*3 BAZELON, Bеfore LEVENTHAL and ROBB, Judges. Circuit Opinion Court by for the filed Circuit Judge LEVENTHAL.
Dissenting opinion Judge filed Circuit ROBB.
LEVENTHAL, Judge: Circuit In this review an order of the case we (FPC). The or- Federal Power Commission der is one for a approves a certificate gas natural under the cer- producer indicated, program. tificate As we vacate the order for further and remand considera- successor, tion by the FPC’s the Federal (FERC).1 Energy Regulatory Commission AN OVERVIEW must, Since our discussion of issues necessity, extended, we technical provide a preliminary opin- sketch of this ion’s highlights. developed reg- FPC has a mimber of Solomon, Richard A. Washington, C.,D. ulatory programs alleviating aimed at Schiff, Counsel, with whom Peter H. Gen. gas shortage. Starting’in natural Public Service Commission State of N. here, FPC developed the involved
Y., Y., brief, Albany, N. on the was program. Option- certification petitioner. producers al gave favorable Garten, Atty., Allen M. Federal Energy procedures standards and rate as an incen- Com., Washington, C., Regulatory D. exploration with tive to increase their and devel- Counsel, Journey, whom Drexel D. opment Gen. sources. gas of new Perdue, Deputy Counsel, W. upheld procedures. Robert Gen. re- program’s Tuttle, Sol., standard, and Allan Abbot Federal Ener- manded the which program’s Com., C., gy Regulatory Washington, D. had used a “test basis year” instead of brief, respondent. requisite were on the data.2 actual cost Energy Regulatory cy points 1. The Federal Commission under review. At where Act the 1977 Department Energy has affected our created discussion we have its § noted impact. Organization Act of 42 U.S.C.A. (West 1977). provided appeals The act 2. Moss v. prior taken to the stаtute were to continue as (1974), part, cert. denied though 705(c), it had not been enacted. Id. § L.Ed.2d rev'd 7295(c) (West 1977). 42 42 U.S.C.A. § part, appeal prior events involved in this occurred S., (1976); Inc. v. Union of U. Consumers passage of the act. For convenience we refer agen- the Federal Power as the However, acreage. insofar explanation, adequate Without (at low- anyway would be leased acreage stan- optional certification adopted an bids), it is hard to see how inclusion rates that er approve it will dard under gas supply. such would increase cost of the total producers return Again, Commission has advanced incompati- find standard projects. We justification. The Commission cannot any its asserted aim respects ble several justifica- development. just shrug requirement off the increasing exploration and agency man- is another federal the standard because problem The chief indepen- has an ages leasing. main rate- It FPC’s offshore with the not coordinated national con- ratemaking. dent consider responsibility its making procedure, takes care of already statutory cerns duties. ratemaking National which relate reim- projects; in the reasoned engage The FPC by their inclusion *4 projects bursed for such necessary to formulate and consideration Optional average cost base. in the national remand, its rate standards.3 On it justify producers a reimburse would engage in opportunity will the such have time, high same cost directly, for the second consideration. with na- any without coordination projects, plain is thus a There ratemaking. tional I. THE OPTIONAL CERTIFICATION consum- counting” billing risk “double — PROCEEDINGS may high same costs. It twice for the ers authority permit that FPC the Development A. Certification Optional a consumers as such a double burden on Standards discretion, it but reasonable exercise of begin there is deliber- We with the must at a minimum show a brief review of discretion, origin by identifying changes and in the ate exercise of certifica- approach. for its tion its reasons problem, program.
This
has not done.
7(e)
Act of
Under
§
the Natural
1938,15
the costs now
issues
The allowance of some
717f
FPC
U.S.C. §
“total cost” standard
public
included in the
certificates of
convenience and neces-
so,
This
projects.
gas. To do
simply
sity
bail out
cost
for new sales of natural
an incentive
charged
the rates
rather than
must approve
means windfall
already
Since the
existing projects
particu-
those sales.4
task of
as
producer’s
sales was too
part
scrutiny
that
larized
of individual
sunk. We note
spent
burdensome,
adopted
this
were
in the 1960’s
total costs in
case
1960’s,
Supreme
practice, approved by
certifica-
long before this
Court,
issuing
If
is a
without
program was envisioned.
there
7 certificates
close to
scrutiny
it has
such
rates
justification
existing projects,
particularized
as to
contemporary
authorized under
A
rates
not been advanced
the Commission.
