215 Ct. Cl. 976 | Ct. Cl. | 1977
"This case is before the court on cross-motions for summary judgment, but the judgment sought by plaintiff is
"Defendant alleges various defenses. It relies on the title recording system of the state to impute prior knowledge of the easement to the plaintiff, but plaintiff says it was affirmatively misled. We can pass this issue by because of another defect in the claim, which defendant also relies on and which is decisive.
"The Lease/Build contract required plaintiff first to obtain title to the site by quitclaim deed of the defendant. It had to have good title to obtain necessary financing from private sources. Financial institutions would not lend in face of the title defect. Therefore, says plaintiff, the
"Plaintiff was given an opportunity, at oral argument, to submit new affidavits clearing up this defect in its proof. They have been filed and considered, and fail to answer the real problem.
"A showing that the defendant’s alleged dereliction could have caused the delay or was capable of doing so is not enough. It must appear that the delay, or at least some significant part thereof, was proximately caused by defendant, i.e., would not have occurred if the delays for which defendant was responsible had been eliminated. Merritt-Chapman & Scott Corp. v. United States, 208 Ct. Cl. 639, 528 F.2d 1392 (1976). Since the defendant’s contract did not embody a disputes clause, the issue formulated itself as a breach claim, whereas the cited case involved a suspension of work clause, but the principles are the same. Even if, as here, the assessment of damages is reserved for the quantum phase of the case, the plaintiff as part of its proof of entitlement, must show it was damaged to some extent, by defendant’s derelictions, and it has failed to do so for the reason stated. One of plaintiffs post-argument affidavits makes the conclusory allegation that plaintiffs losses were the 'direct, sole, and proximate result’ of the existence of record of the channel easement, but the detailed history of the case reveals the contrary.
"Defendant advertised for bids on November 5, 1970, and opened the bids on January 10, 1971. On April 20, 1971, it advised plaintiff an award would be made to it and entered into an 'agreement to lease’ on the same date. Plaintiff was required to pay $373,700.41 for the land, and it was to receive $172,787 per annum for 20 years as rental. Closing was originally to be within 30 days, but the date was repeatedly extended.
"Plaintiff had financing commitments but the leading institutions refused to permit closing until the title was cleared.
"On March 23, 1972, plaintiffs attorney wrote (referring to a conversation of evidently recent date) to the Army Engineers, which had assumed construction responsibility for the project. He stated that areas taken for the channel easement were located under a substantial portion of the proposed building, that lenders were unwilling to close, and that the location (perhaps he meant the exact location) was not known to plaintiff until the preceding week, 'when Gateway Engineers, Inc. indicated same on the Plan.’ He thought the United States could easily obtain extinguishment of the right of way from the Commonwealth of Pennsylvania, since the Plan stated the involved areas were not in use since completion of an arch culvert. Defendant explains the easement was originally taken in 1950 to allow drainage from a state highway and that it had ceased to serve that purpose since installation of an arch culvert in 1965.
"Both plaintiff and defendant were thereafter in contact with the state. Defendant wrote the Pennsylvania Department of Transportation on March 28, 1972. On May 25, 1972, the Pennsylvania District Engineer executed a notice that except for the culvert, the channel easement had become unnecessary and it was, therefore, abandoned. This enabled the closing to take place, as it did, the following day, May 26, 1972.
"Defendant of course had long been aware of the channel easement and plaintiff, as has been said, became aware on May 7, 1971. The letter of March 23, 1972, indicates that until shortly before that date, plaintiff or its counsel had
"Plaintiff would like to have us believe, and hold, that the defendant should have extinguished the channel easement at the time of inviting bids, or before, and that its failure to do so (not having advised plaintiff of the defect before it bid) was a breach of implied obligations, and caused the refusal of the financing institutions to go to closing, the repeated postponements of the closing date, and the delay losses plaintiff suffered.
"It is obvious that the plaintiff at the outset, and throughout, did not ask defendant to remove title defects. It worked on them itself (several others besides the channel easement) and asked for time extensions when difficulty arose with them. It did not ask for defendant’s help on the channel easement, departing from its previous cours^ of dealing, until March 23, 1972, almost a year after the award date. The channel easement was a matter of appearance, not substance. It could have been removed on request at any time. All parties seem to have been late in tumbling to its significance as a stumbling block to early closing.
"It seems clear that responsibility for delay up to March 23, 1972, cannot be imputed to the channel easement itself, whose significance no one realized, and, therefore, it fails as a vehicle for charging defendant with causing that delay. As to the period after March 23, 1972, it appears that on or before April 25 plaintiffs counsel had learned that Pennsylvania would release the channel easement. He asked for a time extension to May 31. The extended time was almost all used, but there is nothing to show Pennsylvania would not have met an earlier deadline. Assuming, however, that it took two months to get a release out of the state bureaucracy, once it was asked for, plaintiff, or defendant at plaintiffs request, could have
"Plaintiff had two other alleged breach claims. One related to an alleged misdescription. The quitclaim deed gave the western property line of the site as 483.73 feet, while the Agreement to Lease gave it as 439.73 feet, but the latter was eventually corrected to agree with the former. This minor discrepancy cannot be rationally said to have caused all or any part of the delay of over a year in effecting a closing. The other relates to the failure of Parkway Terminal Company to complete Turnbull Drive until December 1971, that drive having to be crossed for access to the project site. Defendant says that the drive, even when incomplete, offered no impediment to plaintiffs crossing it, and in any event, plaintiff was not ready to close until long after the drive was completed. We conclude that both these matters lack standing as independent breaches that require consideration even if, as we hold, the channel easement claim fails. Plaintiff hardly attempts to argue otherwise.
"Accordingly, upon consideration of the motions for summary judgment, the briefs, affidavits, and documents submitted in support thereof, and the oral arguments of counsel, it is ordered, that plaintiffs motion for partial summary judgment is denied, defendant’s motion for summary judgment is granted, and the petition is dismissed.”