128 Minn. 270 | Minn. | 1915
Plaintiff while working for defendant was injured. This action followed, the injury being attributed to defendant’s negligence. Defendant appeals from the order denying its alternative motion for judgment notwithstanding the verdict or for a new trial.
The defendant is a corporation engaged, among other things, in putting up, taking down and moving metal smokestacks, metal breeching, etc., in factories and large buildings. On Saturday, July 5, 1913, defendant started to move the smokestack and take down the breeching in the. boiler room of the Waldorf Box Board Co. in St. Paul. It was to be done in three days. This room is about 50 by 60 feet in dimension. The boilers are in the northwest corner and extend south to within 25 feet of the south wall. The smokestack, about 4-|- feet in diameter, of sheet steel, stood at the time within a foot of the south wall and about 25 feet from the southwest corner of the room. The smoke and gases were conducted from the vent of the boilers near the west wall by a huge pipe, variously estimated as 4 feet wide by 5, 7, or 9 feet high, made of sheet steel, riveted together. This pipe, called the breeching, passed from the boilers south along the west wall, but at a distance
Defendant’s undertaking was to move the smokestack from the south wall and place it against the west wall of the room. This .necessitated taking down the stack, and removing the breeching, at least all thereof parallel with the south wall. On the Saturday mentioned, a crew of four or five men under a foreman, accompanied by Osear W. Olson, an officer and superintendent of defendant, began the work. The foreman and part of the crew worked on the outside, rigging up a gin-pole, an instrumentality necessary in taking down large smokestacks. Olson and the others worked inside. The record is vague as to what particular work was done inside on Saturday. Plaintiff contends that preparation was then made by placing planks as staging for the larger crew which was expected there Sunday. But undoubtedly some rivet cutting upon the breeching took place on Saturday and perhaps part thereof was
The jury were justified in finding that this plank was placed there on Saturday, July 5, although Gust Wonhala, the man who worked with plaintiff at the time of' the accident, testified that he and plaintiff procured the plank on Sunday forenoon and placed it in position.
The question presented is: Assuming that this plank was negligently placed in an unsafe position on Saturday, when plaintiff was working at another place, by one of defendant’s servants, is defendant liable ? The negligence charged was failure to provide plaintiff a safe place to work; negligence in constructing the staging or scaffold upon which plaintiff was ordered to work, particularly in respect to the plank mentioned; and other grounds not here important. The answer denied negligence, and set up contributory negligence, assumption of risk, and negligence of fellow servant as the sole causes of the injury.
The trial court thus charged the jury: “Of course, if the evidence of Mr. Wonhala, as given in this case, is true, and Mr. Quinn
“If the plank was placed there by the defendant on Saturday •for the purposes of a scaffolding or a staging, a question will arise as to whether or not it was a reasonably safe place.
“The duty of a master when furnishing a place in which his servant is to work requires him to use ordinary care to furnish a reasonably safe place in which to do the work, and it is for you to say whether or not the plank as placed was placed in a reasonably safe and secure manner.”
No exception to the charge was taken on the motion for a new trial, nor. is error assigned thereon in this court. Therefore, right or wrong, the instructions set out must be taken as the law of this case. Smith v. Pearson, 44 Minn. 397, 46 N. W. 849; Bergh v. Sloan, 53 Minn. 116, 54 N. W. 943; Bates v. B. B. Richards Lumber Co. 56 Minn. 14, 57 N. W. 218; Kleis v. Travelers Ins. Co. 118 Minn. 422, 136 N. W. 1101; Bertram v. Bemidji Brewing Co. 123 Minn. 76, 142 N. W. 1045. The question whether the negligent placing of the plank in position on Saturday affected the right of recovery cannot be considered under the assignments of error. Nor is the refusal to dismiss an available error here, if, when the evidence was all in, there was sufficient to go to the jury upon defendant’s liability.
However defendant’s assignments that he should have had judgment notwithstanding the verdict, and that there is no evidence to
Is the verdict excessive? The neck of the femur of plaintiff’s right leg was fractured, also there was some fracture in the shoulder joint. The trial took place eight months after the injury. The doctors were of the opinion that the surgical treatment afforded plaintiff had caused as good a union of the bones as could be expected. The leg ivas shortened about an inch. The callus thrown out at the point of the shoulder and at the neck of the femur interferes with the movement of the limbs. The experts do not doubt that he will have a serviceable leg and arm, though somewhat limited in movement, depending on the absorption of the callus. Plaintiff was bound to have a use both of his arm and leg according to his medical expert, although it might take a year more for a substantial recovery. Aside from the shortening of the leg the calluses seem to be the only baneful effect from the injury. One doctor testified that the absorption of a callus cannot be expected to begin until about eight months after the fracture begins to heal. No evidence of any medical or hospital expenses appears. At the time of the injury plaintiff was 49 years old, earning 25 cents an hour. He'was a farmer and ordinary laborer. There is no injury or suffering except such as usually attend the painful recovery from a fracture where it is necessary to place weights on the limb to keep the bones in position, The verdict was for $9,850. We consider it excessive, unless the anticipated improvement in the use of the limbs should fail to appear. We think therefore that a new trial should be had, unless plaintiff at this time deems $7,000 a proper compensation which he is willing to accept.
The order, insofar as a new trial is denied, is reversed and a new trial is granted, unless plaintiff, within 10 days after the remittitur is sent down, file in the court below written consent to a reduction of the verdict to the sum of $7,000. If such consent is filed no new trial shall be had.
Affirmed conditionally.