ERIC QUETOT, et al., PLAINTIFFS-APPELLANTS VS. M&M HOMES INC, DEFENDANT-THIRD PARTY PLAINTIFF-APPELLEE VS. ALLEN RUMMEL, et al., THIRD-PARTY DEFENDANTS-APPELLEES
CASE NO. 12 CO 1
STATE OF OHIO, COLUMBIANA COUNTY IN THE COURT OF APPEALS SEVENTH DISTRICT
February 25, 2013
2013-Ohio-752
Hon. Cheryl L. Waite, Hon. Joseph J. Vukovich, Hon. Mary DeGenaro
CHARACTER OF PROCEEDINGS: Civil Appeal from the Court of Common Pleas of Columbiana County, Ohio, Case No. 10 CV 979. JUDGMENT: Affirmed.
For Plaintiffs-Appellants Eric & Tina Quetot: Atty. Geoffrey D. Korff, The Korff Law Firm LLC, 310 E. Euclid Ave., Salem, Ohio 44460
For Defendant-Appellee M&M Homes: Atty. Michael P. Marando, Pfau, Pfau & Marando, P.O. Box 9070, Youngstown, Ohio 44513
For Third Party Defendant Allen Rummel: Atty. Wm. Scott Fowler, Comstock, Springer & Wilson Co., LPA, 100 Federal Plaza East, Suite 926, Youngstown, Ohio 44503
For Third Party Defendant Boak & Son, Inc.: Atty. Craig G. Pelini, Pelini, Campbell, Williams & Traub, LLC, 8040 Cleveland Ave., NW, Suite 400, N. Canton, Ohio 44720
For Third Party Defendant James R. Close, dba Siding Guys: Atty. James E. Featherstone, 610 South Front Street, Columbus, Ohio 43215
For Third Party Defendant L&L Masonry: Atty. Brian J. Macala, 117 South Lincoln Avenue, Salem, Ohio 44460
For Third Party Defendant David Rose, dba Rose Excavating: Atty. Maria Placanica, 50 South Main Street, Suite 502, Akron, Ohio 44308
Third Party Defendant: Ted Bell, dba Bell Plumbing, 580 Continental Drive, Salem, Ohio 44460
OPINION
WAITE, J.
{¶1} Appellants Eric and Tina Quetot (“Appellants“) are appealing a partial summary judgment decision of the Columbiana County Court of Common Pleas. Appellants filed a multi-count complaint arising from disputes over a house that was built for them by Appellee M&M Homes Construction, Inc. (“M&M Homes“). One of the counts involved an alleged violation of the Consumer Sales Protection Act (“CSPA“). The court granted summary judgment to Appellee on the CSPA claim, but other claims remain pending. The trial court determined that Appellants’ CSPA claim was barred by the two-year statute of limitations in
{¶2} Appellants argue on appeal that their CSPA claim was not time barred. The parties all agree that a CSPA claim may be brought for a deceptive act that occurs before, during or after a consumer transaction.
{¶3} In Appellants’ second assignment of error they request that we reverse the trial court‘s ruling regarding whether punitive damages and attorney fees may be sought on a pending tort claim. The trial court did not deny the possibility of punitive damages and attorney fees for the tort claim and no relief is necessary on appeal. Both of Appellants’ assignments of error are overruled, and the judgment of the trial court is affirmed.
History of the Case
{¶4} This case arose out of the construction of a single family residence by M&M Homes in late 2006 and early 2007 for Appellants in New Waterford, Ohio. The contract was entered into on September 1, 2006. M&M Homes was the general contractor, and it utilized a variety of subcontractors in construction. Mr. Nathan Maley is the founder of M&M Homes and is one of the two shareholders of the corporation.
{¶5} Appellants moved into the house in February, 2007. Appellants found problems with the structure soon after they moved in. These problems included issues with the drywall, the roof, plumbing, water leaks, and excess moisture. Appellants contacted M&M homes about these problems in 2007 and M&M Homes attempted to correct the problems.
