R.A.C. Group, Inc. v. Board of EducationR.A.C. Group, Inc. v. Board of Education
Louis R. Rosenthal, Brooklyn (Alexander M. Dudelson of counsel), for appellant.
Catafago Law Firm, P.C., New York City (Jacques Catafago of counsel), for respondents.
OPINION OF THE COURT
COZIER, J.
The instant appeal presents an issue of first impression for this Court—whether a contract which violates
The plaintiff Robert Shahid is an architect who was employed by the defendant Board of Education of the City of New York (hereinafter the BOE) from 1985 until May 1994. Shahid was assigned to the BOE Department of Real Estate, Office of Lease Management, which oversaw the implementation of the leased-facility program. Under the leased-facility program, the BOE identified privately-owned buildings suitable for conversion into school facilities and leased them from landlords. The BOE expended capital funds for the construction work required to convert the buildings into school facilities (hereinafter the build-out), and the landlord selected the contractor to perform the build-out.
In early 1994 BOE architect Clarence Jackson visited the premises at 350 Gerard Avenue in the Bronx (hereinafter the subject property), and recommended against leasing that property for school use on the ground that construction costs would be “prohibitive.” The subject property was located in a manufacturing district next to the Major Deegan Expressway, and the use of that property as a school would have required, among other things, a zoning override to obtain approval for a certificate of occupancy.
However, in April 1994, Shahid visited the subject property at the alleged direction of his supervisor, overruled Jackson‘s recommendation, and approved that property for BOE‘s leased-facility program. During this time, Shahid was a senior project coordinator and supervised a staff of six architects, including Jackson. As senior project coordinator, Shahid reviewed proposed site selections for leased space and oversaw the design of build-outs.
Shortly thereafter, on May 20, 1994, Shahid resigned from his $46,000-a-year position with the BOE, and on July 22, 1994, entered into a contract with Bruckner in his representative capacity as president of the plaintiff R.A.C. Group, Inc. (hereinafter RAC), to serve as the project manager for the build-out project on the subject property (hereinafter the July 1994 contract).
One of Shahid‘s duties under the July 1994 contract was to recommend contractors as potential bidders for the subject build-out project, and to contact those contractors which Bruckner selected. Under the terms of the July 1994 contract, Bruckner, as owner, was required to pay RAC 3% of the total construction cost for the subject property (i.e. $364,200 of $12.14 million). Shahid is the owner, director, and sole stockholder of RAC.
After RAC commenced its work as project manager under the July 1994 contract, RAC received three checks (dated August 17, 1995, November 1, 1995, and November 29, 1995, respectively) totaling $72,786.78. Although Shahid cashed the first two checks totaling $46,062.33 without incident, the third check for the sum of $26,724.45 was dishonored when he attempted to cash it.
In December 1995 Bruckner terminated Shahid‘s services as the project manager at the direction of the BOE and pursuant to an investigation by the Inspector General‘s Office of the New York City School Construction Authority (hereinafter the I.G.), suggesting that Shahid violated
The I.G. concluded, inter alia, that 350 Gerard Corp. was neither the owner of the subject property nor an existing entity at the time that the BOE negotiated the subject lease in May 1994 or when the BOE adopted a resolution in June 1994 to go forward with the lease and build-out of the subject property. According to the I.G., 350 Gerard Corp. was incorporated on July 6, 1994, and obtained legal title to the subject property on July 13, 1994. Particularly, the I.G. found that nonparty 350 Asset Corporation (hereinafter 350 Asset) acquired the $6 million note for the subject property, foreclosed on the subject property on June 29, 1994, for $400,000, and assigned its interest in that property to 350 Gerard Corp. In addition, the I.G. found, inter alia, that Holand and/or his family members controlled both 350 Asset and 350 Gerard Corp.
The I.G. also found that Bruckner awarded a contract to nonparty American Redevelopment Enterprises (hereinafter ARE) to serve as the general contractor based upon Shahid‘s recommendation, and that the former principal of that entity was a convicted felon. According to the I.G., ARE and another nonparty, Creation Contracting Co. (hereinafter Creation), formed a joint venture to perform various construction projects, including the build-out project for the subject property. In fact, 350 Gerard Corp. advised the BOE officials that ARE would be the general contractor before ARE was selected as the contractor. It appeared that Creation was formed for the sole purpose of performing the build-out work for the subject property.
