Lead Opinion
Opinion
Mаy an unlicensed contractor who worked on a project, but who is barred by statute from bringing an action for any recovery of compensation for work performed, nevertheless seek equitable indemnity from the subcontractors it hired to perform other work on the project, on the basis that such subcontract work was negligently performed? Such indemnity rights would stem from the fact that this unlicensed contractor at the same time was acting in the related capacity of developer of the overall project (i.e., its own contract principal), and is subject as a developer to strict liability for construction defects, in favor of the plaintiff-homeowners who purchased the units it built.
These issues arise in the following context: In these construction defect actions, consolidated on appeal, the trial court granted summary judgments in favor of numerous cross-defendant subcontractors and against cross-complainants, the developers/general contractors of the two separate condominium projects involved. The trial court found that since neither of the developers/general contractors possessed contractors’ licenses, their cross-complaints for equitable and implied contractual indemnity, contribution, negligence, and certain contract-based theories against the allegedly negligent subcontractors who worked on the projects were necessarily barred by Business and Professions Code
We conclude the trial court’s ruling in each consolidated case was erroneous because it disregarded the dual nature of the developers 7general
I
Factual and Procedural Background
A
Ranchwood Development
We need only sketch the facts regarding each condominium development (the project) in broad outline, since this appeal primarily presents questions of law for our resolution. Ranchwood Park is a 325-unit development in Spring Valley, developed by Ranchwood Communities Limited Partnership (RCLP), the developers/general contractors of the project. RCLP’s fellow cross-complainants were fellow owners and lenders on the project, Mission Hills Park Associates, CDS-RGK, Inc., MHP-1, Inc., and RSD Investment, who did not take an active role in the construction activities. RCLP never had a general contractor’s license during the 1981-1988 design and construction of the project; however, owner/lender MHP-1 obtained such a license in 1987. RCLP hired numerous subcontractors to work on the project.
In 1993 the homeowners association for the project (Ranchwood Park Property Owners Association) brought a construction defect action against RCLP and the other owner/lenders (RCLP et al.), alleging they as developers/contractors were liable for damages under strict liability, breach of express and implied warranties, negligence, nuisance, and negligent misrepresentation. RCLP et al. responded with their answer and cross-complaint against numerous subcontractors on the project, alleging they were entitled to equitable indemnity, implied contractual, express, and total indemnity,
B
Sickels, Kellogg Project
The scenario as to the other project, the 168-unit Ventana development in La Jolla, is similar. It was built in two phases, with general partnership Sickels, Kellogg Development Company (Sickels, Kellogg) serving as the developer/general contractor of the first phase of eighty-five homes, built between 1984 and 1986. Sickels, Kellogg had three general partners who are its fellow cross-complainants here: Raymarc Development, Inc. (Raymarc), Doublegood Industries, Inc., and CDS-Bay Area Development, Inc. (sometimes collectively Sickels, Kellogg). Raymarc became the developer/general contractor of 83 homes in the second phase, constructed from 1987-1989. None of these entities had general contractors’ licenses. They hired a licensed general contractor, Stouffer Construction Management (SCM), to supervise construction at the site of both phases. They also contracted for various trade work with the subcontractors who are now being sued in the cross-complaint.
Sickels, Kellogg was sued in 1993 as developer/contractor by the project’s homeowners association (La Jolla Alta Common Council No. 3) for construction defects on theories of strict liability, negligence, breach of implied warranty, and an action on a bond. It responded with its answer and cross-complaint on similar theories to RCLP’s: Equitable indemnity, implied contractual, express, and total indemnity, contribution, and recovery on theories of negligence, breach of contract and warranties, and declaratory relief regarding contractual duties.
