Putrelo Construction Co. v. Town of MarcyPutrelo Construction Co. v. Town of Marcy
It is hereby ordered that the order so appealed from is unanimously affirmed without costs.
Memorandum: Plaintiff commenced this action seeking damages for breach of contract in connection with its construction of a new town hall for defendant/third-party plaintiff (hereafter, defendant). Third-party defendant, the successor in interest to the architect who contracted with defendant, moved for partial summary judgment dismissing plaintiff‘s second cause of action, which sought delay damages. Defendant joined in that motion. Supreme Court properly granted the motion based on plaintiff‘s failure to file a notice of claim within the time limitations of
Finally, we reject plaintiff‘s remaining contentions that defendant waived compliance with or is estopped from relying on