{¶7} On January 3, 2012, the trial court ruled that Appellants’ CSPA claim was time barred. It denied M&M Homes’ motion for summary judgment on the negligence claim. It also ruled that the claim for punitive damages under the CSPA was time barred, and that the motion to bifurcate the claims for punitive damages was moot. Thus, the court granted partial summary judgment to M&M Homes only on the CSPA claim and on the claim for punitive damages under the CSPA. Appellants filed an appeal on January 11, 2012. We notified the parties that the January 3, 2012, judgment entry was not a final appealable order and did not contain
ASSIGNMENT OF ERROR NO.1
APPELLANTS’ CSPA CLAIM IS BASED ON ACTIONS AND REPRESENTATIONS OF THE DEFENDANT THAT OCCURRED WELL AFTER CONSTRUCTION OF THEIR HOME WAS COMPLETED, AND WITHIN THE 2-YEAR STATUTE OF LIMITATIONS REQUIRED FOR A CSPA CLAIM.
{¶8} Appellants present two arguments in support of the idea that the CSPA claim was not time barred by the two-year limitations period found in
{¶9} The parties agree on the relevant law. First, they agree that the appellate court conducts a de novo review of a trial court‘s decision to grant summary judgment, using the same standards as the trial court as set forth in
{¶10} “[T]he moving party bears the initial responsibility of informing the trial court of the basis for the motion, and identifying those portions of the record which demonstrate the absence of a genuine issue of fact on a material element of the nonmoving party‘s claim.” (Emphasis deleted.) Dresher v. Burt, 75 Ohio St.3d 280, 296, 662 N.E.2d 264 (1996). If the moving party carries its burden, the nonmoving party has the reciprocal burden of setting forth specific facts showing that there is a genuine issue for trial. Id. at 293. In other words, when presented with a properly supported motion for summary judgment, the nonmoving party must produce some evidence that suggests that a reasonable factfinder could rule in that party‘s favor. Brewer v. Cleveland Bd. of Edn., 122 Ohio App.3d 378, 386, 701 N.E.2d 1023 (8th Dist.1997).
{¶11} The parties also agree on the basic law applicable to the statute of limitations for a CSPA claim. The parties assume for the sake of argument that the services provided by M&M Homes were covered by the CSPA, found in
{¶12} No discovery rule applies to claims for monetary damages under the CSPA. Weaver v. Armando‘s, Inc., 7th Dist. No. 02 CA 153, 2003-Ohio-4737, ¶37; Lloyd v. Buick Youngstown, GMC, 115 Ohio App.3d 803, 807, 686 N.E.2d 350 (7th Dist.1996).
{¶13} The dispute in this appeal, which was the same dispute at the trial court level, is about the date of the alleged “occurrence” that triggered the two-year statute of limitations. There is no question that a “transaction” took place starting on September 1, 2006, when the parties entered into the contract to build a home. This transaction continued until the house was built and Appellants occupied it in early 2007.
{¶14} It is at this point that the parties’ arguments diverge. Appellants first argue that the statute of limitations was tolled starting on June 18, 2010, when they sent a letter to M&M Homes about defects in the construction. Appellants sent another letter on September 22, 2010, notifying M&M Homes of the impending lawsuit. Under
{¶16} Whether Appellants tolled or did not toll the statute of limitations on June 18, 2010, does not determine the outcome of this assignment of error. The only significant question under this assignment of error is whether there was an “occurrence of a violation” within two years of October 27, 2010, which is the date the complaint was filed.
