delivered the opinion of the Court.
On June 15, 2000, Tim L. Peckinpaugh and Pamela S. McKinney-Peckinpaugh (the Peckinpaughs), owners of a home in Wheat-land Estates, Fairfax County, filed an amended motion for judgment against Pulte Home Corporation (Pulte), builder of the home, for damages allegedly caused by Pulte’s use of a defective synthetic stucco product known as “Exterior Insulation and Finish System,” or “EIFS.” 1 Parex, Inc. (Parex), the manufacturer of the EIFS, was also named as a defendant. The Peckinaughs sought damages of $500,000 from Pulte and Parex to cover the cost of removing the synthetic stucco, installing new exterior siding, and repairing the damaged property.
Also on June 15, 2000, Pulte filed a cross-claim against Parex. In separate counts, Pulte asserted claims for breach of express warranty, breach of implied warranty, indemnification, and contribution. 2 In each count, Pulte sought recovery from Parex for any damages that Pulte might be required to pay the Peckinpaughs, plus costs, interest, and attorney’s fees. 3
*522 Pulte filed a demurrer to the Peckinpaughs’ amended motion for judgment, and Parex filed demurrers to the Peckinpaughs’ amended motion for judgment and to Pulte’s cross-claim. The demurrers were argued before the trial court on September 28, 2000. With respect to Pulte’s demurrer to the Peckinpaughs’ amended motion for judgment, the trial court orally overruled the demurrer and entered a written order embodying that ruling.
With respect to Parex’s demurrer to the Peckinpaughs’ amended motion for judgment, the trial court sustained that demurrer. With respect to Parex’s demurrer to Pulte’s cross-claim, the trial court orally sustained the demurrer as to each count, except the count for breach of implied warranty, which the court took under advisement. Later in the day on September 28, 2000, the court entered an order sustaining the demurrer to the count for implied warranty.
On October 18, 2000, Pulte sought by motion to have the trial court reconsider its action on the demurrers but was unsuccessful in the effort. Pulte then settled the Peckinpaughs’ claim. It does not appear from the record, but Pulte states on brief and Parex does not deny, that the Peckinpaughs assigned to Pulte their claim against Parex. Pulte stated during oral argument that it is not asserting any rights as an assignee in this appeal. 4
An order sustaining Parex’s demurrer to the counts in Pulte’s cross-claim for breach of express warranty, indemnification, and contribution was entered on March 2, 2001. The proceeding was terminated by a final order entered on May 20, 2002. Thereafter, we awarded Pulte this appeal.
Pulte has filed four assignments of error, attacking in order the sustaining of the demurrer to the cross-claim counts for breach of express warranty, breach of implied warranty, indemnification, and contribution. The sole question for decision is whether the trial court erred in sustaining Parex’s demurrer to Pulte’s cross-claim.
I. Breach of Express Warranty
Pulte argues that, in its cross-claim, it “pled its breach of express warranty based on two separate theories.” First, it alleged in the *523 cross-claim that, to the extent it approved the use of EIFS on the Peckinpaughs’ house, such “approval was based upon the express oral or written warranties of Parex by way of affirmations of fact, promises, descriptions, and/or use of samples and/or models regarding the appearance, durability, and/or water-resistance of [EIFS].” Second, Pulte alleged in its cross-claim that it was entitled to recover as a direct and/or intended beneficiary under written limited warranties provided by Parex to the subcontractors and supplier.
Pulte maintains that, in sustaining Parex’s demurrer, the trial court engaged in “raw fact finding,” erroneously “determining that there was ‘no express warranty’ ” and that “no [written limited] warranties existed.” For this error, Pulte concludes, the judgment of the trial court should be reversed.
We disagree with Pulte. Before demurring to Pulte’s cross-claim, Parex filed a motion referencing the allegations in the cross-claim with respect to oral and written express warranties and craving oyer. The motion sought “any alleged contract or agreement and any alleged express warranty forming the basis” of the count for breach of express warranty in Pulte’s cross-claim. Pulte responded that it was “not yet in possession of any written contract entered into by Parex, nor any written warranty issued by Parex” but would soon serve requests for documents upon Parex, the subcontractors, and the supplier.
