R. Zoppo Co. Inc. v. CommonwealthR. Zoppo Co. Inc. v. Commonwealth
This is a petition under G. L. c. 258 to recover for work and expense allegedly incurred by the petitioner during the performance of a contract with the Commonwealth acting through the Metropolitan District Commission (Commission). Both the petitioner and the respondent filed motions for judgment on undisputed facts in the pleadings and affidavits of counsel, each seeking entry of judgment in its favor 1 under G. L. c. 231, § 59. A Superior Court judge denied the petitioner’s motion and allowed the respondent’s motion. The petitioner appealed. ■ The contract provided for the construction of a sewer for the Deer Island sewage treatment plant in the city of Boston. It included certain deep marine trench excavation •and provided in part for construction and installation of forty linear feet of sixty-inch precast reinforced concrеte subaqueous pressure diffuser pipe between designated stations on the outfall sewer line. The petitioner subcontracted the construction of this pipe to the Perini Corporation (Perini).
After manufacture of the pipe and its delivery to the job site and payment in full for it by the subcontractor, certain tidal actions created a condition which in the opinion of the engineer necessitated the deletion of the final twenty-four linear feet of the pipe. The deleted pipe was subsequently transported by the petitioner to its storage yard in East Boston and later, at the direction of the engineer, to the Commission’s storage area on Deer Island. In a lettеr from the engineer to the Commission dated May 1, 1963, he stated the cost of the contractor’s claim for the twenty-four feet of sixty-inch pipe to be $4,075.63, and further averred that the work performed by the petitioner was extra to the prime contract and should be approved for payment as an extra work claim. The Commission approved the claim in that amount on May 2, 1963, but subsequently requested an opinion of the Attorney General “as to the proper method of payment” for the unused pipe. Acting on the advice of the Attorney General, the Commission thereafter refused payment to the petitioner. The opinion of the Attorney General referred to the advertisement for bids (which became a part of the contract) which indicated that the work to be done consisted of the construction of
approximately
5,454 linear fеet of outfall sewer, that quantities to be excavated were
approximate
only, that the work under certain items might be materially greater or less than indicated, and
1. Gеneral Laws c. 258 contains the provisions of the statute law upon which the Commonwealth in general waives its sovereign immunity to lawsuits and consents that claims “'of the character which civilized governments have always recognized’
(Murdock Parlor Grate Co.
v.
Commonwealth,
2. Under the provisions of the contract, an engineer was assigned to resolve all questions arising during its pеrformance and, specifically, was empowered to make alterations either before or after the commencement of construction.
3. Based upon the foregoing, we view this contract as an agreement best interpreted under Restatement: Contracts, § 236. Section 236 (a) calls for an interpretation “which gives a reasonable, lawful and effective meaning to all manifestations of intention” as against an interpretation “which leaves a part of such manifestations unreasonable, unlawful or of no effect.” Section 236 (d) provides additional guidance: “Where words or other manifestations of intention bear more than one reasonable meaning an interpretation is preferred which operates more strongly against the party from . . . [which] they proceed [the Commonwealth], unless their use by . . . [it] is prescribed by law.”
4. We pause to consider certain aspects of this contract and the item, the non-payment for which produced this action. The diffuser pipe, as has been stated, possessed unusual design features and required specialized manufacture. It had no salvage value and the only possible user of it was the Commission. In the contract which the Commission presented to the petitioner it was provided that “[t]he time in which the various portions and the whole of this contract are to be performed and the work is to be completed is оf the essence of this agreement.” To comply with this commitment to have the diffuser pipe on the job when required, it was necessary that the contractor arrange for fabrication of the pipe at a period sufficiently far in advance
■ 5. As we have indicated, performance by the contractor was prevented by the Commission in its own and the public interest. The petitioner may thus be excused from nonperformance of the requirements for payment set out in the
We hold that this case is governed by
Albre Marble & Tile Co. Inc.
v.
John Bowen Co. Inc.
6. In our view the petitioner is thus entitled to recover its costs representing fabrication, subcontractor’s handling and storage costs, and a reasonable amount for subcontractor’s overhead and profit, together with the petitioner’s overhead and profit, on the item fabricated and furnished to the amount set forth in appendix A of the petition.
The orders of the judge are reversed. Judgment is to be entered for the petitioner in the sum of $4,483.19.
So ordered.
Notes
The petitioner’s motion was for entry of judgment “in the sum of $4,483.19 with interest thereon.” The principal sum covered the cost óf the pipe and the subcontractor's handling and storаge costs, overhead and profit, all at $4,075.63, plus ten per cent for the petitioner’s overhead and profit, for a total of $4,483.19.
“Section 14 14 Measurement and Payment. The quantities to be paid for under Items 14 to 22 inclusive shall be the number of linear feet of precast reinforced concrete subaqueous pressure pipe including diffuser sections together with all appurtenances satisfactorily built into place in the completed work . . . .”