Act,
717c
provision
and 5 of
15 U.S.C.
objection
§§
§§
different
arises as
FPC would
(1976).5 Generally, the
outlays to
on 717d
projects whereby
for new
bid
refund
subsequently require
in total
offshore
are included
costs.
leases
However, re-
way.6
may
an incentive to bid rates certified in this
give producers
This
Prop
Callery
problems
Improvement
in-
v.
argues
5.
3.
that
same
United Gas
Co.
Petitioner
erties,
Inc.,
pro-
special relief
88 S.Ct.
volved
are
U.S.
here
involved
merit,
(1965).
ceedings.
Federation
argument
L.Ed.2d
While the
has some
See Consumer
express
opinion about the
v.
we need not here
America
validity
proceedings.
n.
515 F.2d
cert.
standards
356 n.
such
96 S.Ct.
46 L.Ed.2d
Refining
Public Service
4. Atlantic
Co. v.
Co.,
Comm’n,
Sunray
6.
DX Oil
L.Ed.2d 388
did not state what stan-
ordered,
No. 455
Order
occasionally
funds were
determining the rea-
would be used in
dard
uncertainty.7
in some
were left
ducers
rates,
proposed
4 of
under §
sonableness
uncertainty,
producer
To diminish
be considered.
of factors would
what kind
exploration
“impeded domestic
which had
“certification
only promised
The FPC
Order
FPC issued
development,”
of Sections
the standards
shall conform to
That order established
in 1972.8
However,
Act.”10
and 7 of the Natural Gas
Under
for certification.
optional procedure
hold-
in a crucial
declared
the Commission
an individ-
the FPC conducts
procedure,
circumstances,”
“special
ing that absent
both
which determines
proceeding
ualized
strict stan-
very
art which invoked
term of
issue and
7 certificate
should
whether a §
“accept
conclusive the
dards,11 it would
reasona-
rate is
proposed
whether
also
findings
embodied in our area rate
If all determinations
ble under §
also declared
The Commission
decisions.”12
“re-
favorable,
rate is a firm
proposed
rates
way
proposed
negative
in a
floor,”
can be ordered.
“notwithstanding
fund
and no refunds
would be considered
ex-
other desirable bene-
be in
[proposed]
Producеrs also receive
contract
established in a
ceiling
of an area
a certificate.9
cess
fits from such
455-A,
quoted
in Moss
10. Order
48 FPC
7. Hunt Oil Co. v.
1970).
supra,
U.S.App.D.C. at
requirement
certified rates
at 467.
Certificating
Optional
New
Procedure for
is embod-
sections
meet the standards of both
*5
Gas,
R-
Docket No.
Producer Sales of Natural
2.75(1) (1977).
ied in 18
§
C.F.R.
223
Order No.
regulations
48 F.P.C.
by the order are
The
established
ratemaking
completed
area
The
first
FPC’s
codified
18 C.F.R. 2.75
§
proceeding
Supreme
decision
and the
Court’s
Cases,
it,
affirming
Permian Basin Area Rate
program are discussed
9. The full details of the
390 U.S.
L.Ed.2d 312
in
Moss
(1968),
producers “special
allowed
relief’ if the
(1974),
part,
cert. denied in
confiscatory.
rates
threatened to be
The
set
in
95 S.Ct.
as
Principles of Review of
C.
Per-
In the
evidence,
conclusive.”
shall be
Regulation
Producer
Cases, 390 U.S.