C
Summary Judgment Motions
In both actions, the subcontractor cross-defendants individually and collectively brought motions for summary judgment on the cross-complaints, arguing that since the developers/general contractors RCLP and Sickels, Kеllogg were not licensed general contractors, their entire cross-complaints were barred by section 7031 as the equivalent of actions for compensation for work performed, pursuant to illegal contracts entered into by unlicensed persons. This argument was based on recent Supreme Court authority interpreting section 7031, Hydrotech Systems, Ltd. v. Oasis Waterpark (1991)
In opposition to the motions, both sets of cross-complainants argued section 7031 was not a bar to all causes of action, since the cross-complainants were potentially subject to strict liability and should be allowed to spread the loss among all negligent parties. They also claimed there had been substantial compliance with the licensing statute in various ways and, in any case, they were exempt from licensing requirements because they were “owner-builders” within the meaning of section 7044. They relied on legislative history to support their substantial compliance and owner-builder arguments. They further claimed not all cross-complainants (e.g., the owners and lenders, who did not actively participate as contractors) should be subject to the rule of section 7031, and not all the causes of action of the cross-complaint (e.g., the tort-based claims) should fall. Laches was asserted as an affirmative defense.
In reply, the various moving parties disputed that the substantial compliance and owner-builder arguments were viable under current statutory law or that an adequate showing of same had been made. They reiterated that the cross-complaints effectively sought “compensation” for work and were barred under Hydrotech. The trial court аgreed and granted summary judgment dismissing the cross-complaints. The orders recited that under Hydro-tech, the statutory term “compensation” in section 7031 should be interpreted broadly and should apply to the entire cross-complaint as a matter of law. The court found no substantial compliance had been shown and no exemption from section 7031’s requirements was available under section 7044 (applicable to owner-builders). The court found the cross-complainants could not claim laches as to the subcontractors’ claims, due to their own unclean hands. Finally, the court relied on its discretion under Code of Civil Procedure section 437c, subdivision (b) to grant the motion, despite the various missing separate statements, “as the material facts upon which the Court is relying are the same as to all moving parties.”
In Ranchwood, reconsideration was sought on the basis that the court had made statements at oral argument indicating it was only disposing of the
D
Current Procedural Status
In both matters, once the cross-complaints were dismissed, the plaintiff homeowners sued the subcontractors directly for negligence. They have since reached settlements with all those subcontractors. The record does not reveal if the settlements included good faith settlement or contribution orders which shielded the settling subcontractors from liability for equitable indemnity or contribution under Code of Civil Procedure section 877.6, subdivision (c).
In Ranchwood, the only respondents who have appeared in this appeal have been dismissed pursuant to settlements reached with appellants, and remittiturs have issued accordingly. There are also a number of respondents who are in default on appeal but who have not been dismissed out. As to the main action between the plaintiff homeowners and the defendant developer/ general contractors, the record on appeal does not reveal if any judgment or settlement was reached.
In Sickels, Kellogg, there is one remaining respondent (Southwest Construction Co.) who has filed a brief and who has not settled and been dismissed; the remainder of respondents who appeared have settled the action on appeal. This court was requested to stay the trial of the main action between the plaintiff homeowners and the defendant developer/general contractors, but declined to do so. (See fn. 3, ante.) We consolidated these appeals of the cross-complaint summary judgments for purposes of oral argument and the issuance of this opinion. Supplemental letter briefs were requested and obtained to clarify and confirm the procedural status of the case.
Analysis
A
Standard of Review
“In evaluating the correctness of a ruling under [Code of Civil Procedure] section 437c, we must independently review the record before the trial court. Because the grant or denial of a motion under [Code of Civil Procedure] section 437c involves pure questions of law, we are required to reassess the legal significance and effect of the papers presentеd by the parties in connection with the motion. [Citation.] We thus must apply the same three-step analysis required of the trial court:
“ ‘ “First, we identify the issues framed by the pleadings since it is these allegations to which the motion must respond .... [*10 Secondly, we determine whether the moving party’s showing has established facts which negate the opponent’s claim and justify a judgment in movant’s favor. . . . [H When a summary judgment motion prima facie justifies a judgment, the third and final step is to determine whether the opposition demonstrates the existence of a triable, material factual issue.” ’ [Citations.]
