28 Mo. App. 666 | Mo. Ct. App. | 1888
delivered the opinion of the court.
This is an action by a firm of subcontractors against the principal contractor, for the erection of a building, and also against the owner of the building and premises, to recover a balance due for work and labor done, .and materials furnished, in the erection of the building under a contract with the principal contractor, and also to enforce a lien for such balance upon the building, and the land on which it is situated. The principal contractor, Hoffman, answered with a general denial; the owner of the building and premises, McManus, filed a separate answer, portions of which were stricken out; so that, upon the issue raised by a reply to the remainder, the questions were raised which we are called upon to consider. The case was referred, by consent, to .a referee, to try all the issues of law and fact. The
I. One of the grounds upon which the validity of the plaintiffs’ lien is assailed is, that it was not shown that the last item of work done b^ them under their contract with Hoffman was done within four months before their claim of lien was filed. It is a sufficient answer to this that there was substantial evidence, including an admission of the appellants’ counsel, in support of the conclusion of the referee that the last item of the work was done within four months of the-filing of the claim of lien.
II. The next objection is, that the account filed with the claim of lien mingles together items for which the law gives a lien with items for which the law gives no lien. The item which constitutes the principal specification under this objection is an item of ninety-six dollars for illuminating tiling. Touching this item the referee found, under the evidence, that the illuminating tiling went into the front of the building, in the vestibule of the door, in the rear of the front sill, and also extended from the south line of the building about four feet into the sidewalk. There was also evidence tending
III. A second specification, which we understand the appellants intend to rank under the same objection, is an item of one dollar and eight cents, for five anchors, and another item of four dollars for thirty ventilators. It is admitted that neither of these items went into the building. But the referee finds that these items were inserted in the account filed with the claim of lien by a mere mistake, and he justly concludes, on the authority of Allen v. Mining Company (73 Mo. 688, 692), that such a mistake ought not to vitiate the whole lien. It may be added that this conclusion is unassailable, for the further reason, as stated in the opinion of this court, in Johnson v. Building Company (23 Mo. App. 546, 549), that these were items for which a lien might have attached, and that they were clearly severable from the rest of the account, and not mingled with other items so as to be incapable of separation. They are, therefore, not within the rule in Nelson v. Withrow (14 Mo. App. 270), and cases there cited, but are within the rule in Kershaw v. Fitzpatrick (3 Mo. App. 575), reaffirmed on this point in Johnson v. Building Company (supra), where it was said that, where an objectionable item can be separated from the other part of the account, the lien may stand.
IV. Objection is made to certain items in the account filed with the claim of lien, which were for materials not called for in the original contract between the owner and the principal contractor, but which were what are called in the language of building contracts “ extras.” It is not claimed that these were not furnished under a contract between the principal contractor and the owner; but the argument, as we understand the force of it, is, that as they were not called for in the
V. In fixing the amount for which the plaintiffs were entitled to their lien, the referee ruled, against the contention of the plaintiffs, that the decision of the Kansas City Court of Appeals in the case of Henry v. Hinds (18 Mo. App. 497), the same not being in conflict with any decision of this court or of the Supreme Court, was binding upon him as judicial authority. We are of opinion that, under, the appellate court system, as at present organized in this state, this is the correct view. We do not understand the plaintiffs as challenging this view, but they do challenge .the correctness of that decision and argue that it does not express the law of Missouri. It was there held that, after the owner pays the principal contractor the full contract price, in good faith, without knowledge of the demand of a subcontractor, and the money so paid actually goes to the satisfaction of claims for work done and materials furnished on the building, it is, in legal effect, the same as if the defendant had paid the contract money directly for the work and materials to the subcontractor, and that the property cannot thereafter be subjected to the lien of the subcontractor. As the referee has found in favor of the plaintiffs for all they claim. and awarded them a lien accordingly, and as the court has confirmed this finding
It is so ordered.