Area Rate
mian Basin
certification, like other new
Optional
(1968), the
88 S.Ct.
decade, poses certain
initiatives of the last
responsibil-
three
delineated
Supreme Court
judicial review which
special
for
problems
determine
reviewing
court:
ities
discussion.
worthy
separate
we deem
of
order abused
whether the Commission's
development
in FPC
path
The main
of
each ele-
authority, whether
exceeded
been,
course,
of
regulation has
producer
by sub-
supported
ment of the order was
ratemaking to
individualized
evolution from
evidence, and whether
order
stantial
ratemaking.
areawide
nationwide
integrity while
would maintain financial
However,
decade, there has
in the last
been
public
the relevant
providing protection for
major path
development in FPC
a second
of
were
responsibilities
interests.
These
a
producer regulation in the form of
series
key
sentence:
up
summed
“[t]he
special ratemaking programs.28 These
supplant
responsibility
court’s
deregulation
produc-
small
have included
these interests
Commission’s balance
ers,29 deregulation
emergency purchas-
liking,
in-
nearly to its
but
with one more
es,30
special
relief
payments,31
advance
the Commission
stead to assure itself
contingent escalations
ceedings,32
and re-
to each
given reasoned consideration
special
credits,33
fund
work-off
rates
390 U.S.
pertinent
factors.”
gas”).34
(“rollover
renewal contracts
added.)
(emphasis
at 1373
pat
have
programs
these
Some
Statutory
B.
Standard
statutory
command
ently violated
regu
responsibility
no
about the rele
the FPC exercise its
There is also
issue
not simply
late
rates and
producer
For
statutory
vant
standard.
stamp rates set
contract.35 Other
procedure,
proposed
rubber
under
courts
programs
presented
have
conve
“public
must meet both the
calling
sensitivity
more
task
difficult
7 of the Natural
nience” standard
§
the need
adminis
Act,
the conflict between
“just
and reasonable”
two,
flexibility
responding
to a crisis
require-
4’s
trative
4.26 Of the
standard of §
479;
nied,
455-A,
consumer
has es
interests. But there can be no
basis for
tablished
guaranteeing producers
average
more
national rates on
than
production
basis,
their
costs in the absence
exceptions escalating
individual
of such a showing.
the price
above the national
are estab-
43. Petitioner’s Brief at 32.
totalling
respectively,
to 33.2 and 31.4 cents
(after
project
rounding out)
per
65 cents
Mcf
provided
44. Pennzoil
schedules
costs.
costs. R. 813-15.
Sunk costs of the 1960’s
principle
text,
discussed in
not the illus-
Mcf;
acquisition,
included lease
18.5 cents
figures,
specific
trative discussion
is decisive
dry
cents;
exploratory,
hole and
and more
4.8
note,
example,
here. We
the FPC staff
costs,
cents,
than half of successful well
4.4
adjustment
contested the
costs to
of Pennzoil’s
outlays
a total of 27.7 cents. New
of the 1970’s
States,
royalty paid
include the
the United
costs,
included less than half of successful well
percentage
before
return. R.
calculation of the
cents;
facilities,
production
cents;
13.4
accounting approaches
1173. Such alternative
production
cents,
operating expense, 8.8
for a
specific figures
would alter the
but
total оf 26.2 cents. These totals must be ad-
principle
undermine the
involved here.
justed
royalty,
for the United States’ one-sixth
*11
increasing supply,
283, 318,
2328,
FPC,
in the interest of
94 S.Ct.
lished
v.
417 U.S.
between such
occasion,
a
2350,
must be
connection
an
(1974).
there
On
41
72
L.Ed.2d
explo-
experimental
program
increased
funding
and the
to
increased
be allowed
gas
newof
sources
development
without
ration and
commence
a tentative
existence
has been
principle
to result. This
alleged
showing
such a
of a connection if the FPC
that
there
ways:
in a number of
stated
pro-
in
of the
committed
its continuation
”
for
extra
“quid
quo
pro
must be a
gram
verify
to monitoring in order to
“inquiry
must be an
there
funding;45
programs
such a connection exists.48 Such
gas supply”
increase
the incremental
into
subject
being
to
vacated if
Commis-
and
program;46
to the
attributable
requisite
sion fails
make the
demonstra-
between
“symmetry”
must be
there
tion.49
In
production.47
funding and increase
incentive
provide
programs
its
words,
program
Court’s
Supreme
long
FPC
expenditures
for new
funding “while as-
increased
provide
avoiding payment
been
with
lev-
concerned
such
be
suring that
increase
the announce
accompanied by
expenditures
“sunk” before
consumers unless
upon
ied
e.,
avoiding
incentive,
Mobil Oil
a
supplies
gas.”