“In practical effect, we assume the role of a trial court and redetermine the merits of the motion. In doing so, we must rigidly scrutinize the moving parties’ papers. [Citations.]” (Chevron U.S.A., Inc. v. Superior Court (1992)4 Cal.App.4th 544 , 548-549 [5 Cal.Rptr.2d 674 ].)
Concurrently, application of a statute to a set of facts raises questions of law to which de novo review applies. (Vallejo Development Co. v. Beck Development Co. (1994)
B
Issues Presented
“Section 7031 . . . states that one may not sue in a California court to recover ‘compensation’ for ‘any act or contract’ that requires a California contractor’s license, unless one ‘alleges and proves’ he was duly licensed at all times during the performance.” (Hydrotech, supra, 52 Cal.3d at pp. 991-992, fn. omitted.) To determine the correctness of the trial court’s rulings disposing of these cross-complaints, we must first outline the scope
As we will show, the trial court gave too narrow a scope to the issues framed by the pleadings and too broad a scope to the licensing law. Our resolution of this threshold issue, that certain causes of action of the cross-complaint are not barred by licensing requirements, requires us to return the matters to the trial court for further proceedings on the remaining appropriate theories as pled. However, as we shall explain, the trial court was correct in concluding that other causes of action (those based in contract) may not be pursued in light of the lack of appropriate licenses and, in that connection and to the extent necessary, we will discuss the subsidiary issues argued on appeal (substantial compliance and owner/builder exemption; §§7031, 7044; see pt. IIE, post).
C
Section 7031 Licensing Law
“The purpose of the licensing law is to protect the public from incompetence and dishonesty in those who provide building and construction services. (Lewis & Queen v. N. M. Ball Sons (1957)
“Regardless of the equities, section 7031 bars all actions, however they are characterized, which effectively seek ‘compensation’ for illegal unlicensed contract work. (Lewis & Queen, supra, 48 Cal.2d at pp. 150-152.) Thus, an unlicensed contractor cannot recover either for the agreed contract price or for the reasonable value of labor and materials. [Citations.]” (Hydrotech, supra,
Similarly, in Vallejo Development Co. v. Beck Development Co., supra, 24 Cal.App.4th at pages 934-935, a “master developer” for a development project who agreed to install infrastructure improvements was not allowed to “prosecute any of its claims for compensation—whether characterized as actions on the contract or in quasi-contract, actions to foreclose a mechanic’s lien, actions to enforce a vendor’s lien, or otherwise—because, during the time it was providing the agreed-upon services to respondents, it did not have a valid contractor’s license as required by section 7031, subdivision (a) . . . .” (Fn. omitted.) Neither of these leading licensing cases discussed indemnity issues where a developer of a project, licensed or unlicensed, also acted as its own general contractor and now seeks to obtain indemnity from subcontractors who furnished labor and services on the project.
It is therefore necessary to inquire into the definition of “compensation” under the licensing law to see if indemnity and contribution sums fit within it. Under section 7031, these developer/contractors may not sue to recover compensation for their work from the property owners (here, themselves) or from the buyers of the property (plaintiff-homeowners). These cross-complaints, however, seek recovery from persons to whom these developer/contractors paid compensation for work, i.e., the subcontractors. The developer/contractors are now subject to being required by strict liability to pay damages to the plaintiff-homeowners, and are seeking to spread that loss among the subcontractors via indemnity. Obviously, this is not the normal “compensation” context, but its converse, which makes applying the licensing law bar particularly difficult here.
