*401 OPINION
Opinion by
Randy and Barbara Gentry appeal the trial court’s judgment in favor of Squires Construction, Inc. and against the Gentrys on their counter-claims against Squires Construction and third-party claims against Lewis Almon Squires. The trial court awarded Squires Construction its reasonable costs for labor and materials under the theory of quantum meruit in the amount of $16,134 and ordered each party to bear its own costs and attorneys’ fees.
The Gentrys raise fourteen issues that generally argue four points: (1) the trial court erred when it concluded Squires Construction was entitled to be paid for work done under the theory of quantum merit, the Gentrys claims were preempted by the Texas Residential Construction Liability Act (RCLA), and the Gentrys were not entitled to attorneys’ fees; (2) the evidence was legally and factually insufficient to support the trial court’s finding that Squires Construction had made a reasonable settlement offer and the evidence required the trial court to find that Squires Construction filed a fraudulent lien; (3) the trial court abused its discretion when it failed to rescind the contract; and (4) the trial court erred when it failed to award the Gentrys damages and statutory penalties on their claims.
Squires Construction cross-appealed. In Squires Construction’s sole issue, it argues the trial court erred when it concluded that it was not entitled to attorneys’ fees.
We conclude the trial court did not err when it concluded Squires Construction was entitled to be paid for work done under the theory of quantum meruit and the Gentrys were not entitled to attorneys’ fees. However, the trial court erred when it concluded the Gentrys’ claims were preempted by the RCLA and Squires Construction was not entitled to attorneys’ fees. We also conclude the evidence is legally and factually sufficient to support the trial court’s findings of fact. The trial court’s judgment is affirmed, in part, and reversed and remanded, in part.
I. FACTUAL AND PROCEDURAL BACKGROUND
The Gentrys contacted Squires Construction about building a house. The Gen-trys showed Squires Construction a photograph of what they wanted their new home to look like, but they did not have any blueprints. Squires Construction told the Gentrys it could build the home based on its own drawings because the Gentrys wanted to save money. Then, the Gentrys entered into a written contract with Squires Construction. Under the contract, the Gentrys were going to purchase several items and do some of the work themselves. The parties agreed that Squires Construction would be paid through the lender by submitting draw requests.
When Squires Construction made its final draw request to the lender, the Gen-trys refused the payment. The Gentrys complained of numerous construction defects, including the first floor of their home was built with eight foot ceilings instead of ten foot ceilings as called for by the building plans, problems with the front porch, and leaking windows that were not caulked.
Squires Construction sued the Gentrys for breach of contract and foreclosure of the hen, or in the alternative quantum meruit. The Gentrys filed counter-claims against Squires Construction and third-party claims against Squires alleging breach of contract, breach of implied warranty, violations of the DTPA, and fraud, or in the alternative seeking rescission of the contract. After the Gentrys filed their *402 counter- and third-party claims, Squires Construction inspected the property and made a settlement offer, which was rejected.
The case was tried before the court. After the trial, the trial court rendered judgment in favor of Squires Construction under the alternative theory of quantum meruit in the amount of $16,134. All relief requested by the Gentrys was denied. Squires Construction requested findings of fact and conclusions of law and both Squires Construction and the Gentrys filed motions for new trial. The trial court issued findings of fact and conclusions of law and the motions for new trial were overruled by operation of law.
II. CONCLUSIONS OF LAW
In issues one, two, three, ten, twelve, and thirteen, the Gentrys argue the trial court erred when it concluded: (1) Squires Construction was entitled to be paid for work done under the theory of quantum merit after finding it did not substantially comply with the contract; (2) their claims against Squires Construction and Squires were preempted by the RCLA 1 ; and (3) they were not entitled to attorneys’ fees on their breach of contract and fraud claims. In Squires Construction’s cross-appeal, it argues the trial court erred when it concluded they were not entitled to attorneys’ fees. 2
A. Standard of Review
An appellate court conducts a de novo review of a trial court’s legal conclusions.
Ramirez v. Hariri,
B. Conclusion that Squire Construction Entitled to Recover Under Quantum Meruit
In their first and second issues, the Gen-trys argue the trial court erred when it concluded Squires Construction was entitled to be paid for work done under the theory of quantum meruit after finding it did not substantially comply with the contract. Squires Construction responds that quantum meruit is a viable cause of action for a construction contractor who has not substantially performed the underlying contract.
1. Applicable Law
Quantum meruit is an equitable theory of recovery based on an implied agreement to pay for benefits received.
Heldenfels Bros., Inc. v. City of Corpus Christi,
2. Application of the Law to the Facts
The Gentrys challenge the trial court’s third conclusion of law, which states:
3) [Squires Construction] is entitled to be paid for work done on a quantum meruit basis.
