104 Tenn. 560 | Tenn. | 1900
Quigley & Co. brought this suit against E. A. Shedd and C. IT. Pond on the following written contract, namely:
“This memorandum of agreement, made this the 21st day of November, 1898, between R. M. Quigley & Co. and E. A. Shedd and C. PI. Pond, witnesseth:
“'Whereas, The said Quigley & Co. entered into a contract with said Shedd and Pond, on April 2, 1898, to build the pile trestles and lay the tracks on the lines of the new roads between Tutwiler, Miss., and "Ruleville, Miss., and between Moorehead, Miss., and Lake Dawson, Miss.;
“Ahd, whereas, It is desired to terminate and cancel the said contract; now, therefore,
“Said Shedd and Pond agree to reimburse the
“In determining the various items of the expenditures of the said Quigley & Go., Captain A. W. Grloster shall act as arbitrator in the event of a disagreement ■ between the parties to this contract.
“This contract, being consummated, payment shall be made Quigley & Co. immediately.
“In witness whereof, The parties herdto set their hands on day and date first above mentioned.
“[Signed] E. M. Quigley & Co.,
“E. A. Shedd and C. H. PoND,
“.By C. H. Porno"
The plaintiff claimed a recovery for $21,302.55 in the aggregate — $5,000 as the bonus and $16,-
The defendants conceded liability for the $16,-302.55, and also for $1,000 of the bonus, in all $17,302.55, but denied liability for the other $4,000 of the bonus and for interest. So that, at the trial, the only controversy was in respect of the interest and $4,000 of the bonus. The jury returned a verdict in favor of the plaintiff for $17,302.55, the. amount which the defendants conceded they owed, and $596.93 interest thereon, making an aggregate of $17,899.48. The Court pronounced judgment upon the verdict as rendered.
On their appeal in error the plaintiffs still contend that they are entitled to recover the whole of the $5,000 bonus, and insist that they were deprived of that right by certain erroneous rulings of the trial Judge as to evidence and in his charge.
It was agreed at the commencement of the trial that the defendants paid the plaintiffs the sum of $4,000 under and during the life of the original contract of April 2, 1898, which was canceled by the contract sued on. The defendants contended before the Court and jury that they were entitled to have that payment credited on the $5,000 bonus, and that they were, therefore, liable on the item of bonus for the re
It will be observed that the. contract before the Court- makes no allusion to the previous payment of the $4,000, but stipulates unconditionally for “the payment, as a bonus, of $5,000.” The fact that such payment was made appears alone from the assertion of the defendants and the admission of the plaintiffs.
While on the stand as a witness for the plaintiffs, Pi. II. Quigley delivered testimony tending to show that, before the second contract was executed, it was understood and • agreed between himself for the plaintiffs and C. PL Pond for the defendants, that the plaintiffs should, receive the $5,000, to be included in the second contract as a bonus, in addition to the $4,000 already paid to them under the first contract.
The Court excluded this testimony from the consideration of the jury for the assigned reason that the written contract was “the consummation of the agreement” between the parties, and not subject to explanation.
That ruling was erroneous, the evident purpose and tendency of the rejected testimony being not to alter, vary, or contradict the terms of the written contract in any respect, but only to- establish an independent verbal agreement collateral
It is true, as suggested by counsel of defendants, that the plaintiffs based their su.it entirely upon the written contract, and to no extent upon the alleged verbal agreement, yet that fact cannot affect the admissibility of this testimony, since it was introduced with the sole view of rebutting and defeating the counter claim or credit interposed by the defendants, and not for the purpose of extending the affirmative rights of the plaintiffs beyond the plain' terms of the written contract.
The Court charged the jury, in effect, that the defendants were entitled to a credit on the $5,000 bonus for the $4,000 paid to the plaintiffs under the first contract and before the execution of the second one.
This charge is assailed by the plaintiffs for the reason that it took the issue of credit or no credit from the jury and peremptorily directed that the credit claimed by the defendants be ' allowed, when, as insisted, the question was one of fact for the decision of the jury alone. The defendants respond to the criticism, and say
If the particular issue was one of fact to be determined from the whole evidence, as we think it obviously was, the instruction was a palpable invasion of the province of the jury, and for that reason erroneous; or if, on the other hand, the issue was one of law, dependent alone upon the construction of the written contract, as we think it clearly was not, the instruction was erroneous in that it did not give the contract its true meaning. Judged by its own terms alone, the contract’s meaning is exactly the reverse of the charge. It contains an unconditional obligation on the part of the defendants to pay the plaintiffs “thereafter” the full sum of $5,000 as a bonus, making no reference to the previous payment of the $4,000, or any other sum; from which it must of necessity follow, in the absence of other evidence, that the $5,000 was to be paid without abatement or reduction.
There can be no doubt that it is the duty of the Court to construe unambiguous writings upon which litigated rights are based, and to instruct the jury as to their legal meaning (Railroad v.
Reverse and remand.