra Assigned Benefits Service Company (Symetra, collectively), the annuity issuer and the structured settlement obligоr, respectively, filed an objection to the petition for approval. The trial court approved the transfer but struck from the transfer agreement paragraph 10, which had granted Rapid Settlements a right of first refusal on any future transfers of the remaining periodic payments not otherwise transferred by Foreman. On appeal, Symetra contends that the trial court erred in approving the transfer. Rapid Sеttlements cross-appeals and argues that the trial court erred by striking paragraph 10 from the transfer agreement. We reverse the trial court’s judgment approving the transfer. Because we reverse, we need not address the cross-appeal.
BACKGROUND
The structured settlement at issue derives from a settlement agreement and release entered into on or about February 8, 1996, between Foreman, administrator of the estate of Dashawna Foreman, and Illinois State Medical Insurance Services, Inc., as insurer for and on behalf of Warren Babcock, Jr., M.D., for the purpose of settling a wrongful death action in the circuit court of Winnebago County. The settlement agreement provides that Foreman was to receive $121,445 at the time of settlement, and the following future periodic payments: $1,000 per month, “beginning on December 1, 1996[,] through June 1, 2005, all 103 payments being guaranteed certain,” and $789 per month, “beginning on July 1, 2005, guaranteed for 10 years certain, increasing at 3% annually, and payable thereafter for the life of Mary Foreman.” The settlement agreement further provides that “[Foreman] acknowledges that the Periodic Payments described in Section 2 cannot be accelerated, deferred, increased or decreased by [her]; nor shall [she] have the power to sell, mortgage, encumber, or anticipate the Periodic Payments, or any part thereof, by assignment or otherwise.” The settlement agreement also states that it “shall be construed and interpreted in accordance with the law of the State of Illinois.”
In order to fulfill and discharge its obligation to make the periodic payments to Foreman under the settlement agreement, the insurer made a qualified assignment of its liability to make the periodic payments, to Safeco Assigned Benefits Service Company, n/k/a Symetra Assigned Benefits Service Company. In order to fulfill its obligations to Foreman under the structured settlement, Safeco purchased an annuity from Safeco Life Insurance Company, n/k/a Symetra Life Insurance Company, naming Foreman as annuitant. Under this annuity, Symetra Life makes the periodic payments required under the structured settlement agreement directly to Foreman, although Symetra Assigned Benefits Service is still obligated to make the periodic payments should Symetra Life fail to do so.
Foreman contacted Rapid Settlements, seeking to transfer a portion of her structured settlement payment rights for a lump-sum payment. On August 9, 2004, Foreman executed an amended transfer agreement under which she agreеd to transfer to Rapid Settlements, its successors and/or assigns, the assigned payments in exchange for a lump-sum payment of $10,500.
On September 10, 2004, Rapid Settlements filed in the circuit court of Winnebago County a petition for approval of the transfer of the structured settlement payment rights. Subject to the trial court’s approval, Foreman agreed to transfer to Rapid Settlements, its successors and/or assigns, the follоwing periodic payments: “Six (6) monthly payments each in the amount of $942.11 beginning on January 1, 2012[,] through and including June 1, 2012; and Thirty-Six (36) monthly payments each in the amount of $970.37, both sets of payments subject to a 3% annual increase each July 1st, beginning on July 1, 2012[,] through and including June 1, 2015, ultimately increasing to $1,029.47 per month.” Foreman signed a written waiver indicating that she chose to waive seeking independent professional advice regarding the financial, legal, and tax implications of the transfer. All interested parties received a notice and a copy of the petition for approval.
On October 12, 2004, Symetra filed an objection to the petition. Symetra argued that the transfer would place unacceptable burdens upon it. Symetra also argued that the transfer failed to comply with the provisions of the Act. Of relevance to this appeal, Symetra contended that under the Act a proposed transfer of settlement rights is not authorized if it would contravene any law. See 215 ILCS 153/ 30(e) (West 2004). Symetra argued that the proposed transfer would contravene Illinois contract law because the antiassignment clause of the settlement agreement expressly prohibits Foreman from entering into a transfer agreement such as the one with Rapid Settlements.
