Lead Opinion
Dissent by Judge ERICKSON.
OPINION
Candelaria Corporation (“Candelaria”), a prime contractor on a federal construction project, Carolina Casualty Insurance Company (“CCIC”), its surety, and Otay Group, Inc. (“Otay”), a subcontractor (collectively, “Defendants”), appeal the district court’s judgment in favor of Ramona Equipment Rental, Inc. (“Ramona”), Candelaria’s supplier of rental equipment,
I.
This dispute arises from a federal construction project known as ICE El Centro SPC — Perimeter Fence Replacement/Internal Devising Fence Replacement (the “Project”). Candelaria was the prime contractor on the Project and, in tandem with CCIC, provided a payment bond as mandated by the Miller Act. See 40 U.S.C. § 3131. In December 2007, Otay entered into a subcontract with Candelaria agreeing to supply certain labor and equipment for the Project. Shortly thereafter, Otay submitted, and Ramona approved, a credit application which established an open account for Otay to rent equipment from Ramona for use on the Project. Under the terms of the credit application, rentals would be documented by a rental agreement and invoice.
Between December 2007 and June 2008, Otay and Ramona entered into eighty-nine rental agreements on credit, totaling $235,446.84. On June 6, 2008, Candelaria terminated Otay’s subcontract for cause. At that time, Candelaria owed Otay over $500,000 for labor and equipment provided to the Project, and Otay had paid Ramona only $17,658.57 on the outstanding rental agreements.
On July 25, 2008, Ramona served a ninety-day notice of its claim for payment on Candelaria’s payment bond pursuant to 40 U.S.C. § 3133(b)(2).
The district court rejected Defendants’ first argument and concluded that, in light of the open book account, the ninety-day notice covered all rental equipment furnished to the Project. The court, however, determined that Ramona’s duty to mitigate damages arose as of June 10, 2008 (four days after Otay’s termination by Candelaria) and barred recovery for invoices after that date. Finally, the court rejected Ramona’s claim for compound prejudgment interest and awarded simple interest at the contractual rate of 1.5%. Accordingly, on August 31, 2011, the district court entered judgment awarding Ramona $178,686.56 plus $106,516.64 in service charges and $114,081.28 in attorneys’ fees. Defendants timely appealed.
The Miller Act “represents a congressional effort to protect persons supplying labor and material for the construction of federal public buildings in lieu of the protections they might receive under state statutes with respect to the construction of nonfederal buildings.” Mai Steel Serv. Inc. v. Blake Constr. Co.,
We have not addressed the precise issue presented by this appeal.
In United States ex rel. A & M Petroleum, Inc. v. Santa Fe Engineers, Inc., the Fifth Circuit concluded that notice within ninety days of the last delivery on a project involving multiple purchase orders— including orders made more than ninety days before the notice — was timely under the Miller Act.
Similarly, in Water Works Supply Corp., the First Circuit considered circumstances where the plaintiff extended a line of credit on an open book account for the purchase of pipe and piping materials.
Here, the relationship between Otay and Ramona was governed by an open book account that allowed Otay to rent equipment from Ramona on an ongoing credit basis. Ramona continued to rent equipment to Otay for use at the Project until Candelaria terminated its subcontract on June 6, 2008, and, within ninety days of the last rental, Ramona served notice of its claim for payment on Candelaria. These circumstances are clearly analogous to those addressed by the First, Fourth and Fifth Circuits. Accordingly, we join our sister circuits and hold that if all the goods in a series of deliveries by a supplier on an open book account are used on the same government project, the ninety-day notice is timely as to all of the deliveries if it is given within ninety days from the last delivery.
Relying on several recent district court cases, the dissent asserts that the ninety-day notice requirement selves to protect the general contractor and its surety. Dissent at 14; see e.g., United States ex rel. Country Boys Feed & Farm Supply v. Eickelmann, No. 08-3429-CV-S-GAF,
Moreover, contrary to Defendants’ argument, there is no risk here of double liability to Candelaria. See United States ex rel. Blue Circle West, Inc. v. Tucson Mech. Contracting, Inc.,
III.
Defendants also argue that the district court erred in determining that Ramona’s duty to mitigate damages arose only after June 10, 2008, four days after Candelaria terminated Otay’s contract. Reviewing the district court’s factual determination regarding the reasonableness of Ramona’s mitigation efforts for clear error, we find none. See Jackson v. Shell Oil Co.,
From December 2007 to June 2008, Ramona furnished equipment to Otay for the project and regularly invoiced Otay for the rentals. Otay paid the first nine invoices through March 4, 2008, but by May 28, 2008, had paid only two of the remaining eighty invoices. Recognizing that Otay was having financial difficulties, Candelaria made several attempts in May and June 2008 to meet with Otay representatives in order to determine a payment plan. These efforts were unsuccessful and, on June 6, 2008, Candelaria terminated Otay for cause. Ramona ceased renting equipment to Otay upon learning of the termination, but seventy-eight invoices remained unpaid in the amount of $218,329.23.