i. with
increased
ment
248,
fund
FPC,
U.S.App.D.C.
strable
between the increased
connection
v.
164
45. MacDonald
ing
gas supplies.
Service
355,
and new
Public
258,
(1974).
The Second
See
F.2d
505
365
307,
FPC,
Cases, supra,
407
186
Comm’n v.
151
Natural
Rate
Gas
National
U.S.App.D.C.
1059-60,
(1972).
66-67,
pro
F.2d 361
F.2d at
at
567
FPC continued
FPC,
1061,
gram
465,
(1972)
with
quoting
Oil
v.
Order No.
Shell
Co.
1550
48 FPC
941,
denied,
499,
(1975),
96
(1973).
cert.
426 U.S.
Order No.
50
1077
FPC 2111
These
2661,
(1976).
difficulty
In the absence
394
orders evinced an
аwareness
of the
pro
quid
quo
showing any
connection, except
in The Second National
a clear
demonstrable
pric
generous
(“reasona
Rate
Natural Gas
Cases
for funds advanced within a short
funding pro
gas,
ing
ble”)
increased
expenditure
exploration
rollover
time of
experimental
an
gram
development,
allowed on
by clarifying
“reasonable time”
2115;
basis.
limits. See 50 FPC at
51
FPC
819
significance
(explaining the
of “reasonable”
FPC,
time);
Pipeline Co.,
652,
46. Public Service
v.
U.S.
Natural Gas
Comm’n
167
52 FPC
338,
(1974).
App.D.C.
(1974).
F.2d
347
511
655
This court reviewed the 1972 and
1973 orders and concluded
had failed
the FPC
FPC,
connection,
188
47. Cities of Fulton v.
to show a demonstrable
Public Ser
33, 38,
FPC,
952
vice Comm’n v.
167
(1975),
511
F.2d 338
but commended
limitation,
U.S.
167 U.S.
Public Service
for its
Comm’n
“reasonable time”
(1972);
App.D.C.
App.D.C.
n.115,
The Second
posed
on
total of all
based
.the
costs, including
Pennzoil’s
the lease
begin
noting
dimensions
acquisition
(the original
acquir-
cost of
acquisition
lease
issue. According
ing
to statis-
the offshore lease from
federal
compiled
tics
by the Department
words,
government).
In other
the FPC’s
FPC,
Interior and
used
guaranteed
costs of
standard
reimbursement
acquisition
lease
gas
in
offshore oil and
acquisition
way
lease
costs
the same
grown
past
have
exploration
enormously in
guaranteed
decade.
reimbursement
Those costs rose
development
approach
and
costs. Such an
from less than
billion in
$3
years
1967-71,
consequences.
has
New
five
prospective
serious
from
billion
$2
on
billion
argued
$3
York
before
and
billion in
$5
is al-
for a
rehearing
guarantee
that “if such
total of over
billion in 1967-
$13
50. The Second
Cases,
Rate
Natural Gas
Basin Area
National
Rate
Cases,
U.S.App.D.C.
supra,
at
ing
order
with the limitation
Moreover,
in our most recent
“give
attentive
FPC would have to
more
U.S.,
Union
case, Consumers
certification
situation of
special
consideration” to the
U.S.App.D.C. at
FPC, supra, 166
Inc. v.
57-58,
costs,
at
offshore
id. at
661-62,
special
took
1050-1051;
see also id. at
567 F.2d at
contentions
producers’
rehearing
on
note
1060.
acquisition
lease
higher offshore
about the
national
Similarly,
in Public
Comm’n v.
upholding
Service
In
costs.
