323 Mass. 624 | Mass. | 1949
These six actions are all brought to recover for damage to property caused on December 22, 1942, by water released from a sprinkler pipe which froze and broke in “Wampanoag Mill No. 2” at Fall River. All the actions except those of R. H. Macy & Co., Inc., and Greenwelk Knitwear Co., Inc., were tried as actions in contract or tort. The Macy and Greenwelk actions were tried as actions in tort only.
Some time before October 20, 1942, the city had acquired title to the mill by foreclosure of its tax lien and had leased different floors of the building respectively to the plaintiffs Cape Cod Shirt Company, F. R. Knitting Mills, Inc., and Avon Curtain Corp. Each lease was in effect in December, 1942, and each contained a covenant by the lessor (the city) “to furnish sufficient heat to reasonably heat the said premises in accordance with the proper or customary use of such building, between the hours of 7 a.m. and 10 p.m. on each week day.” Each lease also contained a covenant by the lessee that the lessor should “not be held liable for any damage done or occasioned . . . from plumbing, . . . water, steam, ... or other pipes . . . , or the bursting, leaking or running of any pipes . . .. ” The heating was by means of steam supplied through pipes from another mill some distance away which had also been acquired by the city. On October 20, 1942, the city conveyed “Wampanoag Mill No. 2” to the plaintiff Harmon Realty & Trading Corp., “subject to ” the leases, and at the same time executed an agreement with that plaintiff which contained a covenant to supply heat to the mill, framed in substantially the same language as the covenants in the leases, except that it should be in force until May 1, 1950, or until the Harmon corporation should provide heating facilities on the premises, and that the corporation should pay the city $3,500 a year. This agreement contained no provision by which the Harmon corporation agreed that the city should not be held liable for any damage occasioned by water or the bursting or leaking of pipes. The Macy and Greenwelk companies, which were neither lessees nor grantees of the real estate, base their claims solely upon damage to stock belonging to
In each case the trial judge directed a verdict for the defendant. The cases are here on report. In each case the question is whether a verdict was rightly directed for the defendant.
The conveyance.by the defendant to the Harmon corporation did not relieve the defendant from its obligations to the lessees on the leases. Jones v. Parker, 163 Mass. 564, 568. Carpenter v. Pocasset Manuf. Co. 180 Mass. 130, 133-134. Neal v. Jefferson, 212 Mass. 517, 521-522. Bickford v. Dillon, 321 Mass. 82, 83. But, whether the claims of the several plaintiffs are in contract or in tort, the obligations of the defendant in respect to heating spring from, and are necessarily defined by, the precise provisions of the leases and the agreement. McElroy v. Nashua & Lowell Railroad, 4 Cush. 400, 403. Squire v. Western Union Telegraph Co. 98 Mass. 232, 236-237. Wiley v. Bunker Hill National Bank, 183 Mass. 495, 496. Miles v. Boston, Revere Beach & Lynn Railroad, 274 Mass. 87. Tefft v. Boston Elevated Railway, 285 Mass. 121, 124. Abrams v. Factory Mutual Liability Ins. Co. 298 Mass. 141, 144. Lakube v. Cohen, 304 Mass. 156, 159. See Bryant v. Rich, 106 Mass. 180, 188-189; Vannah v. Hart Private Hospital, 228 Mass. 132. Compare Tuttle v. George H. Gilbert Manuf. Co. 145 Mass. 169; Bickford v. Richards, 154 Mass. 163. In the face of express provision there is no room for the implication of any broader duty than that expressed.
It is difficult to see how the defendant can be held liable to any of the lessee plaintiffs, or to the plaintiffs .whose material was in the lessees’ possession, in view of terms of the leases that the lessor shall not be held liable for any damage done or occasioned from plumbing, water, steam, or other pipes, or the bursting, leaking or running of any pipes. Fera v. Child, 115 Mass. 32. Henry H. Tuttle Co. v. Phipps,
We are of opinion, moreover, that none of the plaintiffs, including the Harmon corporation, was entitled to go to the jury for the comprehensive reason, applicable alike to all the plaintiffs, that the evidence would not warrant a finding that the damage was caused by failure of the defendant to perform its covenant to furnish heat as defined in the leases and in the agreement of October 20, 1942. The pertinent evidence is related to a period of about three days from Saturday, December 19, to Tuesday, December 22. This appears to have been a period of extreme cold weather for Fall River. The only evidence of failure to furnish heat during this period was that on Saturday and Sunday “'there was no heat at all”; that on Monday “the temperature around the plant ‘must have been around 40 or 42°/ ” and it was so cold that the employees did not work, but that “heat began to come up that afternoon”; that the employees worked the next day, Tuesday; that the flow of water was first discovered between seven and eight o’clock Tuesday night; and that the premises were then “awful cold.” A person in charge of the weather bureau testified that on Saturday the outside temperature was ten degrees above zero at 8 a.m. and seven degrees at 8 p.m., with a maximum for the day of seventeen degrees and a minimupa of four degrees; that on Sunday the temperature was zero at 1 a.m., reached a minimum of twelve degrees below zero at 6 a.m., a maximum of seven degrees above at 4 p.m., and
The defendant was under no obligation to furnish any heat at all from ten o’clock Saturday night until seven o’clock Monday morning. This period of thirty-three hours included the coldest part of the three days, the thermometer being below zero, according to the weather observer, during all but about nine hours of this time. The lowest temperature was twelve degrees below zero and the highest seven degrees above. We see no reason to believe that the freezing took place on Saturday, when the thermometer outside did not go below zero at all, rather than on Sunday, when the weather was considerably colder. Neither is there any particular reason to believe that the freezing occurred during the day Monday, while there was an obligation to furnish heat. So far as the evidence discloses, the inside temperature was about ten degrees above freezing on Monday, and the heat “began to come up” that afternoon. If the freezing occurred Monday night, again .the defendant was not required to furnish any heat at that time. On Tuesday the employees were working once more, and the weather moderated rapidly. There was no evidence as to the heat retaining qualities of the building except that it was of mill construction; that it was a stone building; and that the walls were brick, whatever that may mean. There was no evidence that failure to heat on Saturday would result in freezing before 10 p.m., or that heating on Saturday to the extent required by the covenants would have prevented freezing on Sunday. There was no evidence of “the proper or customary use” of the building on Saturdays. So far as appears it may not have been customary to work on Saturdays, and under the terms of the covenants little or no heat may have been required on those days. There was
Because of the view we have taken of the evidence it becomes unnecessary to consider the defendant’s contention that, as a municipality, it had no power to contract to furnish heat.
In each case the entry will be
Judgment for the defendant.