Hence, Pulte was left with the naked allegation in its cross-claim that its approval of the use of the EIFS was based upon the express oral or written warranties of Parex “by way of affirmations of fact, promises, descriptions, and/or use of samples and/or models regarding the appearance, durability, and/or water-resistance of [EIFS].” This allegation merely parroted the language of Code § 8.2-313, which sets forth several
legal
bases for the creation of express warranties, and amounted to no more than a legal conclusion.
5
The cross-claim did not identify any “affirmations of fact, promises, descriptions, and/or use of samples and/or models” purportedly made by Parex. The allegations of the cross-claim were insufficient, there
*524
fore, to state a claim for breach of express warranty. Rule l:4(d);
see also Moore v. Jefferson Hospital, Inc.,
II. Breach of Implied Warranty 6
Whether the trial court erred in sustaining Parex’s demurrer to Pulte’s claim for breach of implied warranty turns on whether the damages for the alleged breach are direct or consequential. Parex contends the damages are consequential and not recoverable in the absence of privity between Pulte and Parex. Pulte does not claim privity exists but contends the damages at issue are direct and recoverable despite the lack of privity. 7
In its order of September 28, 2000, the trial court stated that it was sustaining Parex’s demurrer to Pulte’s count for breach of implied warranty “based upon the ruling in
Beard Plumbing and Heating, Inc. v. Thompson Plastics, Inc., et al.,
Is privity required to recover economic loss under Va. Code § 8.2-715(2) due to the breach of the implied warranty of merchantability, notwithstanding the language of Va. Code § 8.2-318?
We said that to “answer this question, we must first determine whether § 8.2-715(2) requires the existence of a contract for the recovery of economic loss damages in breach of warranty cases.”
Consequential damages resulting from the seller’s breach include
(a) any loss resulting from general or particular requirements and needs of which the seller at the time of con- *525 trading had reason to know and which could not reasonably be prevented by cover or otherwise[.]
We said that because the Court of Appeals had directed its inquiry specifically to this section, we would assume the court had concluded that the economic loss damages claimed by Beard were consequential damages rather than direct damages.
We then turned to the question whether the provisions of § 8.2-318, also referenced in the certified question, supersede the contract requirement of § 8.2-715(2)(a). Section 8.2-318 provides in pertinent part as follows:
Lack of privity between plaintiff and defendant shall be no defense in any action brought against the manufacturer or seller of goods to recover damages for breach of warranty, express or implied, or for negligence, although the plaintiff did not purchase the goods from the defendant, if the plaintiff was a person whom the manufacturer or seller might reasonably have expected to use, consume, or be affected by the goods[.]
We stated that because § 8.2-715(2)(a) addresses in a specific way the subject of the ability to raise the common law requirement of privity as a defense and § 8.2-318 addresses the subject in a general way, § 8.2-715(2)(a) prevails. We stated further that “because § 8.2-715(2)(a) requires a contract between the parties for recovery of consequential economic loss damages in a claim for breach of the implied warranty of merchantability, we answer the certified question in the affirmative,”
Here, Pulte argues that the trial court misapplied this Court’s opinion in Beard. That case dealt only with consequential damages, not direct damages, Pulte maintains, yet the trial court cited Beard in ruling that privity is required not only to assert claims for consequential damages but also to assert claims for direct or non-consequential damages.
*526 Pulte cites a passage from the record to show that the trial court made such a ruling. During oral argument on Parex’s demurrer on September 28, 2000, the trial judge stated he was taking under advisement the question whether the damages in question were direct or consequential and that he would “have an answer on that this afternoon.” One of the counsel then stated that “the Beard case doesn’t address whether the anti-privity [rule] does apply to direct damages” and “[t]hat will have to be part of your ruling.” The judge replied: “You are right. Thank you.” This indicates, Pulte says, that when the trial judge entered the order that afternoon sustaining Parex’s demurrer based upon Beard, such entry meant that the judge had held the requirement of privity applicable to both consequential and direct damages.
