59 Mo. App. 6 | Mo. Ct. App. | 1894
This is an action to enforce the lien of a material man for the value of giant powder, alleged to have been furnished to, and used by, contractors in the construction of a specified section of the deferfdant’s railroad. The court sustained a demurrer to the plaintiff’s evidence, and it is of this that the plaintiff complains on this appeal.
The contentions are, that under the undisputed evidence the plaintiff was entitled to a judgment enforcing its lien, and, also, to a personal judgment against the defendant for the amount of the claim. "We will notice the latter proposition first. Section 2565 of the Revised Statutes of 1889 reads: “Whenever any contractor for the construction of any part of railroad which is in process of construction, or any contractor for. the repairing of any part of a railroad, shall be indebted to any subcontractor or laborer, or
In the cáse at bar the notice above specified was served on T. A. Miller, the general manager of the road. There was no proof that Miller had the immediate supervision of the section of the road where it is claimed the materials were used, and for this reason
In support of the judgment denying the plaintiff’s right to a lien, it is urged that giant powder is not a lienable article, and that it must be considered a part of the “plant” of the contractor. It is further contended that there is a total lack of evidence tending to show that the use of powder was provided for in the contract, or was necessary for the work.
There has been no construction of our statute which would throw any particular light on the first proposition. The question has been decided in other states under like statutes, and the conclusions reached are opposed to the construction here contended for. The statute in this state (R. S. 1889, sec. 6741) reads: “All persons who shall do any work or labor in constructing or improving the roadbed, rolling stock, station houses, depots, bridges or culverts of any railroad company, incorporated under the laws of this state, or owning or operating a railroad within this state, and all persons who shall furnish ties, fuel, bridges or material to such railroad company, shall have, for the work done and labor performed and for the material furnished, alien,” etc.
Without subscribing to all that the learned judge said in the foregoing opinion, we think that both on reason and authority the conclusion reached on the question in judgment was right. This court in the case of Knapp v. Railroad, 6 Mo. App. 205, made the statement incidentally that a material man was not entitled to a lien, unless the materials furnished were “actually incorporated,” in the structure. Under , this statement of the law it would be difficult, in our opinion , to sustain the conclusion in the Oregon case. In a subsequent case, however, the court modified its former opinion and held that materials provided for in the contract and necessary for the work might, under certain circumstances, be covered by a mechanic’s lien, though they may not have been actually incorporated in the structure. Andrews v. Railroad, 16 Mo. App. 299.
The question under consideration has been before the New York courts. Hazard Powder Co. v. Byrnes, 21 How. Pr., 189. The statute of New York provides, that any person who shall, in conformity with the terms of the contract between the owner and contractor, furnish to the contractor any materials in building any house or building shall have alien on the improvement. In the case above cited the plaintiff claimed a lien for powder and fuses furnished the contractor for the purpose of blasting rock preparatory to laying the foundation walls for the defendant’s building. In delivering the opinion Judge Hilton said: “I think that the fair and reasonable interpretation of such language is, that the right of lien extends to all such materials as ordinarily enter into, or are used in the construction of,
In Colorado there is a lien statute applicable particularly to mines, wherein it is provided that any person .furnishing “timber or other materials to be used in or about the mine, shall have a lien therefor.” In Keystone Mining Co. v. Gallagher, 5 Col. 23, one of the claimants had furnished powder, steel and candles, which were used in working the mine, and for which he claimed a lien on the mine. In disposing of the objection made to this claim the court said; “It is objected that the decree as to Boettcher’s claim is erroneous, because the articles furnished by him were not of the character comprehended by the lien law, specifying ‘timber or other materials to be used in or about the mine.’ The testimony shows that the articles furnished were powder, steel and candles, for use of the mine. These articles are as clearly within the meaning of the statute as anything we can conceive of essential to the working of amine.”
The rule to be deduced from, the foregoing authorities is that, in order to maintain a lien for materials furnished, it is not necessary in all cases that such materials should actually have gone into the structure
It was admitted by the defendant that the persons to whom the plaintiff furnished the powder were subcontractors, and that they did the necessary work in preparing a portion of the defendant’s roadway for the reception of the ties and iron. Under this' admission it was not necessary for the plaintiff to show that the contract specially provided for the use of powder, or that its use was necessary in the construction of the road. We know by common experience that the use of powder is generally necessary in making excavations for railroads; hence the right of the contractors, under their contract, to purchase it for that purpose is implied from the very nature of the work. Phillips on Llechanies’ Liens [3 Ed.], section 161. In addition the plaintiff proved the sale and delivery of the powder, and that it was actually used in the construction of the
Under an order of this court the clerk of the circuit court has sent up the lien and original papers in the cause. These show that the lien was filed, and action thereon commenced within the time prescribed by statute. This answers the objections to the plaintiff’s abstract of the evidence on that score.
Objection is made in reference to the sufficiency of the lien paper, but, as we are of the opinion that there is no merit in the objection, a discussion of it would be unprofitable.
Under the present record we are of the opinion that the demurrer to the evidence as to the enforcement of the lien ought to have been overruled. For this reason the judgment of the circuit court sustaining it will have to be reversed, and the cause remanded for further proceedings.