delivered the opinion of the court:
This is an appeal from.the judgment of the circuit court of Sangamon county affirming an order of the Public Utilities Commission granting the right to construct a switch or spur-traclc across the highway known as East street, in the town of Anchor, in McLean county, Illinois.
This cause has heretofore been before this court on appeal from the judgment of the circuit court of Sangamon county dismissing- an appeal on the question whether an order of the Public Utilities Commission could be appealed from. (Public Utilities Com. v. Thedens,
The original petition was filed by the Illinois Central Railroad Company in January, 1914, praying the Public Utilities Commission to grant it permission to construct a side-track across the public highway known as East street, in Anchor township, unincorporated. The petition alleged the location of the side-track and that it has been partly constructed and that the highway commissioner of Anchor township objected to the location of the same; that the elevator to which it was proposed to construct said side or spur-track, when open for business, would be a public elevator having a capacity of some 60,000 bushels of grain, and that when said track was constructed grain could be loaded into cars with great expedition from the elevator; that the elevator is located several hundred feet from any track now at Anchor station and that grain has to be hauled in wagons from the elevator to the station for loading; that there is a great public demand for grain and for facilities for handling it, and that the method of carrying and loading grain from the elevator to the railroad delays the movement of the grain and the use of cars for that purpose at the station. Hans Thedens, highway commissioner of Anchor township, who was made a party to this proceeding, filed an answer denying that the building referred to was a public elevator but averring that it was only a large corn-crib, and further alleged that the car shortage, would not to any extent be relieved by the construction of a switch-track to the elevator; that without crossing the highway the elevator could be approached by a switch on the land of D. B. Stewart, who was made a party to the proceedings and who owned most of the farm land in that vicinity. He further answered setting out the proceedings in an injunction suit in the circuit court of McLean county brought by the highway commissioners against Stewart to restrain him from constructing a side-track across the highway, (Town of Anchor v. Stewart,
The evidence taken on the hearing before the Public Utilities Commission shows that Stewart owns a large farm surrounding Anchor, which annually produces about 15,000 bushels of grain; that he originally constructed the building here in question as a corn-crib and a bin to store oats; that he has converted it into an elevator with a capacity of 60,000 bushels of grain and has been taking steps to operate it, when he shall obtain facilities for loading, as a public elevator subject to supervision by the Public Utilities Commission; that it is impracticable to locate a sidetrack to this elevator in any place except that now proposed without extensive changes in the existing side-track and stock pens of the Illinois Central Railroad Company at Anchor. ' The evidence tends to show that the most fear sible location for the side-track to the elevator is that proposed in this proceeding; that the highway commissioners of Anchor township had knowledge of the location of this track and made no objection thereto until a personal dispute arose with the stockholders and officers of the Farmers Elevator Company, located at Anchor; that Thedens was, when these proceedings were instituted, highway commissioner and also an officer in the Farmers Elevator Company; that the evidence tends to show that many of the stockholders of the Farmers Elevator Company are opposing the construction of this side-track to Stewart’s building, as argued by counsel for appellee, because of the fear of the competition that will result from the operation of an elevator by Stewart. The testimony offered on behalf of appellee shows, without serious contradiction, that a sidetrack can be located across the highway at grade in such way as not to interfere with travel thereon; that it is proposed to deliver cars from the elevator across the highway with a tractor, which cannot be operated at to exceed three or four miles per hour, or with pinch-bars; that the most serious objection urged by the highway commissioner is that the cars would be moved across the highway from the elevator to the railway by a tractor; that the only obstruction shown to the view of travelers upon the highway is a hedge growing on the side of the highway nearest the elevator, which the highway commissioner testified afforded some obstruction and which other witnesses testified would not materially obstruct the view. The testimony of Stewart was to the effect that if requested by the commission he would cut down the hedge so that the view on the highway would be wholly unobstructed at this point. The evidence tends to show that a large number of grain growers in this locality desire to use this elevator when the spur-track is constructed and that it would afford business to the Illinois Central Railroad Company, and that the side-track, when constructed, would facilitate the operation of its road and be a public convenience to the community. Appellant attempted to show on the hearing before the Public Utilities Commission that it would be practicable to construct a spur-track to certain land of Stewart’s upon which an elevator could be constructed without crossing the highway, by extending the side-track now located and connecting the main track of the railroad with the stock pens of the railroad company, while the evidence for appellee was to the effect that if the track were so constructed it would cost far more to move the cars to and from the railroad to the elevator at that point than it would on the proposed location of the side-track and Stewart’s elevator.
