Purington v. United States

126 Ill. App. 323 | Ill. App. Ct. | 1906

Me. Pbesiding Justice Smith

delivered the opinion of the court.

The Act of Congress of August 13, 1894, provides:

“ That any person or persons making application therefor and furnishing affidavit to the department under the direction of which said work is being or has been prosecuted, that labor or material for the prosecution of such work has been supplied by him or them, payment of which has not been made, shall be furnished with a certified copy of said contract and bond, upon which said person or persons supplying such labor or material shall have a right of action and shall be authorized to bring suit in the name of the United States for his or their use and benefit against said contractor and sureties, and to prosecute the same to final judgment and execution.”

It is urged in behalf of appellants that when a statute gives a new remedy, as does this statute, and directs how the right to the remedy is to be acquired and enjoyed, and how it is to be enforced, the act should be strictly construed and the validity of all acts done under the authority thereof will depend upon a strict compliance with its terms; and this rule is particularly applicable when it is sought to enforce a contract of suretyship. It is claimed that the plaintiffs did not furnish the affidavit until after this suit was commenced.

We think this point is not tenable. As held in American Surety Co. v. U. S. of America, 77 Ill. App. 106, the provision of the act in regard to filing an affidavit has reference only to the procuring of a copy of the bond and contract and is not a prerequisite to the right to maintain the action. Further, we think, the record shows that the affidavit, was filed with the treasury department prior to June 4, 1900, the date of the certificate, for it was upon the affidavit that the certificate was issued. The objection by appellants to the admission of the contract and bond in evidence upon that ground was therefore properly overruled.

The question raised by appellants based upon the failure of appellees to bring in the principals of the bond before proceeding to judgment against the sureties is one of procedure simply. It has no semblance to the statutory proceedings for a mechanic’s lien, as contended by appellants; nor is it governed by any of the rules applicable to mechanic’s lien procedure. This action is a common law action and it is governed by the common law rules of procedure, except as modified by our statute. The Act of Congress above referred to contains no provision or limitation upon the procedure connected with enforcing the bonds provided for by it. That question is left to the practice of the forum in which relief may be sought by the beneficiaries. Under our Practice Act (R. S., chapter 110, sec. 10) where one or more, but not all of the defendants are served, the plaintiff may proceed to trial and judgment against the defendants upon whom process is served and may afterwards proceed by scire facias to make the others parties to the judgment. Under this practice the proceedings were regular.

Considerable stress is laid in argument upon the point that covenant will not lie on an instrument not properly sealed. It is assumed in making this point that the contract between L. L. Leach & Son and McNulty Bros, is the instrument declared on in this case. Counsel are in error in this assumption. The defendants’ bond to the United States is the instrument declared upon.

It is urged, upon the merits, that appellees’ work was not completed by them to the satisfaction of the supervising architect or the principal contractors. The ground of this contention is that the walls were dirty, stained and discolored. The evidence shows that this was due to the careless manner in which L. L. Leach & Son used the furnaces, salamanders and stoves which they placed in the building for heating purposes. The evidence abundantly sustains the verdict of the jury on this question, and we cannot disturb it.

The contract between Leach & Son and the McUultys provided that the former should pay the latter the balance of the contract price when the Leaches had received full payment from the United States. It appears from the final voucher signed by L. L. Leach & Son that the Government made deductions on the work amounting to $982. This amount deducted from the contract price of $164,550 plus the additions thereto amounting to $3,273.10, made $166,-841.10, the total amount which Leach & Son were entitled to.receive for the work. They had been paid $166,815.10, leaving a balance due them of $26, which they receipted for in full payment. The contract contained a provision whereby the department reserved the right to make any additions to, omissions from or changes in the work and material, the value of which was to be determined by the supervising architect upon the basis of the contract unit or prevailing market rates. Under this provision of the contract the changes resulting in the foregoing figures were made and adjusted. It is, therefore, evident that Leach & Son had received full payment from the Government for the work contracted for by them, and that appellants’ contention to the contrary is without basis in the proofs.

The questions arising on the demurrers to replications are not argued and are, therefore, waived.

We find no reversible error in the record and the judgment is accordingly affirmed.

Affirmed.