In any case, it is clear that “compensation” for work can take nonmonetary forms: In Johnson v. Mattox (1968)
However, the licensing law has been held not to bar certain forms of recovery by unlicensed contractors. Where the unlicensed contractor is also party to a separate contract, the unlicensed status will not bar him from obtaining relief for breach of the separate contract. (See, e.g., McCarroll v. L. A. County etc. Carpenters (1957)
Moreover, there are “cases permitting an unlicensed contractor to assert a setoff based on a contract for building services, notwithstanding that the contract is otherwise unenforceable due to the absence of a license. (Marshall v. Von Zumwalt (1953)
In Gaines v. Eastern Pacific (1982)
In a somewhat similar context, this court in Executive Landscape Corp. v. San Vicente Country Villas IV Assn. (1983)
The above authority represents efforts to reconcile the licensing law with related contract principles. It also represents an effort to read the licensing law penalties strictly so as not to add new penalties the Legislature did not intend to impose. (See Davis Co. v. Superior Court, supra,
On the tort front, in Hydrotech, supra, 52 Cal.3d at pages 999-1002, the Supreme Court interpreted the line of authority which has allowed unlicensed contractors to recover tort damages, i.e., where the “plaintiff’s involvement as an unlicensed contractor was incidental to the overall agreement or transaction between the parties. By the same token, the primary
From the above authority we learn that the prohibition on actions for compensation by unlicensed contractors is subject to numerous theoretical exemptions, in addition to the express statutory exemptions found in section 7040 et seq. (See 1 Witkin, Summary of Cal. Law (9th ed. 1987) Contracts, § 496, pp. 440-441.) To determine if the equitable and other forms of indemnity and related relief sought in this cross-complaint are similarly exempt from the licensing law, we turn to an analysis of the nature of the claims made in that cross-complaint, as well as the nature of the cross-complainants’ business.
D
Developer's Versus Contractor’s Liability
In their discussion of liability for defective construction, leading сommentators have explained the distinction drawn between “contractors” and “developers”: “The developer builds his improvements for sale to the public after they are completed. He is either a subdivider who improves the raw land and then constructs buildings for sale, or one who buys improved lots and builds the buildings on speculation for sale to the public. In either case, he builds and sells his products in the same manner as any other manufacturer of a product, ['fl] In contrast, the contractor builds improvements on the land of the owner pursuant to a construction contract. His
In some cases, a contractor who is also an owner-builder may have the responsibilities of a “developer.” (8 Miller & Starr, op. cit. supra, Defective Construction, at § 25:3, pp. 219-221, fn. 30.) In general, though, “[t]he rules of liability applicable to a contractor are different from those placed оn the developer.” (Id. at § 25:2, p. 218, fn. omitted.) A contractor may be held liable for negligence (his own and his subcontractors’), implied warranty, and in some cases fraud. (Id. at §§ 25:4-25:7, pp. 221-229.)
In contrast, a developer may be held liable for defective construction on a strict liability theory, as well as theories of negligence, breach of warranty, nuisance, and fraud or negligent misrepresentation. (8 Miller & Starr, op. cit. supra, Defective Construction, at § 25:14, pp. 265-266 & cases cited; La Jolla Village Homeowners’ Assn. v. Superior Court, supra, 212 Cal.App.3d at pp. 1142-1144.) Whether a residence falls within the category of a mass-produced home, such that strict liability for construction defects may be imposed, is a question which must be determined on a case-by-case basis. (Oliver v. Superior Court (1989)
With this state of the pleadings in mind as a frame for the issues, we next discuss the licensing status of these contractors and then outline the nature of the indemnity claims pled to see if such status is dispositive of all of their cross-complaints.
E
Substantial Compliance! Owner-Builder Exceptions to Licensing
Before we may analyze the effect of licensing requirements upon the contract-based causes of action, we must discuss as a threshold matter the developer/contractors ’ claims that there had been substantial compliance with the licensing statute in various ways, and in any case, they should be exempt from licensing requirements because they were “owner-builders”
Here, Ranchwood’s claim to substantial compliance appears to be that in 1987, one of its owner/lenders, MHP-1, obtained a license, even though the construction took place from 1981-1988. Also, Ranchwood and Sickels, Kellogg both argue that their hiring of licensed subcontractors should suffice for substantial compliance. Sickels, Kellogg adds that it hired a licensed general contractor, SCM, to manage the construction, and argues that also should suffice. None of these circumstances raises triable issues to show substantial compliance nor establishes it as a matter of law, under the prior law as set forth in Asdourian v. Araj, supra,
Moreover, we are not persuaded that these developers’ cross-complainants have shown they qualify as owner-builders under section 7044, a licensing requirement exemption for owners doing their own work or hiring licensed subcontractors, etc. This statute was amended in 1989 to change an “apparent exemption” in the licensing law for individual owner-builders, tract development builders, and builders building on speculation. (Assem. Bill No. 3841, statement of legislative intent.) The Assembly Third Reading states that the bill would narrowly restrict the existing owner-builder exemption. It thus appears that the Legislature was seeking to clarify existing law by further defining the owner-builder exemption. “[W]hen the legislation merely сlarifies existing law,” it may be applied retroactively. (Balen v. Peralta Junior College Dist. (1974)
Since the developers/general contractors may not avoid application of the licensing law on these technical bases, we turn to the merits of their cross-complaint claims.