We do not read the record this way. Since the trial judge cited Beard, it will be presumed that he had read our opinion, understood that the case involved only consequential damages, and applied our ruling correctly. Without some indication the trial judge acted otherwise, we can only conclude that his reference to Beard meant he found the damages in this case, like those in Beard, to be consequential, not direct, and, as a result, there could be no recovery for Pulte without privity between it and Parex.
Pulte maintains that if the trial court did determine that the damages at issue were consequential, its determination was inappropriate because made at the demurrer stage and “this was the wrong point in time.” Pulte says that in its cross-claim it specifically requested “direct damages under Section 8.2-714(2) of the Virginia Code, together with consequential damages to the extent available by law.” This was sufficient, Pulte concludes, to save its claim for direct damages from dismissal on demurrer, and it was “entitled to have [its] day in court on that issue.” 8
We disagree with Pulte. Whether damages are direct or consequential is a matter of law for decision by the court.
R.K. Chevrolet, Inc. v. Hayden,
With respect to Pulte’s argument that its claim for direct damages should have survived demurrer merely because it requested such damages in its cross-claim, the trial court during argument appropriately observed that just saying damages are direct does not make them direct. The allegations of the cross-claim leading up to the request disclose the true nature of Pulte’s damages as consequential. These allegations read as follows:
In the event [Pulte] is found liable to [the Peckinpaughs] or otherwise incurs any loss whatsoever as a result of [the Peckinpaughs’] allegations, [Pulte] is entitled to recover from Parex for the breach of said implied warranties insofar as Parex’s breach would be the factual and proximate cause of all or part of [Pulte’s] loss.
WHEREFORE, [Pulte] demands payment from Parex for any damages that [Pulte] may be required to pay [the Peckinpaughs] and for any other loss that [Pulte] consequently may incur ....
In other words, Pulte would suffer damages from Parex’s breach of warranty only upon the happening of an intermediate event, i.e., Pulte being found liable to the Peckinpaughs for the damages they suffered. Hence, by their very nature, Pulte’s damages would be consequential rather than direct.
“The term ‘consequential damages’ is thus defined in Black’s Law Dictionary: ‘Such damage, loss, or injury as does not flow directly and immediately from the act of the party, but only from some of the consequences or results of such act.’ ”
Washington & Old Dominion Ry. Co. v. Westinghouse Elec. & Mfg. Co.,
Pulte’s damages fit into this definition like a hand in a glove. They did not flow directly and immediately from the act of Parex’s breach of warranty but from a consequence of the Peckinpaughs’ recovery of damages from Pulte. Indeed, Pulte acknowledges that it is entitled to recover only on some “sort of a pass through.” Since such a detour is required to get from Parex’s breach of warranty to Pulte’s damages, those damages cannot be considered as direct but *528 consequential, with a showing of privity necessary for their recovery. There has not been such a showing in this case.
III. Indemnification
Pulte states that its claim for indemnification “is based on the theory that any liability incurred by [Pulte] ‘would be derivative, constructive, passive and/or secondary, while the acts and omissions of [Parex] would be the active, direct and primary cause of Plaintiffs’ damages.’ ” Pulte says it is entitled to implied or equitable indemnification because it is called upon to discharge the obligation of Parex, the party primarily liable for the Peckinpaughs’ damages. Yet, Pulte complains, the trial court denied its claim for implied or equitable indemnity because the court erroneously relied upon
Virginia Elec. & Power Co. v. Wilson,
Pulte maintains that the statement in
Wilson
is “pure dicta,” that the case involved contribution, not indemnification. However, the statement is not dicta; the Court stated that it had granted the appeal “to determine if Vepco . . . has a right of contribution or
indemnity
against Wilson,”
id.
at 980,
However, Pulte argues,
Wilson
is not controlling because this Court held in
Carr v. The Home Ins. Co.,
So, whether Wilson or Carr is applied, Pulte loses either way. It cannot win under Wilson because the claim for indemnification did not arise out of a contractual relationship, and it cannot win *529 under Carr because there has been no determination that any act or omission of Parex caused the damage to the Peckinpaughs’ house.
