Ramirez v. MurdickRamirez v. Murdick
Plaintiff-Appellant Hermilo Ramirez filed a
Huffman
claim
1
seeking liquidated damages, attorneys’ fees and costs for the late payment of Worker’s Compensation benefits. He appeals the Superior Court’s grant of summаry judgment in favor of the Defendants-Appellees, Jeremy Murdick, M & A Construction, Inc. and M & A Construction (the “Employer”). The Superior Court determined that the remedies under
Ramirez makes two arguments on appeal. First, he contends that the Superior Cоurt erred in its interpretation and application of two provisions of the Workers’ Compensation Act, specifically
I. Facts
The facts are undisputed. While working for Employer as a construction worker, Ramirez was injured. He filed a petition with the Industrial Accident Board seeking payment of workers’ compensation benefits. On February 8, 2007, the parties entered into a settlement agreement under which Employer would pay Ramirez total disability benefits and medical expenses. That same day, Ramirez’s counsel wrote a letter to Employer’s counsel making a Huffman demand that the benefits be paid within thirty days of his letter. The employer mailed payment on March 14, and Ramirez’s counsel received the payments on March 16, whiсh occurred thirty-four and thirty-six days after Ramirez made his Huffman demand, respectively.
Ramirez filed a complaint in Superior Court seeking liquidated damages, attorneys’ fees and costs under
II. Discussion
Ramirez argues that the Superior Court erred in dismissing his complaint because the thirty-day demand period under
A.
Civil actions filed under
“The goal of statutory construction is to determine and give effect to legislative intent.” 12 “If a statute is not reasonably susceptible to different conclusions or interpretations, courts must apply the words as written, unless the result of such a literal application could not have been intendеd by the legislature.” 13 Here, we must determine the intent of the legislature in defining when an amount is due after a settlement agreement.
Section 2862(c) of Title 19 defines when an amоunt is due to be paid after a settlement agreement. Under this provision, “payment of compensation shall commence within Up days of the date of that agreement.” 14 There is nothing ambiguous about when payment is due under this provision. Because the settlement agreement between the parties was made on February 8, the statute required that payment be made within fourtеen days of that agreement. As a matter of law, the amount due date was no later than February 22. A Huffman demand, therefore, for an amount due would be timely and propеr after that date. The Employer would be subject to Huffman liability thirty days after that demand. 15
The record in this case shows that payment was mailed by Employer’s counsel on March 14. This was within the thirty day period сontemplated by
B.
Next, Ramirez argues that the Superior Court erred in converting his motion to dismiss into a motion for summаry judgment. We review rulings on motions to dismiss pursuant to Rule 12(b)(6) and motions for summary judgment de novo. 16
In Appriva Shareholder Litigation Co. v. EV3, Inc., 17 we explained that “in reviewing the Superior Court’s decision to convert a motion to dismiss into a motion for summary judgment, we will examine three issues: [i] whether the materials submitted required conversion; [ii] whether the parties had adequate notice of the trial court’s intentiоn to convert; and [iii] if the parties did not have notice, whether the trial court’s failure to provide notice was harmless error.” 18 Superior Court Civil Rule 12(b)(6) expressly requirеs that if matters outside the pleadings are considered, “all parties shall be given reasonable opportunity to present all material made pertinent to such a motion by Rule 56.” 19 “An error in converting a Rule 12(b)(6) motion without notice is harmless only where there is ‘no set of facts on which plaintiffs could possibly recover.’ ” 20
The Supеrior Court converted the motion to one for summary judgment in this case because it was considering matters that were outside of the pleadings.
21
The parties agree that they did not have notice of the Superior Court’s intention to convert the motion. The parties also agree, as they did in Superior Court, that the facts pertinent to this litigation are undisputed. This case turned upon the court’s application of two statutes to undisputed facts. Although the Superior Court erred in not giving notice of thе conversion, this error was harmless because there are no facts on which Ramirez could recover under
III. Conclusion
The judgment of the Superior Court is AFFIRMED.
Notes
.
See Huffman v. C.C. Oliphant & Son, Inc.,
.
Ramirez v. Murdick,
.
.
.
LeVan v. Independence Mall, Inc.,
.
National Union Fire Insurance Co. v. McDougall,
.
.
.
.
Id.
at 934 (quoting
Aero Extrusion Corp. v. Cunningham,
. Id.
.
Id.
at 932 (quoting
Eliason v. Englehart,
.
Leatherbury v. Greenspun,
.
. The Supеrior Court correctly noted that a demand letter cannot in and of itself create a default in payment where one has not yet occurred.
See Ramirez v. Murdick,
. Asbestos Workers Local Union No. 42 Welfare Fund v. Brewster,
.
.
Id.
at 1286 (quoting
In re Rockefeller Ctr. Props., Inc. Sec. Litig.,
. Super. Ct. Civ. R. 12(b)(6).
.
Id.
at 1288 (quoting
Rose v. Bartle,
.
Ramirez v. Murdick,