The defendant at the opening of the trial challenged the sufficiency of the complaint, in that the cause of action is based upon a contract, a copy of which is annexed to the complaint, and that the contract does not sustain the theory of the complaint. The cause of action is for a violation of the contract which is by appropriate reference made a part of the complaint. Where this is done, if there is a variance between the contract and the allegations of the complaint, the terms of the contract must control; therefore, we may disregard the allegations of the legal effect of the contract in the complaint and resort to the contract itself as if it had been set out in the body of the complaint in extenso. (Rubin v. Siegel, 188 App. Div. 636, 638.) The motion to dismiss being in effect an oral demurrer for insufficiency, the question is whether, assuming every fact alleged to be true, enough has been stated to constitute any cause of action. The complaint will be deemed to be sufficient whenever the requisite allegations can be fairly gathered from all the averments, and will be held to state all facts that can be implied from the allegations by a reasonable and fair intendment. (Sage v. Culver, 147 N. Y. 241, 245.) Applying these rules to the complaint, it appears that the defendants are engaged in the banking and brokerage business in the city of New York; that the plaintiff and defendants entered into a contract in writing, wherein it was agreed that certain oil properties in West Virginia therein described were to be acquired at the price of $400,000; $100,000 to be paid in cash and $300,000 in notes bearing six per cent interest payable on or before six months; that the defendants are to form a corporation, to take over the said oil property, with a capital stock of $1,500,000 par value, all of which should be deposited as security for the payment of the $300,000 of notes to be withdrawn and payments to be arranged on account of the notes, if necessary, before they fall due. The defendants are to take
This is the fair and reasonable intendment of the language of the contract. The allegation of damage is predicated upon present value of non-existent stock. This defect is immaterial, as the defendants having interposed an answer, the court may permit the plaintiff to take any judgment consistent with the case made by the complaint and embraced within the issues. (Code Civ. Proc. § 1207.) This contract was not unlawful or
“A party has no right to induce another to contract with him on the supposition that his words mean one thing while he hopes the court will adopt a construction by which they would mean another thing more to his advantage.” (Potthoff v. Safety Armorite Conduit Co., 143 App. Div. 161, 164.)
How much less should the court allow a party to contend that the contract he has himself drawn is unintelligible or insensible. The defendants were sufficiently informed of the cause of action against them to frame their answer and present their defenses. The Code of Civil Procedure has provided a speedy remedy for testing the sufficiency of a complaint by demurrer and bringing the same on for trial as a contested motion. (Code Civ. Proc. §§ 488, 976.) When this is done we feel it our duty to more strictly construe the complaint, for by amendment at small costs the defects in the pleading can be cured, and' the issue presented by the complaint can be made definite without resort to inference, so that the defendant by answer may clearly and intelligently meet the exact issue. Where, however, the defendant is sufficiently apprised of the issue tendered and has made answer thereto and delayed until the case is called for trial, and then challenged the sufficiency of the complaint by motion, we give full force and effect to the rule that the allegations of a pleading must be liberally construed with a view to substantial justice between the parties. (Code Civ. Proc. § 519.) In one case substantial justice requires that a defendant be informed with reasonable exactitude of the cause of action afieged against him (Stabilimento Metallurgico Ligure v. Joseph, 189 App. Div. 173, 177), that he may not be compelled at his peril to correctly interpret the meaning of the pleading and the nature of the issue tendered. In the other, the defendant has not asserted this hazard, but has met the issue tendered by the complaint in his answer, and substantial justice between the parties is better conserved by a liberal construction, giving full scope to every intendment that can reasonably be found from the language used, in an effort
In my opinion the complaint states facts sufficient to constitute a cause of action, and the judgment should be reversed and a new trial ordered, with costs to the appellant to abide the event.
Clarke, P. J., Dowling, Smith and Philbin, JJ., concur.
Judgment reversed and new trial ordered, with costs to appellant to abide event.