IV. Contribution
Pulte initially said on brief that its claim to contribution was based upon Code § 8.01-34, which provides that “[contribution among wrongdoers may be enforced when the wrong results from negligence and involves no moral turpitude.” Countering, Parex stated that it cannot be deemed a joint tortfeasor with Pulte and, therefore, Code § 8.01-34 is inapplicable.
Apparently conceding the point, Pulte now says that, “even if Parex were not a joint tortfeasor,” this Court recognized in
Thweatt’s Adm’r
v.
Jones, Adm’r,
We agree with Parex. In
Virginia Elec. & Power Co. v. Wilson, supra,
we emphasized that “
‘before contribution may be had it is essential that a cause of action by the person injured lie against the alleged wrongdoer from whom contribution is sought.’
”
The trial court’s action in sustaining Parex’s demurrer to the Peckinpaughs’ amended motion for judgment was tantamount to a holding that the Peckinpaughs never had an enforceable cause of action against Parex. 9 Hence, there is no joint liability for the Peck *530 inpaughs’ claims as between Pulte and Parex, and Pulte’s claim for contribution against Parex does not lie.
V. Conclusion
Finding no error in the rulings of the trial court, we will affirm its judgment.
Affirmed.
Pulte states it is the implied warranty of merchantability that is at issue in this case.
Notes
The Peckinpaughs alleged in their amended motion for judgment that the EIFS was defectively designed and applied, causing undue amounts of moisture intrusion into the structure of their home, without means of escape, in turn causing wood to rot and decay.
Originally, the cross-claim also contained a count for breach of contract, but Pulte later abandoned that count.
Pulte makes the assertion on brief that “[o]ne item of damage sought by [Pulte] is the lost value of the stucco goods received from Parex . . . (i.e. the lost value of a defective product). App. 13.” However, this claim cannot be found on Page 13 of the appendix; that is a page in the Peckinpaughs’ amended motion for judgment related to an entirely different matter. But the claim cannot be found in the cross-claim either.
The owners of fourteen other homes built by Pulte filed similar separate actions against Pulte and Parex for damages caused by the use of EIFS. Those cases are not before us, but Pulte states in a footnote to its brief that the cases “followed a similar path, with the plaintiffs settling their claims with [Pulte] and assigning their remaining claims against [Parex] to [Pulte],” and that Pulte and Parex agreed that Pulte “would non-suit its assigned claims against Parex in the other cases pending the outcome of this appeal . . .
Code § 8.2-313 provides in pertinent part as follows:
(1) Express warranties by the seller are created as follows:
(a) Any affirmation of fact or promise made by the seller to the buyer which relates to the goods and becomes part of the basis of the bargain ....
(b) Any description of the goods which is made part of the basis of the bargain
(c) Any sample or model which is made part of the basis of the bargain ....
Pulte did not purchase the EIFS from Parex. Rather, Pulte engaged a subcontractor to apply the EIFS, the subcontractor obtained the EIFS through a supplier, and the supplier purchased the EIFS from Parex.
Code § 8.2-714(2) provides that “[t]he measure of damages for breach of warranty is the difference at the time and place of acceptance between the value of the goods accepted and the value they would have had if they had been as warranted, unless special circumstances show proximate damages of a different amount.”
In a last-ditch effort to demonstrate that the Peckinpaughs have an enforceable cause of action against Parex, Pulte says that the Peckinpaughs “alleged facts that supported an unasserted claim against Parex for false advertising, in violation of Va. Code § 18.2-216,” and that the same allegations in the fourteen companion cases withstood demurrers by Parex. However, *530 Pulte does not tell us what facts support the unasserted claim, where they can be found in the record, or how we can even consider, let alone find determinative, what happened in cases not before us.