Further, the I.G. determined, inter alia, that Shahid similarly entered into contracts to provide project management services for two other leased-facility buildings (one in the Bronx, and one in Brooklyn), and that the aggregate value of such contracts, as well as the contract with Bruckner, was nearly $750,000. The I.G. advised the BOE, inter alia, that it could demand that the contract with Shahid be terminated, and that the BOE be reimbursed for any funds paid to 350 Gerard Corp. as part of project management services. The I.G. also informed the BOE that it referred Shahid to the Office of the Manhattan District Attorney for possible criminal prosecution.
350 Gerard Corp. subsequently retained a different contractor to complete the build-out project at the subject property, and
Shahid and RAC (hereinafter the plaintiffs) then commenced this action, inter alia, to recover damages for breach of contract against, among others, Bruckner and the BOE. The action against the BOE was dismissed for failure to timely serve a notice of claim.
A nonjury trial was held in Supreme Court, Kings County, and the court concluded that the plaintiffs were entitled to recover under the contract. During the trial, a Bruckner representative acknowledged during direct examination that the lease for the subject property set forth certain postemployment restrictions with respect to former city employees.
After the trial, the Supreme Court found, inter alia, that Shahid violated
A person who violates
The violation of a statute which is merely malum prohibitum will not necessarily render a contract illegal and unenforceable if that statute does not expressly provide that its violation will deprive the parties of their right to sue under the contract, and the denial of relief is wholly out of proportion to the requirements of public policy (see Benjamin v Koeppel, 85 NY2d 549, 553 [1995]; Lloyd Capital Corp. v Pat Henchar, Inc., 80 NY2d 124, 127 [1992]; Wowaka & Sons v Pardell, 242 AD2d 1, 6 [1998]). Further, recovery under a contract which is malum prohibitum in nature will be upheld where regulatory sanctions and statutory penalties exist to redress statutory violations (see Benjamin v Koeppel, supra at 553; Lloyd Capital Corp. v Pat Henchar, Inc., supra at 127; Wowaka & Sons v Pardell, supra at 6).
Acts in violation of
We note that Shahid was instrumental in securing approval of the subject property for the BOE‘s leased-facility program, and that by virtue of his employment with the BOE and direct involvement with the build-out project at issue, he acquired valuable information regarding that project and obtained a contract to serve as the project manager for said project after terminating his employment with BOE, in violation of
Further, the fact that the circumstances surrounding the conversion of the subject property into a school facility was permeated with such fraud and deceit compels a finding that the plaintiffs should not be allowed to benefit from such conduct. Public policy prohibits recovery under a contract where a party engages in fraud or other immoral conduct in tendering its performance under the contract (see McConnell, 7 NY2d at 469-471). As the Court of Appeals stated in McConnell (7 NY2d at 469), “long-settled public policy closes the doors of our courts to those who sue to collect the rewards of corruption.”
As it appears that Bruckner does not have clean hands in the subject transaction, normally we would not allow Bruckner to use public policy “as a sword for personal gain rather than a shield for the public good” in seeking to preclude recovery under the subject contract (see Charlebois v Weller Assoc., 72 NY2d 587, 595 [1988]). However, although barring the plaintiffs from recovering under the subject contract may result in a windfall to Bruckner, precluding such recovery is consistent with the public policy sought to be served by imposing postemployment restrictions under
Although the conclusions of a trial court are entitled to great deference on appeal and will not be set aside unless they could not have been reached under any fair interpretation of the evidence (see Frost v Goldberg, 13 AD3d 409, 411 [2004]; Northvale Prop. Assoc. v Osram Sylvania, 300 AD2d 373 [2002]), the judgment in favor of the plaintiffs must be reversed, as any recovery would thwart the postemployment restrictions under
Therefore, in light of the foregoing, the judgment is reversed, on the law, the order is vacated, and the complaint is dismissed.
H. MILLER, J.P., RIVERA and SKELOS, JJ., concur.
Ordered that the judgment is reversed, on the law, with costs, the order is vacated, and the complaint is dismissed.