86 Kan. 899 | Kan. | 1912
The opinion of the court was delivered by
This action was brought to re-re-leo ver $178 and to foreclose a mechanic’s lien. De-pendant Robert Rankin and the appellee, Hannibal. ¡Rankin, are father and son. Both were plasterers by ¡trade and they worked together. About April 7, 1909,. ¡Robert Rankin entered into an agreement with the-Monarch Portland Cement Company to do plastering |ipon the buildings at the cement plant. The price was.
On October 11, 1909, Hannibal Rankin filed a mechanic’s lien and served proper notice. The action was begun November 5, 1909, praying judgment against both Robert Rankin and the cement company and for a foreclosure of the alleged mechanic’s lien. The answer contained a denial and a plea of payment on the part of the cement company. Robert Rankin did not answer or otherwise contest. At a trial which was had without a jury appellant made an objection to the introduction of any evidence on the ground that the petition did not state a cause of action, but it was] -overruled, and a demurrer to appellee’s testimony was also overruled. The court rendered judgment finding that Robert Rankin owed Hannibal Rankin $174 ano foreclosing the mechanic’s lien, from which judgmenl this appeal is taken.
The point first .made, that there was no allegatioi in the petition of a contract between the company ant the original contractor, is not good. It is expressly .alleged that the contractor entered into an agreemen with the company to plaster its buildings at twent; cents per square yard for outside work and ten cent per square yard for inside work, and that the cor
But it is contended that appellee did not show definitely the class to which he belonged — did not show clearly by his petition or lien whether he was claiming as a laborer or as a subcontractor. There is no room for doubt as to his relation to the owner and contractor or his right in the premises. He stated that he performed labor under a contract with the contractor. His was a claim for labor furnished to a contractor and is therefore a labor lien. Although having been furnished under a contract it is in a sense a subcontract. Strictly speaking, a subcontractor is one who takes from the contractor a specified part of the work, but a day laborer who works under an agreement with ■ the contractor is in one view a subcontractor. The statute provides that “any person who' shall furnish any such material or perform such labor under a subcontract with the contractor, or as an artisan or day laborer in the employ of such contractor, may obtain a lien upon such land,” etc. (Civ. Code, § 651; see, also, Nixon v. Cydon Lodge, 56 Kan. 298, 43 Pac. 236.) Whatever may be the proper classification of the ap-pellee, it is clear that no one could have been misled by his statements in either the lien or the petition. In both he alleged that he performed labor by the day under a contract with the contractor, and if he had followed this statement with another that he claimed a lien as a subcontractor it would not have impaired the validity of the lien, and proof that he worked for the contractor' as an artisan or day laborer could not have been regarded as a variance. Whether regarded as one or the other the proof would necessarily be the same, and, besides, no variance is to be deemed material
A question is raised as to the age of appellee when the work was done, but the evidence, although somewhat obscure, is sufficient to uphold the finding included in the general verdict that he had reached majority when the services were performed and was entitled to recover compensation for them.
The judgment is affirmed.