Roy A. RALLS, Plaintiff-Appellant,
v.
The VILLAGE OF GLENDALE HEIGHTS et al., Defendants-Appellees.
Appellate Court of Illinois, Second District.
*340 Francis G. Libbe, Sandra L. Bucha, James Paul Costello, Ltd., Chicago, for Roy V. Ralls.
William J. Wylie, Thomas J. Laz, Stephen A. Rehfeldt, Wylie, Mulherin, Rehfeldt & Varchetto, P.C., Wheaton, for Village Glendale Heights and Concrete Structures of Midwest.
James T. Ferrini, Clausen, Miller, Gorman, Caffrey & Witous, P.C., Chicago, for Advance Mechanical Systems.
William H. Weir, Brittain, Ketcham, Strass, Terlizzi, Flanagan, Weir, Johnson & David, Elgin, for Strand Associates, Inc.
Robert G. Black, Hinshaw & Culbertson, Lisle, D. Kendall Griffith, Hinshaw & Culbertson, Chicago, Thomas A. Brabec, Lisle, Douglas J. Esp, Hinshaw & Culbertson, Lisle, for Doetsch Bros. Co.
Justice NICKELS delivered the opinion of the court:
Plaintiff, Roy A. Ralls, appeals the order of the circuit court granting defendants' motions for summary judgment of both Ralls' claim under the Structural Work Act (Ill.Rev.Stat.1987, ch. 48, par. 60 et seq.) and his claim for common-law negligence based on injuries he sustained when he fell on a snow-covered earthen incline at a construction site. Ralls asserts that the circuit court erred in finding as a matter of law that: (1) the earthen incline was neither a support nor was Ralls engaged in ultrahazardous activity at the time of his injury as required for application of the Structural Work Act; and (2) defendants owed no duty to Ralls, which defeated his claim for common-law negligence. We affirm in part and reverse in part.
Sometime prior to February 1988, defendant Village of Glendale Heights (owner) contracted with defendant Concrete Structures of the Midwest, Inc. (general contractor), for the construction of a sewage treatment plant. The construction was designed and engineered by defendant Strand Associates, Inc. (engineer), and defendant Doetsch Brothers (excavator) was the subcontractor for the excavation work. Ralls was the jobsite foreman in charge of the work for the processed plumbing subcontractor, which supplied specialty piping for carrying fluids other than water. As the foreman, Ralls had been at the site daily for seven to eight months and had the authority stop his crews' work if the conditions were unsafe.
The engineer designed, among others, the structure referred to as the blower building, which was the site of Ralls' injuries and which had two entrances. The north entrance was at ground level, but the south entrance was six to eight feet above ground level due to a temporary construction road on the south side of the building. The temporary construction road was below the planned eventual grade to allow access to the foundations of other buildings at the site during construction. The excavator had, however, backfilled the foundation of the blower building six months before Ralls' accident to prevent frost damage. In so doing, the excavator had constructed an earthen incline to the south entrance, as well as a two- to three-foot-wide earthen pathway around the entire perimeter of the building. Deposition evidence presented to the trial court estimated the incline to slope at an angle between 45 and 60 degrees over a space of six to eight feet. After its completion, the earthen incline was routinely used by workmen to reach the south entrance of the blower building. Both the incline and perimeter path were smooth and free from ruts in February 1988.
On February 4, 1988, Ralls and a co-worker were performing tests designed to discover leaks in pipes located in another *341 building. Ralls was to turn on the water to fill the pipes, which he would then shut off when the pipe was full upon a signal from his co-worker. Overfilling of the pipes was to be avoided because freezing of the excess water would damage the pipes. The controls for the water were located in the blower building.
Because the north entrance of the blower building was blocked by masoners, Ralls' only access to the water controls was via the south entrance. Therefore, Ralls used the earthen incline to enter the south entrance of the blower building. However, the perimeter path from the north entrance could have been used to reach the south entrance.
On the day of the accident, the earthen incline was covered with five to six inches of snow with the exception of an 18-inch path that had been packed down by prior workers using the incline to reach the south entrance of the blower building. Ralls' hands were empty as he walked up the incline, entered the blower building, and turned on the water. He paid particular attention to his footing because the pathway was snow packed and icy. Although Ralls could have waited on the perimeter path outside the south entrance, he instead descended the incline to wait for the shut-off signal. Ralls then again began to walk up the incline when he fell to his knees. At his deposition, Ralls testified that, although in his opinion the earthen incline was not dangerous, he slipped on the snow and ice on the footpath on the incline after taking a few steps. As a result of the fall, Ralls suffered injuries to both his knees, which eventually required several surgeries and which caused him ongoing pain.
Ralls brought this action against all defendants alleging in one count under the Structural Work Act that the earthen incline was a support and that he was engaged in an ultrahazardous activity of the type typically occurring at a construction site within the contemplation of the Structural Work Act. In a second count, Ralls claimed that the defendants owed him a duty to provide a safe system of ingress to and egress from the south entrance of the blower building and, therefore, were liable under a theory of common-law negligence for his injuries.