{¶18} Appellants’ argument fails for two important reasons. First, we have made it clear that if the allegation is that monetary damages stem from the initial construction or installation, then the two-year statute of limitations in
Appellant also argues that appellees violated the OCSPA by deceiving him when they made assurances that the roof was repaired. However, this contention lacks evidentiary support. The evidence does not demonstrate that appellees gave assurances to appellant that they
repaired all problems with the roof. In fact, appellant‘s affidavit states that Shutrump attempted to fix the roof, but was unsuccessful. Because the evidence demonstrates that the roof was likely improperly installed, any violation of the OCSPA occurred in 1998 when the roof was installed. Again, appellant is time barred by the statute of limitations. Appellant‘s argument that the repairs performed in 2001 also constitute a violation is unsupported by the evidence because the improper installation, not the subsequent repairs, led to the problems with the roof.
Id. at ¶18.
{¶19} Appellants try to circumvent our decision in Rosenow by characterizing Mr. Maley‘s promise as a promise to do new work on their home. Unfortunately for Appellants, there is no evidence of a promise of any kind made by Mr. Maley in the section of the deposition they cite. Appellants refer to pages 39-40 of the deposition three times without specifically highlighting the alleged statements made by Mr. Maley that they claim entitle them to relief. Those two pages are reproduced in their entirety below. Note that Mr. Korff is Appellants’ attorney, and Mr. Marando is M&M Homes’ attorney.
MR. KORFF: Strike that.
Q Was there a point where Mr. Quetot, you instructed Mr. Quetot just to call the subcontractor directly to fix any problems?
A No. I would have given him his phone number if they would have asked. But I didn‘t instruct them to call them. They‘re more than welcome to call me any time. Never do I turn somebody down from calling me, never. Q After 2008, do you remember there being any additional issues with the house that were raised to you?
A Up till present, 2008 up till now you‘re saying?
Q Yes.
A In ‘09, January of ‘09, January or February of ‘09 my partner, who did not work with the Quetots, did not really even know the Quetots, calls me and says, Eric Quetot called asking for the roofer‘s phone number. I believe he gave him the roofer‘s phone number at that time. I wasn‘t even asked to call, but I did. He called me and told me, he said, I just wanted you to know that.
So I called Mr. Quetot and asked him what the problem was. At this time there was about 20 or 20, that was when we had one of those 20- to 24-inch snows. He told me where he was getting a little water in in the, in the laundry room.
And at that point I told him that snow will have to come off of there before a roofer can repair, can look at that. And this was, this was, what, three years he was into the house now, probably three years. Then I received -- I didn‘t hear anything back for probably, it was probably a month and a half, two months. Then I received a letter in the mail demanding that I pay 2900 or $3,000 from the Quetots’ insurance company. There was not contact at all to let me know what was going on.
So I just gave it to my insurance company, and asked them, what should I do? I really wanted to just call up and see if I could fix the problem. But it wasn‘t in that form. It was demanding that I pay this amount of money.
Insurance company says, we‘ll handle it. And then I received a letter from his, or from his attorney. And that‘s up, up till now where we‘re at.
MR. MARANDO: Off the record a second, Geoff.
(Whereupon, a discussion was held off the record.)
Q Okay. You mentioned that there was a --
MR. KORFF: Well, strike that.
Q You said that your partner gave Mr. Quetot the [end of page 40].
(8/24/11 Maley Depo., pp. 39-40.)
{¶21} Because Appellants are claiming relief for damages arising from the initial construction of their home, and because such relief under the CSPA is barred by the statute of limitations in
ASSIGNMENT OF ERROR NO. 2
CLAIMS FOR ATTORNEY‘S FEES AND PUNITIVE DAMAGES MAY BE BROUGHT ON ANY TORT CLAIM, NOT ONLY CSPA VIOLATIONS.
{¶22} In Appellants’ second assignment of error they request that we reverse the trial court‘s decision denying punitive damages and attorney fees for a pending tort claim. The trial court did not deny these fees for the tort claim. The judgment entry stated: “this Court also finds as a matter of law that the Plaintiffs’ claims for
Conclusion
{¶23} Appellants argue that their CSPA claim is not time barred under the two-year statute of limitations in
Vukovich, J., concurs.
DeGenaro, P.J., concurs.
