Cross appeals from an order and judgment of the Supreme Court (Viscardi, J.), entered October 27, 1998 in Clinton County, upon a decision of the court in favor of defendant R.P. Brosseau & Company and plaintiff Westinghouse Electric Supply Company.
These consolidated actions involve various claims arising out of contracts for electrical work in connection with the construction of the Pyramid Champlain Centre North shopping mall in the Town of Plattsburgh, Clinton County. In early 1987, the owner/developer of the project, Pyramid Champlain Company, entered into three contracts with defendant R.P. Brosseau & Company (hereinafter Brosseau) to furnish and install electrical equipment in two “anchor” stores, Sears and J.C. Penne/s; the third contract covered electrical work within the mall building itself (hereinafter the mall contract). Most of the electrical equipment and supplies required for the project were custom designed and ordered by Brosseau from plaintiff Westinghouse Electric Supply Company (hereinafter WESCO), with the understanding that payment therefor could not be made until Pyramid paid Brosseau.
Brosseau first commenced work pursuant to the Sears contract, dated January 13, 1987, and shortly thereafter entered into and commenced work pursuant to the J.C. Pen
Thereafter, Pyramid commenced action No. 1 against Brosseau alleging, inter alia, breach of contract and willful exaggeration of three mechanics’ liens Brosseau had filed in connection with each of the contracts. WESCO commenced action No. 2 against Brosseau, Pyramid and others seeking collection of unpaid sums due for materials, equipment and supplies delivered and incorporated into the project. Brosseau asserted claims against Pyramid seeking foreclosure of the three mechanics’ liens and damages for, inter alia, breach of contract. The actions were subsequently consolidated for discovery and trial and, following motions and discovery, a 16-day nonjury trial was conducted in 1996. In a written decision issued in 1998, Supreme Court determined that Pyramid breached its contracts with Brosseau by unjustifiably failing to pay the requisitions and was directly liable to WESCO based upon an enforceable oral promise to pay for materials shipped after April 9, 1987. Supreme Court further determined that Brosseau was jointly liable with Pyramid for certain amounts awarded to WESCO. Judgment was entered accordingly, prompting these cross appeals by Pyramid and WESCO.
We first take up Pyramid’s contention that Supreme Court erred in concluding that it breached its three contracts with Brosseau. We note at the outset that although the scope of our review of this nonjury trial is not limited to determining
Dealing first with the J.C. Penney’s and Sears projects, Pyramid’s site controller testified that he was instructed by his project manager to deny Brosseau’s April 25, 1987 and May 25, 1987 payment requisitions on the ground of nonperformance. The testimony established, however, that these projects were substantially completed when Pyramid refused payment: the J.C. Penney’s project was substantially complete by March 21, 1987 and the Sears project was 99% complete by June 10, 1987. That which was not complete on the Sears and J.C. Penney’s contracts was work that could not be performed until other aspects of the project were completed. An inspection conducted by OSHA established that Brosseau’s work was 100% compliant with its inspection standards. Moreover, Pyramid had requested and drawn down funds from the bank funding the project based on the scope of work completed. As noted by Supreme Court, Pyramid produced no evidence to justify its refusal to pay Brosseau the balance due on the Sears and J.C. Penney’s contracts.
As to the malí contract, the record contains ample evidence from which Supreme Court could have concluded that Brosseau’s failure to complete the contracts was the result of Pyramid’s conduct either designed to, or at the very least having the effect of, frustrating its performance. Relying on this evidence, the court concluded that the reasons cited by Pyramid as justifying denial of payment to Brosseau flowed from Pyramid’s own actions rather than Brosseau’s failure to adhere to the contract specifications or supply the requisite number of workers to complete the job in a timely fashion.
As noted, Brosseau’s delay in beginning work on the mall contract was occasioned by Pyramid’s failure to make the site available and to provide necessary drawings and specifications. Throughout the project, Pyramid continually made numerous,
Nor do we find that Supreme Court erred in calculating the damages owed by Pyramid to Brosseau. Having found that Pyramid breached its contract with Brosseau, and crediting Brosseau’s testimony as to the reasonable value of the scope of work performed by the contractor hired to complete the project, Supreme Court explicitly declined to accept Pyramid’s calculations as to the amounts it was entitled to offset against Brosseau. As with other aspects of the court’s determinations clearly based principally on credibility assessments, we find no reason to disturb this finding.
Turning to Pyramid’s contention that Supreme Court erred in dismissing its claims against Brosseau for willful exaggeration of mechanics’ liens filed in connection with the three contracts, Supreme Court properly determined that it lacked the authority to award such damages. Lien Law § 39 provides that “[i]n any action or proceeding to enforce a mechanic’s lien * * * or in which the validity of the lien is an issue”, the court may declare the lien void and deny recovery thereon upon a finding that the lienor willfully exaggerated the amount claimed in the notice of lien. Where a lien has been discharged for willful exaggeration, Lien Law § 39-a authorizes the court to award damages against the lienor. It is well settled that “Lien Law § 39 and § 39-a must be read in tandem, and damages may not be awarded under section 39-a unless the lien has been discharged for willful exaggeration” (Guzman v Estate of Fluker,
Pyramid also contends that Supreme Court erred in finding it directly liable to WESCO based upon its oral promise to answer for Brosseau’s debt. Absent a writing satisfying the Statute of Frauds (General Obligations Law § 5-701 [a] [2]), a promise to answer for the debt of another is enforceable where it is supported by new and beneficial consideration to the promisor, and where the parties intend that the promisor is to become primarily liable on the debt (see, Martin Roofing v Goldstein,
The trial evidence was more than adequate to establish Pyramid’s agreement to assume primary responsibility for the materials shipped by WESCO.
Turning to WESCO’s cross appeal, the principal issue is whether Supreme Court erred in declining to find a principal-agent relationship between Pyramid and Brosseau so as to render Pyramid liable for the full amount of Brosseau’s liability to WESCO. The significance of this issue to WESCO lies in the fact that although WESCO was awarded the full amount of its underlying claim, i.e., $335,415.57, against both Brosseau and Pyramid, its judgment against Brosseau is considerably larger as a result of the inclusion of contractual interest and counsel fees. Thus, while judgment was entered in favor of WESCO against Pyramid in the total amount of $678,961.63, consisting of $335,415.57 on the underlying claim, $340,581.06 in statutory interest and $2,965 in costs and disbursements, WESCO’s judgment against Brosseau is in the amount of $1,219,658.96, comprised of $335,415.57 on the underlying claim, contractual interest of $729,409.39, counsel fees pursuant to the contract in the amount of $152,194, and costs and disbursements in the amount of $2,640. WESCO therefore sought to establish an agency relationship between Pyramid and Brosseau such as would bind Pyramid to all of the terms of WESCO’s contract with Brosseau.
An agency relationship may be established by.conduct, or by written or oral contract (see, Standard Bldrs. Supplies v Gush,
The parties’ remaining contentions have been considered and rejected as without merit.
Cardona, P. J., Yesawich Jr., Peters and Mugglin, JJ., concur. Ordered that the order and judgment is modified, on the law and the facts, without costs, by providing that the sum of $675,996.61 owed to Westinghouse Electric Supply Company is the joint and several liability of R.P. Brosseau & Company and Pyramid Champlain Company, and, as so modified, affirmed.
Notes
. Pyramid did advance Brosseau a small portion of the requisitioned amount so as to enable him to meet his payroll and keep his crews working on the project.
. Contrary to Pyramid’s suggestions in its brief, oar prior determination on this issue (