The Gentrys contend the trial court’s findings of fact do not support the third conclusion of law. They point to the following findings:
2) [Squires Construction’s] proposal to build [the Gentrys’] house (Plaintiffs Exhibit # 1), which was accepted by [the Gentrys], specified “The first floor will have 10' walls ...”
3) The undisputed testimony is that the first floor has 8 ft [sic] walls.
5) Although the testimony varies as to whether there was an agreement to change to 8 foot walls on the first floor, there is no dispute that no written alteration of the plans was ever executed.
6) [The Gentrys] did not waive the requirement of having 10 foot walls on the first floor.
7) [Squires Construction] did not substantially comply with the contract.
The Gentrys and Squires Construction confuse the application of the doctrine of substantial compliance. It will not normally prohibit the implementation of the theory of quantum meruit. 3 Never *404 theless, we review the trial court’s conclusions of law de novo.
Although the trial court found that Squires Construction failed to substantially comply with the contract, there was evidence that it partially performed under the contract and the Gentrys accepted and retained the benefits of Squires Construction’s partial performance. Accordingly, we conclude the trial court did not err when it concluded Squires Construction was entitled to be paid its costs for labor and materials under the theory of quantum meruit.
The Gentrys’ first and second issues are decided against them. The trial court’s judgment is affirmed, in part, with respect to its third conclusion of law determining that Squires Construction is entitled to be paid for work done on a quantum meruit basis.
C. Preemption Under the RCLA
In their third issue, the Gentrys argue the trial court erred when it concluded their claims were preempted by the RCLA. Squires Construction and Squires respond that the trial court did not abuse its discretion because it found they complied with the “reasonable offer” provisions of the RCLA.
1. Applicable Law
The RCLA does not create a cause of action because it does not: (1) provide a complete structure for liability or (2) contain a description of what conduct will result in liability or an express statement of the elements of a cause of action.
See
Tex. PROp.Code ANN. § 27.005 (Vernon 2000);
Sanders v. Construction Equity, Inc.,
The RCLA does not preempt the DTPA.
See Sanders,
The RCLA does not preempt and clearly authorizes suits for breach of contract or breach of warranty after the pre-suit requirements have been completed.
Sanders,
The RCLA does not preempt a fraud claim.
See Bruce v. Jim Walters Homes,
2. Application of the Law to the Facts
The Gentrys’ assertion that the trial court erred when it concluded their claims were preempted by the RCLA appears to challenge the trial court’s first and second conclusions of law, which state:
1) [The Gentrys] claims under the Deceptive Trade Practices Act are preempted by the Residential Construction Liability Act.
2) Since [the Gentrys] are not entitled to damages other than the cost of repairs, they are not entitled to retain other monies held as a result of the last construction draw.
First, we must determine whether the trial court’s conclusions of law are correct as a matter of law. The RCLA does not preempt the DTPA.
See Sanders,
Second, we must determine whether the trial court’s findings of fact support the judgment under a different legal theory. Because the trial court determined the DTPA was preempted by the RCLA, it did not try the claims so there are no findings of fact that may support the judgment against the Gentrys as to that cause of action. Accordingly, we conclude the trial court erred when it determined the Gentrys’ DTPA claims were preempted.
The Gentrys’ third issue is decided in their favor. The trial court’s judgment is reversed, in part, as to its conclusion that the Gentrys’ counter- and third-party DTPA claims are preempted and the case is remanded for a new trial on the Gen-trys’ counter- and third-party DTPA claims. Based on our resolution of the Gentrys’ third issue, we need not address their seventh and eighth issues that claim the trial court erred when it failed to award them recovery under the DTPA or their fourteenth issue that claims the trial court erred when it failed to award them attorneys’ fees based on their DTPA claims.
C. Attorneys’ Fees
In their tenth, twelfth, and thirteenth issues, the Gentrys argue the trial court erred when it concluded they were not entitled to attorneys’ fees on their breach of contract and fraud claims. In Squires Construction’s cross-appeal, it argues the trial court erred when it concluded they were not entitled to attorneys’ fees.
1. Applicable Law
A person may recover reasonable fees in addition to the amount of a valid claim and costs if the claim is for: (1) rendered services; (2) performed labor; (3) furnished material; (4) freight or express overcharges; (5) lost or damaged freight or express; (6) killed or injured stock; (7) a sworn account; or (8) an oral or written contract.
See
Tex. Civ. PRAC. & Rem.Code Ann. § 38.001. The statute also allows for the recovery of fees in a suit for quantum meruit.
See Weitzul Const. Inc. v. Outdoor Environs,
2. Application of the Law to the Facts
Both the Gentrys and Squires Construction challenge the trial court’s sixth conclusion of law, which states:
6) Neither side is entitled to attorneys fees or court costs.