F
Indemnity: Background and Contractual Theories
In Bay Development, Ltd. v. Superior Court (1990)
“ ‘The obligation of indemnity, which we have defined as “the obligation resting on one party to make good a loss or damage another has incurred” [citation] may arise under the law of this state from either of two general sources. First, it may arise by virtue of express contractual language establishing a duty in one party to save another harmless upon the occurrence of specified circumstances. Second, it may find its source in equitable considerations brought into play either by contractual language not specifically dealing with indemnification or by the equities of the particular case. [Citations.]’ (E. L. White [v. City of Huntington Beach (1978)] 21 Cal.3d [497, 506-507 (
“As this passage indicates, in E. L. White we recognized a distinction between an indemnity claim based on an express contract to indemnify, that is, an express contractual indemnity claim, and an indemnity claim based on ‘contractual language not specifically dealing with indemnification’ (E. L. White, supra,
In these cases, the developers/contractors ’ cross-complaints include against the subcontractors two groups of theories: (1) equitable indemnity, implied contractual and total indemnity, contribution, and recovery in negligence and (2) express indemnity, breach of contract and warranties, and
However, we must treat the cross-complaints’ causes of action for express indemnity as contract based, as are the causes of action for breach of contract and warranties and for declaratory relief. Are such causes of action fundamentally based on the illegal construction contract entered into by the unlicensed contractors here? If so, they would fall within the scope of the licensing laws. (Davis Co. v. Superior Court, supra,
Moreover, in discussing the scope of coverage of the class to be protected by the statute, the court stated that when the person required to have a license is a general contractor, “then the protected class includes subcontractors, materialmen, employees, and owners dealing with the general contractor.” (Lewis & Queen v. N. M. Ball Sons, supra,
Under the approach set out in Lewis & Queen v. N. M. Ball Sons, supra,
It should be noted that at oral argument on the summary judgment motions, counsel for the developers/general contractors seemed to concede that the contract-based causes of action would have to be adjudicated against them, while still vigorously arguing that the tort-based claims should survive the motion. In the Ranchwood matter, the trial court’s comments indicate that it initially seemed to adopt this approach and would adjudicate only part of the pleadings, but the order that was entered disposed of the entire cross-complaint.
In any case, we now conclude the contract-based causes of action of the cross-complaint are inseparable from the construction subcontracts and recovery on those subcontracts in the form of express indemnity cannot be sought by the unlicensed general contractors. Express indemnity payments are very similar to breach of contract damages in this context, and the contracts here (construction subcontracts) are illegal due to the lack of a developer/general contractor license, so they may not be enforced and no compensation can be sought under them. (Lewis & Queen v. N. M. Ball Sons, supra, 48 Cal.2d at pp. 147-148, 152-154.) The causes of action for express indemnity, breach of contract, breach of warranties, and declaratory relief on contractual indemnity rights are accordingly barred by the section 7031 licensing requirements.