It is argued by counsel for appellant that there is no authority to construct the side-track across this highway because the record shows that it is to be constructed solely for the private use of Stewart, and also that the track can not cross said highway without the permission of the highway commissioners being first obtained, and in any event cannot be so constructed because of this court’s decision in the former injunction proceedings in Town of Anchor v. Stewart, supra. Paragraph 5 of section 20 of the Railroad and Warehouse act authorizes any railroad company chartered under the provisions of said act to construct a railway, and also to construct it across a public highway in the State, when the public highway is not located in an incorporated town or village, without the authority or consent of the highway commissioners. (County of Cook v. Great Western Railroad Co.
We do not consider the case of Koelle v. Knecht,
Prior to the enactment of sections 45 and 46 of the Public Utilities act there was no means provided for giving to one shipper the joint use of an industry track which another had constructed for his exclusive use. Said provisions of the act were evidently designed to remedy this among other defects in the then law of the State and commit the whole subject to the control of the Public Utilities Commission and provide for an equitable division of the cost of maintaining and operating such track. The evidence in this record tends to show that the side-track in question was to be constructed at the expense of the Illinois Central Railroad Company where it was to be laid on the company’s own land and from that point to the elevator was to be constructed at the expense of Stewart, and he was to be responsible for any damages that might arise from accidents occurring on his land. It manifestly appears from the reasoning of this court in the decisions already cited, that side-tracks constructed under such conditions become a part of the public railway system with which they are connected, and it plainly appears from the Public Utilities act it was intended that both the railway company and the public elevator connected by a spur-track with the railway company’s main track should be subject to the control of the Public Utilities Commission. (Public Utilities Com. v. Lake Erie and Western Railroad Co.
It is argued most earnestly by counsel for appellant that the finding of the Public Utilities Commission that the railroad company may cross the highway in question is in conflict with the decree rendered by the circuit court of McLean county in Town of Anchor v. Stewart, supra. An examination of the opinion in that,case seems to show that no issue there decided is involved here. The bill filed in that case was based upon the theory that Stewart, without permission of the highway commissioners., was about to obstruct a public highway by building a railroad track across it. The prayer of the bill was for a temporary writ of injunction, which was granted and subsequently made permanent, and the only question passed upon was whether the public highway was about to be obstructed without consent. The bill in that case was filed January 5, 1914, and the act therein complained of occurred before the Public Utilities act became effective, January 1, 1914, so the right of the Public Utilities Commission to grant permission to the Illinois Central to construct a track across the public highway was not involved or adjudicated, because there was no attempt to exercise power or authority under the Public Utilities act. If it be conceded the town of Anchor had the power or right to interfere with the Illinois Central Railroad Company in constructing its track across the public highway before the Public Utilities act was enacted, it also had the power to consent to the construction thereof through the highway commissioners; but under the Public Utilities act whatever power the highway commissioners may have had in that regard was taken from them and passed to the Public Utilities Commission. (Chicago, Burlington and Quincy Railroad. Co. v. Cavanagh, supra.) The bill for injunction in the case heretofore referred to, alleged that an obstruction was about to be imposed upon the highway without the permission of the highway commissioners. Even if it be conceded that this court held in that case that the side-track could not be so located by Stewart without the consent of the highway commissioners, it can not be so held under the construction given to the Public Utilities act in the cases just cited. At the most it can only be held that the injunction in that case restrained Stewart from building the track without the consent of the proper authorities. That is not the situation here. Furthermore, in order to have the opinion in that case binding in this proceeding it must be shown that the parties in that proceeding and in this, as well as the subject matter, are the same. This court said in Chicago Theological Seminary v. People,
It would appear, also, that there is another reason why the judgment of the circuit court in the injunction case would not be binding here. While it is true that everything filed of record in the circuit court and the Supreme-Court in that case is binding upon the parties in that case as an estoppel, the failure to file the remanding order within two years operated as an abandonment of the suit and a wiping out or cancellation of the injunction under the provisions of section 114 of the Practice act of this State. (Hurd’s Stat. 1919, p. 2296.) It appears from the record and briefs in this proceeding that the transcript of the judgment in the injunction proceedings has never been filed in the circuit court of McLean county, and therefore, under the reasoning of this court in construing said statute, that judgment no longer affects or binds the actual parties thereto, Koon v. Nichols,
Counsel for appellant further argue that the order of the Public Utilities Commission granting leave to build the track across the public highway is not warranted by the evidence. Section 68 of the Public Utilities act provides that the findings and conclusions of the commission on questions of fact shall be held prima facie to be true as found by the commission; and the same act also provides that a rule, regulation, order or decision of the commission shall not be set aside unless it clearly appears that the findings of the commission were against the manifest weight of the evidence presented to or before the commission for and against such rule, regulation, order or decision, or that the same was without the jurisdiction of the commission. (Public Utilities Com. v. Toledo, St. Louis, and Western Railroad Co.
The judgment of the circuit court will be affirmed.
Judgment affirmed.