On October 21, 2004, the сourt issued a memorandum of decision holding that the transfer agreement was enforceable and complied with the Act and other applicable law in all respects, with the exception of paragraph 10 concerning the right of first refusal. Accordingly, the court severed paragraph 10 from the transfer agreement. As to the enforceability of the antiassignment clause in the structured settlement agreement, the court first noted that it was cognizant that such clauses are looked upon with disfavor and should be narrowly interpreted. Next, relying on a rule cited in In re Nitz,
On February 25, 2005, the trial court denied Symetra’s motion for reconsideration. An оrder was thereafter entered on June 22, 2005, approving the transfer of the structured settlement payment rights from Foreman to Rapid Settlements but striking paragraph 10 of the transfer agreement regarding the right of first refusal. Symetra timely appealed. Rapid Settlements timely cross-appealed.
ANALYSIS
In support of its first contention, that the trial court erred in approving the transfer, Symetra asserts that the assignment of the structured settlement payment rights is prohibited by the unambiguous terms of the underlying settlement agreement, as well as by the qualified assignment and annuity contracts. We agree.
“Construing the language of a contract is a question of law, and we review a trial court’s determination of a contract de novo.” Nitz,
The parties do not dispute that the structured settlement agreement in this case contains an antiassignment provision. The plain language of the settlement agreement prohibits all assignments. Paragraph 3 of the settlement agreement specifically states that Foreman does not have “the power to sell, mortgage, encumber, or anticipate the [payments], or any part thereof, by assignment or otherwise.” (Emphasis added.) Moreover, similar to the settlement agreement, the qualified assignment and annuity contracts prohibit assignments of the periodic payments. The qualified assignment contract provides that none of the payments “may be accelerated, deferred, increased or decreased and may not be anticipated, sold, assigned or encumbered.” The annuity contract similarly provides that no payment “may be accelerated, deferred, incrеased, or decreased, or anticipated, sold, assigned, or encumbered in any manner by the annuitant (or either joint annuitant) or any other recipient of the payment.”
However, relying on Nitz, the trial court did not enforce the anti-assignment clause of the settlement agreement, determining that the antiassignment provision was ineffective to prevent assignment because the payment of money was the only obligation remaining and the tax treatment was immaterial. Rapid Settlements adds in support that restraints on alienation, as found in the settlement agreement and the qualified assignment and annuity contracts, were included to preserve the tax-exempt character of the transaction. Rapid Settlements asserts that because that status is not protected by federal and Illinois law, the trial court correctly ignored thе antiassignment provision. We disagree for the following reasons.
First, the trial court incorrectly concluded that we enforced the antiassignment clause in Nitz solely because the transfer of payments could have altered the parties’ favorable tax treatment. A review of Nitz as well as other decisions addressing antiassignment provisions shows that the language of the agreements between the parties was the main basis for enforcing the provisions.
Nitz entered into an agreement with Safeco to settle a negligence action. The settlement agreement gave Nitz a life annuity and expressly stated that Nitz had no power to sell, mortgage, or encumber his payments or any part thereof, by assignment or otherwise. Nitz commenced an action seeking court approval to assign the future payments in an annuity agreement. Finding that such an antiassignment provision was enforceable as there was no public policy against it, we held that Nitz’s attempted assignment of future payments was invalid based on the clear and unambiguous language of the settlement agreement. Nitz,
In reaching our conclusion, we relied on the Henderson and Green cases. In Henderson, the court concluded that, although Illinois law disfavored antiassignment clauses in contracts, the plain language of the settlement agreement clearly indicated that the parties intended to forbid Henderson from assigning his periodic payments. Henderson,
Nitz asserted that we should follow the long-held rule that anti-assignment provisions are ineffective to prevent assignment where the only obligation remaining is the payment of money and the money is absolutely due to the debtor, as in that case. Nitz,
Contrary to the trial court’s finding here, the tax issue was not the only basis for our decision in Nitz. The case was not resolved solely on whether any adverse tax consequences existed. We first examined the language of the settlement agreement itself and determined that the parties intended to restrict assignments, then we found an additional reason for finding the assignment void. We determined also that there were potential tax ramifications if assignment were allowed. Thus, Nitz does not stand for the proposition that if favorable tax treatment is lacking, a trial court should ignore the parties’ clear intent against assignment under the language of the settlement agreement, and we will not endorse such a holding.