G
Indemnity: Equitable Theories
Next, in considering the tort-based claims for equitable indemnity, implied contractual indemnity, total indemnity, and contribution, we must be guided by the approach taken by the Supreme Court in Lewis & Queen v. N. M. Ball Sons, supra, 48 Cal.2d at pages 150-151, as described above, for analyzing whether an unlicensed contractor is seeking to enforce an illegal contract or recover compensation under it. The court listed a number of factors that may be taken into account in deciding whether as a matter of policy an illegal contract may be enforced: the nature of the prescribed penalty, the goal of deterring illegаl conduct, and the policy of avoiding disproportionately harsh forfeitures. However, a court will not weigh such equitable factors where the statute governing the matter is clear. (Ibid.) “[T]he courts may not resort to equitable considerations in defiance of section 7031.” (Id. at p. 152.)
Also, on a related point, it is instructive to compare the measure of damages for breach of a construction subcontract (the agreed contract price or the reasonable value of labor and materials; Hydrotech, supra,
In GEM Developers v. Hallcraft Homes of San Diego, Inc. (1989)
This court followed the Safeway Stores lead (supra,
“[T]he principle of risk distribution has been described as the fundamental policy underlying the doctrine of strict liability (Price v. Shell Oil Co. (1970)
This is such a case. This cross-complaint does not represent “a garden-variety dispute over money owed an unlicensed contractor,” such as the Supreme Court considered in Hydrotech, supra, 52 Cal.3d at page 1002. Under all the circumstances, the primary relief sought here is not merely compensation for the work performed, but rather the spreading of the cost of a plaintiff’s damages incurred because of defective work by others. We do not believe a developer who is being held strictly liable for construction defects, and who also acted as an unlicensed general contractor, should be foreclosed from seeking relief from allegedly negligent subcontractors on theories of equitable indemnity, implied contractual and total indemnity, and
H
Negligence Theory of Cross-complaints
Finally, the cross-complaints contain causes of action for negligence damages against the subcontractors. Such negligence claims, like those for equitable indemnity and related concepts, we deem to be outside the scope of the contractual claims and thus not to be barred by licensing requirements. As pled in the cross-complaints, they do not allege any negligence damages beyond those suffered by the homeowner-plaintiffs, except for litigation expenses, and thus they are closely related to the indemnity claims. The record shows that the homeowner-plaintiffs have also taken it upon themselves to sue the subcontractors for negligence. The record also suggests in the correspondence file that the subcontractor defendants have reached good faith settlements with the homeowner-plaintiffs. This raises the issue of whether it would amount to a double recovery for the cross-complainants to pursue their own negligence claims against the subcontractors. Supplemental briefing on this issue was requested and was received from the developers/ contractors and amicus curiae, the Community Associations Institute. We discuss these issues for the guidance of the trial court on remand.
This court has discussed a related issue of potential double recovery in a factual context in which the homeowner-plaintiffs have settled their actions
“Where a release, dismissal with or without prejudice, or a covenant not to sue or not to enforce judgment is given in good faith before verdict or judgment to one or more of a number of tortfeasors clаimed to be liable for the same tort, or to one or more other co-obligors mutually subject to contribution rights, it shall have the following effect:
“(a) It shall not discharge any other such party from liability unless its terms so provide, but it shall reduce the claims against the others in the amount stipulated by the release, the dismissal or the covenant, or in the amount of the consideration paid for it whichever is the greater."
In Erreca’s v. Superior Court, supra, 19 Cal.App.4th at pages 1503-1504, we explained that if the plaintiffs “are able to successfully pursue their assignment of rights through litigation and judgment, they will have reaped a return on the valuable asset they ‘bought’ at settlement, and may be able to make a profit on their efforts. However, such profit or proceeds from their asset should not be characterized as a ‘double recovery,’ because the nonsettlors have been accorded a credit in the direct action for the fair valuation of the assignment of rights, and later developments (such as any indemnity recovery) do not affect the good faith of the settlement at the timе it was approved. Thus, if the two types of primary rights of the plaintiffs are distinguished from one another (direct recovery v. indemnity rights), the problem of a potential double recovery due to the assignment of rights is seen to be illusory.” (Italics added, fn. omitted; see also Regan Roofing Co. v. Superior Court (1994)
Here, too, under Code of Civil Procedure section 877, subdivision (a), to the extent that any good faith settlements have been reached in which the subcontractor defendants have paid negligence damages to the plaintiff-homeowners, the developer/contractor defendants will be entitled to appropriate credit against any recovery the plaintiff-homeowners may be able to achieve against them. This is so because “it is the same loss that is being apportioned—the loss suffered by the plaintiff/consumer.” (GEM Developers v. Hallcraff Homes of San Diego, Inc., supra,
The summary judgments are reversed and the matters are remanded for further proceedings in accordance with the principles set forth in this opinion. Each party to bear its own costs.