Circuit,
supra,
Fifth
ratemaking proceeding,
(footnotes omitted),
acquisition
F.2d at 352
in remand-
in lease
too,
the boom
noted
770-A,
Fed.Reg.
Opinion
(1976) (Exhibit
part).
15 in
See,
Bidding
high
has
e.
levels
continued.
g.,
Andrus,
State of Alaska v.
(1978); County
mine the state 510 (1975), F.2d 1270 duction or severance taxes for aff’d, inclusion 426 U.S. 96 S.Ct. rate, similarly in the allowed this Com- (1976); City FPC, of Pittsburgh v. authority mission no to determine has 113, 126, payments method or amount of lease (1956), approval, cited with California v. Department of the Interior. While FPC, 482, 485, 369 U.S. 82 S.Ct. responsibility are mindful of our not L.Ed.2d 54 National environmental to allow costs in our unreasonable cost- policy is responsibility many federal determination, we based cannot arbi- agencies yet required give the FPC is its acquisition trarily conclude that own independent consideration to environ beyond some set ratio unreason- See, mental g., factors in its decisions. e. timely able infor- without substantial Udall v.
mation. L.Ed.2d 869 generally See NAACP F.2d foregoing analysis made in FPC its aff’d, ratemaking opinion does not relieve it of L.Ed.2d 284 responsibility to consider whether Con versely, leasing because offshore provide implicates an incentive for lease acquisition in energy policy alternatives Optional many certification. certifica- agencies, required we have exception Department tion is an national ratemaking allowing higher Interior to encourage energy rates to assess explora- factors in cluding development. activity It in its pre- is not the environmental scribed statements on passthrough leasing. channel for offshore produc- Natural costs;61 Morton, ers’ that is Resources Defense the funсtion Council v. of national U.S.App.D.C. 5, 15, ratemaking. The (1972); elements F.2d cf. Continental incentive must be Oil Co. v. connected to objectives. 1966) (leasing incentive act The fact that does not block a lease has been arranged by gas regulation). another offshore need not federal de- partment consider weight is a matter for that how much the FPC department, give leasing and is policy not in and of itself reason for ratemak ing because it has special-exception program by yet discussed Commis- matter at all. sion. There is no that the We hold indication Interi- or cannot Department responsibility give abdicate its put it forward that reasoned leasing require simply efforts consideration because leas depend special ing provision department.62 involves another for its lessees. Moreover, functions, in carrying out its providing initial statute for offshore required FPC has been when appropri- leasing, the Outer Continental Shelf Lands *16 give ate to independent policy 1953, consideration Act of expressly staked out an FPC to matters which are also the responsibility regulation role in gas pipelines of from the of other agencies. federal National anti- leased lands to take account of conserva- trust policy is principally the responsibility Beyond tion.63 is the overriding re- of Department of Justice and the Fed- quirement regulation public of in the inter- Commission, eral yet Trade is est, FPC re- which can take account of national poli- quired give to independent its own consider- cy. As any for administrative difficulties ation to competitive in its faсtors decisions. of coordination, justify a total this did not See, g., e. Conway Corp. v. past, lack of in the effort 61. Lease auctions were Department conducted decades 62. The FPC and the of Interior being any optional without there certification have consulted with each other about offshore hardly leasing incentive program. at all. It can be con- 455, tended (1972); the lease Order No. statute 48 commands FPC Order 455-A, program. there be an incentive FPC 1334(c) (1970).