Rapid Settlements argues that the Victims of Terrorism Tax Relief Act of 2001 (Pub. L. No. 107 — 134, 115 Stat. 2427 (to be codified at 26 U.S.C. § 5891(b)(2)(A) (2006))) invalidates the antiassignment provision because it eliminates an obligor’s concerns about potential tax liability when an obligee attempts to assign a structured settlement agreement. The Victims of Terrorism Tax Reliеf Act only specifies what tax treatment certain kinds of structured settlements will be afforded; it leaves to the individual states the question of assignability. The clear and unambiguous language of the settlement agreement controls our analysis here.
Rapid Settlements argues that the new version of the Act (215 ILCS 153/1 et seq. (West 2004)) allows Illinois courts to approve transfers of structured settlement payment rights despite antiassignment provisions in structured settlement agreements. We disagree.
In In re Shaffer,
Like the former version, the current Act does not guаrantee a payee any right to transfer payments merely because the trial court finds that the elements of the Act have been satisfied. See 215 ILCS 153/15(1), (3) (West 2004). “Where a structured settlement agreement does not permit the payments to be assigned, the [trial] court’s authority to act on a petition seeking approval of the assignment of payments under such an agreement is not invoked ***.” Nitz,
We also reject Rapid Settlements’ application of section 322 of the Restatement (Second) of Contracts (Restatement (Second) of Contracts § 322 (1981)) to the facts of this case. Specifically, section 322, which Rapid Settlements misquotes by adding language that does not exist, provides in relevant part:
“(1) Unless the circumstances indicate the contrary, a contract term prohibiting assignment of ‘the contract’ bars only the delegation to an assignee of the performance by the assignor of a duty or condition.
(2) A contract term prohibiting assignment of rights under the contract, unless a different intention is manifested,
% ¿fi i\i
(c) is for the benefit of the obligor, and does not prevent the assignee from acquiring rights against the assignor or the obligor from disсharging his duty as if there were no such prohibition.” (Emphasis added.) Restatement (Second) of Contracts §§ 322(1), (2)(c) (1981).
Section 322(1) limits contract terms that prohibit assignment of the contract as a whole by restricting the prohibition against assignment only to performance of specific duties or conditions under the contract, and only in cases in which the circumstances do not “indicate the contrary.” In this case, the antiassignment prоvision is very specific as it expressly prohibits the payee’s right to assign the payments. Section 322(2)(c) does not restrict enforcement of antiassignment provisions in those cases where the parties’ intentions to enforce the provisions are manifest.
Furthermore, the antiassignment provision of the settlement agreement benefits Foreman by assuring her of a continuing cushion of income, preventing her from “binging away” thе asset and effectively becoming indigent. See Nitz,
In passing, we observe that by our holding we may be enforcing a transaction that will place Foreman in significantly greater financial need today. However, Foreman freely made the agreement that she seeks to avoid now. Absent a violation of public policy, we will not approve the voiding of unambiguous, bargained-for contract terms.
Based upon the foregoing, because the structured settlement agreement in this case contained an enforceable antiassignment provision, the Act does not apply and the petition must be dismissed. We therefore reverse the order of the trial сourt and remand the cause to the trial court for the entry of an order dismissing Rapid Settlements’ petition. Further, based on our decision, we need not address Symetra’s argument that the proposed transfer was not an effective transfer under the provisions of the Act or address Rapid Settlements’ cross-appeal that the trial court erred in striking paragraph 10 of the transfer agreement regarding Rapid Settlements’ right of first refusal.
The judgment of the circuit court of Winnebago County is reversed, and the cause is remanded for the entry of an order dismissing the petition.
Reversed and remanded with instructions.
BOWMAN and HUTCHINSON, JJ., concur.