Benke, Acting P. J., concurred.
Notes
All statutory references are to the Business and Professions Code unlеss otherwise noted.
On a procedural note, we have found no abuse of discretion by the trial court under Code of Civil Procedure section 437c, subdivision (b) in accelerating the proceedings by waiving
Since these records were prepared before any findings were made in the main actions concerning the developer/general contractor’s liability to the homeowner-plaintiffs, on strict liability or other theories, we are assuming arguendo in this opinion that there will be some such liability determination, for which indemnity will eventually be sought by way of these cross-complaints. We are not presented with and do not intend to resolve any such issues of the developer/general contractors’ underlying direct liability to the homeowner/plaintiffs.
The developer/contractor cross-complainants in these cases have also sought a determination that the trial court erred in treating all the entities that have brought the cross-complaint alike for purposes of applying the licensing law. They claim that only one or two such entities in each case acted as a general contractor, and the others were merely lenders and/or owners of the property. Under section 7026, which defines a contractor as any person who “does himself or by and through others, construct, alter, repair, add to, subtract from, improve, move, wreck or demolish any building the trial court’s approach was not in error. From the pleadings, showing that all these entities were sued by plaintiff-homeowners as developers and constructors of the improvements, and cross-complained in a like manner, the trial court could logically infer they should be treated as a group for purposes of interpreting the cross-complaint. (La Jolla Village Homeowners’ Assn. v. Superior Court (1989)
In addition, the RCLP cross-complaint includes a strict liability theory against a component supplier, Gold Shield Fiberglas, Inc. and GSF Installation, Inc.. Since those parties have settled and beеn dismissed from the appeal, all such issues appear to be moot.
With reference to these equitable theories, it is technically not necessary to discuss the subsidiary issues of substantial compliance or whether these developer cross-complainants qualify as owner-builders under section 7044 or other applicable law. (See Kossler v. Palm Springs Developments, Ltd. (1980)
On a procedural note, the only respondents who have not settled and been dismissed from this appeal are, in No. D023845, Southwest Construction Co., and in No. D022053, the respondents who are in default. (See pt. ID, ante.) Only this group of nondismissed respondents may be party cross-defendants to the cross-complaint on remand. If appropriate, they may raise as a matter of defense in the trial court any good faith settlement orders they obtained in connection with their settlements with the plаintiff-homeowners. (Code Civ. Proc., § 877.6, subd. (c); see pt. ID, ante.)
Concurrence Opinion
JConcurring and Dissenting.—I concur in the holding of the majority except insofar as it concludes that contract based claims for indemnity in these cases are barred by Business and Professions Code section 7031 (hereafter section 7031). As to that point, I respectfully dissent.
Section 7031, subdivision (a) bars an unlicensed contractor from bringing suit “for the collection of compensation for the performance of any act or contract for which a license is required . . . .” (Italics added.) I believe the majority has too broadly construed these terms. Section 7031 prevents an unlicensed contractor from obtaining, directly or indirectly, “compensation for unlicensed work” (Lewis & Queen v. N. M. Ball Sons (1957)
Moreover, cases defining “compensation” for the purposes of section 7031 confirm that the statute only bars suits to recover remuneration for work performed without a license. This court stated in Davis Co. v. Superior Court (1969)
Accordingly, I believe the proper result is that neither contract- nor tort-based indemnity claims are barred by section 7031.
A petition for a rehearing was denied October 25, 1996. McIntyre, J., was of the opinion that the petition should be granted.