All defendants moved for summary judgment as to both counts. The circuit court eventually granted those motions as to all defendants, and Ralls now appeals. Ralls asserts that the trial court erred as a matter of law in finding that the earthen incline was a mere pathway and not a support and in finding that Ralls' use of the pathway was not the ultrahazardous type of construction activity encompassed by the Structural Work Act. Ralls also asserts that the court erred as a matter of law in finding that the defendants owed no duty to Ralls.
Summary judgment is appropriate where no issue of genuine fact is present and the moving party is entitled to judgment as a matter of law. (Vuletich v. United States Steel Corp. (1987),
The Structural Work Act provides protection to those workers who are engaged in extrahazardous work. (Lafata v. Village of Lisle (1990),
To sustain a cause of action under the Structural Work Act, a plaintiff must establish that he was: (1) involved in a construction activity, (2) with reference to a structure, (3) using a scaffold or other mechanical device, all of which must fit within the definitions and intended coverage of the Structural Work Act. (Smith v. Central Illinois Public Service Co. (1988),
Whether a device is a scaffold or other mechanical device within the definition of the Structural Work Act is a question of law to be determined by the court. (Vuletich,
However, in Vuletich, our supreme court recognized the distinction between a support, specifically used to accomplish some construction related activity, and a mere pathway. (Vuletich,
Ralls cites Keyser v. Metropolitan Sanitary District (1987),
It is the use of the device that is dispositive of whether the Structural Work Act provides coverage. (Vuletich,
Although Ralls also cites our recent decision in Heino v. Mellon Stuart Co. (1991),
Ralls also asserts that the court erred in finding his walking up the earthen incline was not the type of ultrahazardous activity that the Structural Work Act was designed to protect. Once again, it is the use of the device that is dispositive of whether the Structural Work Act applies. (Vuletich,
We now turn to Ralls' assertion that the circuit court erred as a matter of law in finding that defendants owed no duty to Ralls. To prevail on a claim of negligence, a plaintiff must prove the existence of a duty flowing from the defendant to the plaintiff that is breached and that proximately results in injury to the plaintiff. (Ward v. K mart Corp. (1990),
Ralls' third amended complaint asserted that the defendants failed to provide an adequate means of ingress and egress to the buildings at the construction site, failed to provide ladders or steps and handrails to accommodate such access, and failed to allow access to the blower building through the level north entrance. In finding that defendants owed no duty to *344 Ralls as a matter of law, the trial court focused solely on the duties imposed on a landowner or possessor of land by virtue of such status. (See Ziemba,
A possessor of land remains liable for known and obvious conditions on his land when "`the possessor should anticipate the harm despite such knowledge or obviousness.'" (Ward,
In this instance, Ralls' deposition testimony expressly indicated that he was aware of the snow-covered condition of the incline and, therefore, particularly careful. Thus, Ralls was not distracted, and those cases imposing liability based on the foreseeability of a distraction to the plaintiff are not applicable. (See, e.g., Diebert,
Just as it is reasonably foreseeable that customers leaving a store will be laden with packages distracting their attention from a concrete post near the doorway (Ward,
Nor does Ralls' own opinion that the incline was not dangerous change this conclusion. Conditions that are seemingly innocuous may present an unreasonable risk of injury under certain circumstances. (See Diebert,
Neither the magnitude of guarding against the injury nor the consequences of placing that burden on defendants would be severe in this instance. The excavator offered testimony, as did the former manager of the general contractor, that an eight-foot sheet of plywood with strips of wood for traction could have been placed up the incline to the door or that sand could have been spread on the footpath up the incline.
Finally, an injury from a fall is quite likely. Thus, although defendants owed no duty to Ralls to remove the natural accumulation of snow and ice, and although the slope of the incline was open and obvious, the incline was nevertheless a condition such that defendants should have reasonably anticipated harm to Ralls despite such knowledge or obviousness. (See Ward,
In light of our disposition of this issue, we need not consider the limited analysis of the trial court, which also failed to consider the duties created by either the municipal ordinances or the contracts of several of defendants. However, we note that the trial court was required to take judicial notice of such ordinances once brought to its attention (Ill.Rev.Stat.1987, ch. 110, par. 8-1001) and that violation of an ordinance designed to protect human life or property is prima facie evidence of negligence. (Kalata v. Anheuser-Busch Cos. (1991),
Similarly, the trial court failed to consider the contractual duties of several of defendants, which required them "to erect and maintain, as required by the conditions and progress of the work, all necessary safeguards for safety and protection," "at all times to provide a safe area for workmen and Subcontractors to work," to use "proper warning guards and safety devices with respect to the construction *346 area," or which further provided that "prevention of accidents to workmen engaged upon or in the vicinity of the work [was defendants'] responsibility." Such contracts, therefore, also imposed a duty upon the contracting defendants independent of that based on their status as possessors of the land. See Dyduch v. Crystal Green Corp. (1991),
The judgment of the circuit court granting defendants' motions for summary judgment is affirmed as to count I based on a violation of the Structural Work Act and is reversed as to count II sounding in common-law negligence.
Affirmed in part and reversed in part.
WOODWARD and GEIGER, JJ., concur.