First, we address the Gentrys’ claims that the trial court erred when it concluded they were not entitled to attorneys’ fees on their breach of contract and fraud claims. The trial court entered a judgment in favor of Squires Construction and against the Gentrys on their counter- and third-party claims against Squires Construction and Squires. Accordingly, the Gentrys were not entitled to recover
*407
attorneys’ fees because they did not prevail on their causes of action for which attorneys’ fees are recoverable.
See
Tex. Civ. Prac.
&
Rem.Code Ann. § 38.001;
Solis,
Second, we address Squires Construction’s issue on cross-appeal claiming the trial court erred when it concluded Squires Construction was not entitled to attorneys’ fees. The trial court’s sixth conclusion of law, which makes the legal conclusion that Squires Construction was not entitled to attorneys’ fees, is different from a trial court’s refusal to award attorneys’ fees, which is a fact issue left to the trial court’s discretion. Squires Construction prevailed on its quantum meruit claim and is allowed to recover attorneys’ fees under the statute.
See Weitzul,
Squires Construction’s sole issue on cross-appeal is decided in its favor. The trial court’s judgment is affirmed, in part, with respect to its sixth conclusion of law determining that the Gentrys were not entitled to attorneys’ fees and is reversed and remanded for further proceedings with respect to Squires Construction request for attorneys’ fees.
III. FINDINGS OF FACT
In issues four, five, and nine, the Gen-trys challenge the trial court’s findings of fact. The Gentrys argue: (1) the evidence was legally and factually insufficient to support the trial court’s finding that Squires Construction had made a reasonable settlement offer and (2) the evidence required the trial court to find that Squires Construction filed a fraudulent lien. Squires Construction responds that the Gentrys have not demonstrated the trial court abused its discretion and the trial court’s findings are supported by the evidence.
A. Standard of Review
Findings of fact in a case tried to the court have the same force and effect as jury findings.
See Central Forest S/C Partners, Ltd. v. Mundo-Mundo, Inc.,
When an appellant attacks the legal sufficiency of an adverse finding on an issue for which he did not have the burden of proof, he must demonstrate there is no evidence to support the adverse finding.
See Croucher v. Croucher,
When an appellant challenges the factual sufficiency of the evidence to support an adverse finding on which it did not have the burden of proof, appellant must demonstrate there is insufficient evidence to support the adverse finding.
Dallas County v. Holmes,
It is presumed that all fact findings needed to support the judgment were made by the trial court.
See Carter v. William Sommerville and Son, Inc.,
B. Applicable Law
The RCLA applies to “any action to recover damages resulting from a construction defect, except a claim for personal injury, survival, or wrongful death or for damages to goods.” Tex. Prop.Code Ann. § 27.002. Under the RCLA, an owner seeking damages arising from a construction defect must give the contractor written notice of the defect sixty days before filing suit.
Id.
§ 27.004(a). The purpose of the notice requirement is to encourage pre-suit negotiations to avoid the expense of litigation.
See Kimball,
Once the owner has given the contractor notice of his complaint, the contractor has: (1) thirty-five days to inspect and have inspected the property that is the subject *409 of the complaint and (2) forty-five days to make a written offer to settle the claim. See id. § 27.004(a), (b). However, if the complaint is asserted in a counterclaim, both the inspection and the settlement offer must be made within sixty days of the service of the counterclaim. Id. § 27.004(c).
The limitations on damages and defenses to liability provided in section 27.004 do not apply if the contractor fails to make a reasonable written settlement offer or otherwise cure the defect in the manner prescribed by the RCLA.
See id.
§ 27.004(g);
Homes v. Alwattari,
C. Application of the Law to the Facts
First, we review the Gentrys’ fourth and fifth issues which challenge the legal and factual sufficiency of the trial court’s findings of fact. The trial court made fifteen findings of fact. The Gentrys challenge the trial court’s eleventh finding of fact, which states:
11) [Squires Construction’s] offer of settlement (Plaintiffs Exhibit 19) was reasonable, and [the Gentrys] damages are limited under the Residential Construction Liability Act.
Specifically, the Gentrys claim the evidence is legally and factually insufficient to support this finding of fact because there was no evidence Squires Construction’s settlement offer was reasonable. Instead, the Gentrys assert the evidence shows Squire Construction’s settlement offer was unreasonable because the offer failed to address the discrepancy in the ceiling height and the failure to caulk the windows and it included a demand for payment.
Squires Construction’s settlement offer proposed to repair or complete twelve complained-of items in exchange for the amount requested in the final draw, attorneys’ fees, and settlement of all claims between them. The offer of settlement stated that, under the contract, the Gen-trys were responsible for the caulking and that, during the construction, the Gentrys agreed to proceed with the eight foot ceilings.