63. See 43 U.S.C. § future, justified only programs more in the since tive insofar as may be tractable Energy Organization Department of the incentive there between is connection new De- part of the Act makes the FERC supply The likelihood gas. and the of new of which has inherited partment Energy ex- to the of such a connection diminishes De- leasing responsibilities.64 offshore That conflict, programs duplicate tent posi- will be in a partment the FERC diminishing returns on of both because to take enhanced over- remand incentive, and be- successive increments of policy view of concerns be coordinat- among can choose cause ed here.65 rationally seek programs incentive will stringent least re- those programs with give has failed to Since public. If the quirements benefit factors, pertinent consideration at all to any incen- allows connection between we must for further remand consideration. supply unjustifiably to become at- tive view of “In the absence of Commission coordination, by lack of it has tenuated analysis, we that our do observe comments “ give failed to ‘reasoned сonsideration’ implacable constitute prohibition” have, shaping its order an effort leasing; against incentives for “[W]e however, paying protect consumers from substantial- problems identified substantial necessary bring than forth the ly on re- more FPC will have consider of Fulton v. FPC supplies.” mand.” Comm’n v. needed Cities Public Service supra note
F.2d 1043 at 1074.66
re
More
fundamentally, coordination
III.
TO THE
CHALLENGES
FPC’S
West
quired
justice.
in the
interests
FAILURE TO COORDINATE WITH
Comm’n, 294
Co. v.
Ohio Gas
Public Utilities
NATIONAL RATEMAKING
changed from
Order
project
a
costs standard.
rate
its final
costs standard to
fied the
cent
order.
at
at 658.
F.2d
the
vigorously protests
York
FPC’s
New
recently
problem
kind of
we
This is also the
of
amendment.
approval
the Pennzoil
Natural
in The
National
noted twice
Second
the
respond
approv-
and Pennzoil
FPC
There,
upheld
an FPC
Rate Cases.
justified both
facts
the
by
al was
the
of
to
designed
keep
scheme
consumers
by
precedent.
prior
FPC
Our
case
ratemaking
for
through national
paying
will be
that there
a need
analysis indicates
pro-
payments
in the
they pay for
advance
remand,
on
to reassess
facts of the case
the
at
gram.
weight
and we do not find
of FPC
the
was
at
We
warned
1052-1054.
also
precedent
approval of
the
support
pay
consumers
“questionable” to make
Therefore, we deem it appro-
amendment.
ratemaking
gas they
for
through national
requiring
to outline the factors
fur-
priate
at
pay for in intrastate
Id.
purchases.
approval, leaving
of
ther consideration
on
of the national
op-
optional application
the
instead
applying under
producers
allowed
benefit,
the
this
subsequently
they have filed for
receive
rate. Once
procedure
tional
benefit of
the
producer
they
could
ask for
if the
cannot also
issued national
rate
way
appli
developments
criteria.
Pennzoil
subsequent
certain
satisfy
difficult
proce
ratemaking
have met
“would
cant
the national
asserts here that
it
under
by one
may benefit
assuming this,
producer
FPC
“A
Even
dure can.
criteria.”74
not
other,
both.”
apparent-
but
ratemaking
procedure,
its
by
nationwide
(5th
1275
FPC,
F.2d
Ecce,
which
526
producers
Inc. v.
the route
ly abolished
denied,
Cir.),
rate.75
ac-
cert.
obtain the national
This
could
Accordingly, we re
50
147
against
barriers
L.Ed.2d
previous
reinforces the
tion
reasoned considera
and
amendatory
mand for further
rate hikes.76
of whether
and
tion
the Commission
given
the courts have
simple answer
The
conditions amendment
under what
policy
this “steadfast”77 FPC
upholding
in
optional
application
certificate
be al
attempt
are an
has been that amendments
lowed.
get
proce-
the benefits
two distinct
dures,
optional
na-
procedure
and the
V. CONCLUSIONS
ratemaking
procedure.
tional
Producers
certifica-
reap
filing
optional
benefit
from
un-
created the
an immediate
The FPC
optional
exception
after a nine
tion
as an
national
procedure:
der the
security
they can com-
period
gestation,
ratemaking
give greater
month
Daniel,
area,
See,
supra
g.,
Operations,
note
77.
at 802.
e.
Gas
73.
Pennzoil Offshore
FPC,
1977);
(5th
policies
Inc. v.