Defendants contend that because Ramona did not notify Candelaria of Otay’s overdue payments, and did not cease equipment rentals when prior invoices went unpaid, it failed to properly' mitigate damages. “Where a party is enti-
IV.
Finally, Defendants assert that Ramona waived its right to collect service charges through its course of conduct, as Ramona did not assess service charges until June 30, 2008. This argument was raised for the first time in the district court in a post-trial motion to alter or amend the judgment. The issue is waived. See Beech Aircraft Corp. v. United States,
AFFIRMED.
Notes
. Section 3133(b)(2) provides: "[a] person having a direct contractual relationship with a subcontractor but no contractual relationship, express or implied, with the contractor furnishing the payment bond may bring a civil action on the payment bond on giving written notice to the contractor within 90 days from the date on which the person did or performed the last of the labor or furnished or supplied the last of the material for which the claim is made....” 40 U.S.C. § 3133(b)(2).
. We have jurisdiction pursuant to 28 U.S.C. § 1291. We review the district court’s find
. In Apache Powder Co. v. Ashton Co., we dealt with a ninety-day notice that demanded payment for material supplied more than ninety days before the notice.
. Although Defendants rely on the Second Circuit’s opinion in United States ex rel. J.A. Edwards & Co., Inc. v. Peter Reiss Construction Co., it involved circumstances distinguishable from those at issue here.
. Defendants also argue that equipment Ramona rented from third parties and then "re-rented” to Otay does not constitute materials "furnished or supplied” under the Miller Act. We disagree. The words "furnished or supplied" are not defined in the Miller Act and are therefore entitled to their ordinary meaning. See Woods Constr. Co., Inc. v. Pool Constr. Co.,
Dissenting Opinion
dissenting:
I respectfully dissent. The Miller Act provides,
[a] person having a direct contractual relationship with a subcontractor but no contractual relationship, express or implied, with the contractor furnishing the payment bond may bring a civil action on the payment bond on giving written notice to the contractor within 90 days from the date on which the person did or performed the last of the labor or furnished or supplied the last of the material for which the claim is made.
40 U.S.C. § 3133(b)(2). This case involves a series of contracts under an open account. From January 2008 through July 2008, Otay paid only eleven of its eighty-nine invoices. Of the $706,917.62 Otay paid Ramona during the relevant time period, Otay allocated only $17,538.32 to this federal construction project. The remainder was allocated to a separate project. Ramona did not notify Candelaria until July 25, 2008 of the nonpayment. In the interim, Ramona assessed 1.5% monthly compounding interest on each outstanding balance.
A significant purpose of the 90-day notice provision in the Miller Act is to protect the general contractor and its surety. The potential extended duration of an open account relationship risks surprising the general contractor with an unforeseen and possibly staggering obligation. Requiring a subcontractor to provide notice at 90-day
I join the other courts that have adopted the more stringent notice requirement advocated by Appellants. See, e.g., United States ex rel. Country Boys Feed and Farm Supply v. Eickelmann, No. 08-3429-CV-S-GAF,
I believe Ramona’s July 25, 2008 notice of claim bars recovery for the forty-seven invoices issued prior to April 26, 2008. Accordingly, I would reverse and remand for entry of judgment, reducing the damages by $113,508.46 for failure to provide the proper notice of claim.
Appellants also contend that Otay’s prolonged delinquency on project-related payments should have put Ramona on notice of its need to mitigate damages. I agree. By the time Otay’s subcontract was terminated on June 6, 2008, seventy-eight invoices remained unpaid.
The general rule regarding a party’s duty to mitigate damages provides:
[Wjhere a party is entitled to the benefit of a contract and can save himself from a loss arising from a breach of it at a trifling expense or with reasonable exertions, it is his duty to do it; and he can charge the delinquent with such damages only as, with reasonable endeavors and expense, he could not prevent.
Commodity Credit Corp. v. Rosenberg Bros. & Co.,
The district court failed to consider, as a reasonable mitigating measure, Ramona’s failure to timely notify. Candelaria of Otay’s growing debt. Ramona concedes the very act of filing a Miller Act claim can constitute “available and judicially honorable means of mitigating” losses. United States ex rel. Balboa Ins. Co. v. Algernon Blair, Inc.,
The district court’s determination that the duty to mitigate damages did not arise until June 10, 2008 was clearly erroneous. Providing notice to Appellants of Otay’s
Appellants also assert Ramona waived its right to service charges through its course of conduct. Each rental agreement provides that a customer “agrees to pay a monthly service charge on all unpaid balances of 1-1/2% per month.” Despite Otay’s growing delinquency, Ramona did not assess service charges on any invoices issued during Otay’s subcontract (with the exception of one service charge which Ramona credited back to Otay). Ramona’s first exercise of this contractual light took place on June 30, 2008 — months after Otay’s first default and weeks after its termination by Candelaria- — when Ramona issued thirty-five “finance charge” invoices at once.
Ramona waived its right to collect service charges through its course of conduct. I would, therefore, vacate the award of $106,516.64 for service charges.