The Gentrys only challenge the trial court’s eleventh finding of fact. However, the trial court also found that “there is no practical way to remedy a variance in the height of the first floor walls.” Additionally, there was testimony that the Gentrys agreed to do all of the painting themselves and that, in the industry, painting includes caulking the windows. Further, there was evidence that the payment on which the settlement was conditioned was the amount of the final draw. It is clear the Gentrys’ challenge to finding of fact number eleven is actually an attack on the weight and credibility assigned to the evidence by the trial court. We will not substitute our judgment for that of the trier of fact as to the credibility of the witnesses. We conclude the evidence is legally and factually sufficient to support finding of fact number eleven.
Second, we review the Gentrys’ ninth issue which claims the evidence required the trial court to find that Squires Construction filed a fraudulent lien. After the trial, the trial court sent the parties a letter that listed eighteen findings of fact and stated that, based on those findings, it granted a judgment in favor of Squires
*410
Construction against the Gentrys. A month later, the trial court entered a judgment and ordered that Squires Construction should recover $16,134 from the Gen-trys and that each party was responsible for its own costs and attorneys’ fees. Squires Construction filed a request for the entry of findings of fact and conclusions of law conforming with those listed in the trial court’s letter. The trial court granted that request and made fifteen findings of fact and six conclusions of law that closely resembled those in its earlier letter. Neither the Gentrys, nor Squires Construction filed objections or requested additional or amended findings and conclusions. We conclude the Gentrys failure to request additional or amended findings or conclusions waives their right to complain on appeal about the presumed finding.
See Lewis,
The Gentrys’ fourth, fifth, and ninth issues are decided against them. The trial court’s judgment in affirmed, in part, with respect to finding of fact number eleven. Based on our resolution of the Gentrys’ ninth issue, we need not address their eleventh issue claiming the trial court erred when it failed to assess statutory penalties against Squires Construction for filing a fraudulent lien.
IV. RESCISSION OF THE CONTRACT
In their sixth issue, the Gentrys argue the trial court abused its discretion when it failed to rescind the contract. Specifically, the Gentrys argue Squires Construction breached the contract and they are unable to restore the status quo because of the unique facts of this case. Squires Construction responds that the trial court did not abuse its discretion because rescission would be an inequitable result.
A.Standard of Review
The equitable remedy of rescission is within the trial court’s discretion and need not be granted if inequitable to one party or the other.
Banker v. City of Groves,
B.Applicable Law
Rescission is an equitable remedy that operates to extinguish a contract that is legally valid but must be set aside due to fraud, mistake, or for some other reason to avoid unjust enrichment.
Martin v. Cadle Co.,
C.Application of the Law to the Facts
The trial court found that there was no practical or reasonable way to remedy the discrepancy in the ceiling height and the Gentrys did not prove that the house was of any less value due to the variance. Rescission would result in extreme prejudice to Squires Construction.
*411
The Gentrys rely on the Texas Commission of Appeals’s decision in
Kennedy
to support their position that, in this case, the need for the status quo relationship is obviated.
See Tex. Employers Ins. Ass’n v. Kennedy,
We conclude the trial court did not abuse its discretion in refusing to rescind the contract in this case. The Gentrys’ sixth issue is decided against them. The trial court’s judgment is affirmed, in part, with respect to the trial court’s refusal to rescind the contract between the Gentrys and Squires Construction.
V. CONCLUSION
The trial court did not err when it concluded Squires Construction was entitled to be paid for work done under the theory of quantum meruit and the Gentrys were not entitled to attorneys’ fees but erred when it concluded the Gentrys’ claims were preempted by the RCLA and Squires Construction was not entitled to attorneys’ fees. The evidence is legally and factually sufficient to support the trial court’s findings of fact. The trial court did not abuse its discretion in refusing to rescind the contract in this case.
The trial court’s judgment is affirmed, in part, and reversed and remanded, in part, for a trial on the Gentrys’ DTPA claims and further proceedings with respect to Squires Constructions’ request for attorneys’ fees.
Notes
. We note that in their appellate brief, the Gentrys do not specifically challenge the trial court’s respective conclusions of law in those precise words. However, it is clear from their arguments that is the nature of the error claimed.
. We note that in their appellate briefs, neither the Gentiys nor Squires Construction specifically challenge the trial court’s respective conclusion of law in those precise words. However, it is clear from their arguments that is the nature of the error claimed.
. The doctrine of substantial performance is a separate form of equitable relief from quantum meruit. The doctrine of substantial performance allows a contractor who has performed under the contract to sue on the contract.
Dobbins v. Redden,
Substantial performance is a condition precedent to a contractor’s right to bring a lawsuit on the contract.
Atkinson v. Jackson Bros.,
Under the doctrine of substantial performance, a contractor may recover the full contract price less the cost of remedying those defects that are remediable.
Vance,
The contractor bears the burden of proof under the doctrine of substantial performance.
See Vance,