Ecce,
ty
applicability
(1978);
testimony was that its
$1,649 Mcf, including a 15% rate of per Judge Law The Administrative
return. eliminating eight found that the cost after INC., CO., TRANSPORTATION C & H the return allowance years retroactivity on Inc., Daily & Dallas & Express, Mavis finding seriously is not and this $1.0148 Petitioners, Inc., Co., Forwarding New York challenged by petitioner I note also Public Commission. Service the time briefs the national rate COMMIS- COMMERCE INTERSTATE Mcf, were filed in this court was $1.01 SION & United States would have and that Pennzoil’s contract America, Respondents. Pennzoil not qualified for that rate had Hauling Rigging Co., optional certificate.
obtained its
&
Home
Ace Doran
Inc.,
Company,
Transportаtion
Aero
the Com-
majority
require
would also
Freight,
Trucking,
Inc., Miller’s Motor
give further
consideration to
mission to
Inc.,
Inc.,
Transportation,
H.
J.
Wales
application
Pennzoil’s amendment of
Inc.,
al.,
Line,
et
Interve-
Rose Truck
I
reason to
certificate.
see no
nors.
action in this
question the Commission’s
submitted
regard.
originally
The contract
No. 77-1389.
47$.
rate of
for a
provided
Pennzoil
Appeals,
Court of
United States
in economic conditions
change
of a
Because
District of Columbia Circuit.
unwilling to sell
however Pennzoil became
buyer that it
price
at that
and informed
27, 1978.
Argued April
This
contract.
Penn-
desired to cancel the
Decided
Oct.
2.75(n).
right
zoil had a
to do.'
C.F.R.
31, 1978.
Rehearing Denied Oct.
buyer
however the
wishing
Not
to cancel
21, 1979.
Denied
Certiorari
Feb.
price
80$
and the
agreed to increase
See
thing irregular, or that Presumably question no procedure.
in this
cents
Mcf.
notes
cases,
view applicable to these
which we
gas
at issue here came from an
pro
discuss below
summarize
lease,
but
here
involving
special
offshore federal
two
vide an overall perspective. The basic ten
compensation
considerations:
that full
reviewing
sion in
programs
these
is producers
for lease acquisition costs need-
they
producers
provide
spurs
with rates in lessly
upward spiral
in lease bid-
excess of
found
“just
those
to be
and rea
ding;
jurisdiction
and that the FPC’s
over
sonable” under the
ratemaking
nationwide
gas
offshore
with the
contrasted
lack of
—аs
return,
proceedings.
ancillary pro
jurisdiction
these
gas
over onshore
sold in intra-
grams, according
FPC, encourage
state
the need for
commerce—-lessens
extra
explora
engage
additional
gas
financial incentives
to secure
tion and development
vitally
Finally,
needed new the
New
interstate market.
York
pro
upheld
sources. We have
these
that there are fundamental
contends
incon-
grams
satisfy
if
they
principles.
average
three
sistencies between the
cost method
There
showing
must be substantial evidence
ratemaking,
high-
national
under which
a demonstrable connection between the
cost
enhance
production serves to
the aver-
funding
scrutiny
in the
under
price
and age costs and
available
gas supply
increased
which it will al
producers,
low-cost
the standards of
legedly produce.38 There must
some optional
program,
compen-
certificate
p.-of
U.S.App.D.C.,
FPC,
p.
38. See
Public Service Comm’n
U.S.
553 of
100, 116,
App.D.C.
(1975)
589 F.2d infra.
payments remand], quoting
[advance
Mobil Oil
pp.---of
94 S.Ct.
U.S.App.D.C.,
See
(1974), quoting
pp.
Permian Basin
559-560 of 589 F.2d infra.
Cases,
Area Rate
L.Ed.2d
40. See Consumers Union of U.S. Inc. v.
U.S.App.D.C. 276,
Notes
notes procedure. Second, legal sleight- hypothesized supra. the contract Whether ing parties bearing permitted, Mobil had not the bene received and its of-hand would by applicants case, fits received under the did in this are matters best what Pennzoil procedure. receipt It is the benefits these left to the Commission to consider on remand. prevents applicant option under the procedure changing drop al contracts or ping procedure out of the as it wishes.
