Providence & Worcester Railroad v. Energy Facilities Siting BoardProvidence & Worcester Railroad v. Energy Facilities Siting Board
In this case we are asked to decide whether
Statutory framework. A brief explanation of the relevant statutory provisions provides the necessary framework. The board is an independent agency established by the Legislature within the Department of Public Utilities.
The power to authorize a taking by eminent domain provided in
Facts and proceedings. The relevant facts are not in dispute. Since 1931, Mobil Pipe Line (Mobil) and its predecessors have owned and operated a common carrier pipeline transporting petroleum products from East Providence, Rhode Island, to Springfield. The present dispute concerns a 120-foot section of the pipeline that passes underneath a railroad bed in Oxford that the Providence and Worcester Railroad (P&W) owns. From the time of the pipeline’s construction, P&W or its predecessors have leased an easement covering this 120-foot strip of land to Mobil or its predecessors, which has allowed for the pipeline’s continued operation. The most recent such lease was entered into between Mobil and P&W in 1977. The lease provided for an initial term of five years, renewable up to five times, each for an additional five-year term, at Mobil’s option. Mobil exercised the last of its renewal options in 2002. The lease was not replaced, and the parties subsequently were unable to reach an agreement on the purchase of a permanent easement over the land that the pipeline occupies. P&W made clear to Mobil its intent to treat Mobil as a trespasser — and to evict Mobil from P&W’s property — should the parties ultimately fail to settle.
Shortly before the lease was to expire, Mobil petitioned the board, pursuant to
Mobil subsequently filed a petition for determination of jurisdiction with the board. See 980 Code Mass. Regs. § 2.08 (2002). The board granted P&W leave to intervene in the proceedings, see 980 Code Mass. Regs. § 1.05(1) (2002), and P&W filed an opposition to Mobil’s petition for determination of jurisdiction, as well as a motion to dismiss Mobil’s original petition for the exercise of eminent domain. Before considering Mobil’s eminent domain petition and P&W’s corresponding motion to dismiss, the board decided to consider Mobil’s petition for determination of jurisdiction.
Both parties submitted arguments, which we discuss later in more detail. Briefly, P&W maintained that the board had no power to authorize the condemnation of an easement because Mobil’s pipeline was not “new,” as P&W claimed the statute requires. P&W also argued that the board lacked the power to authorize a taking for a section of the pipeline less than one mile in length. Mobil contended that the statute gave the board the power to authorize the taking of land for “existing pipelines” if they were to be “restructur[ed], rebuil[t], or relay[edj,” and claimed that its pipeline therefore qualified. Following a hearing, a “presiding officer”
Mobil submitted comments on the tentative decision, and subsequently another hearing was held before the full board. Follow
In its final decision, the board
P&W filed a petition for appeal from the board’s final decision to a single justice of this court.
Discussion. 1. Propriety of appeal. Before considering the merits, we first must determine whether this appeal is properly
Here, the board has not yet decided whether it will authorize a taking of P&W’s property by eminent domain. It has decided only that it has the statutory authority to do so, if it determines (after a later hearing) that the taking is “required in the public interest, convenience and necessity.”
2. The board’s eminent domain authority. Our review of the board’s decision, governed by both
The issue in this case is the proper interpretation of
It is well established that eminent domain statutes must be strictly construed because they concern the power to condemn land in derogation of private property rights.
Informed by these principles, we consider the statutory text itself, “the principal source of insight into Legislative purpose.” New Bedford v. Energy Facilities Siting Council,
By its terms,
The board believed that the foregoing interpretation of the statute would lead to an “absurd result,” which should be
However, we do not believe that the distinction
The language of
Mobil offers additional arguments in favor of the board’s decision, but we consider them similarly unconvincing. Mobil concedes that the portion of its pipeline at issue is not “new,” but argues the pipeline is nevertheless an “oil facility” under
We are not persuaded. The most plausible purpose of this clause is to clarify that an existing pipeline that has been “restructured], rebuil[t], or relay[ed]” is not an “oil facility,”
The Legislature has provided the board with the power to authorize the taking of land for an oil pipeline only if it is “new.” Mobil must therefore seek its remedy from the Legislature, for neither this court nor the board has the power to “imply language in a statute if the Legislature has not provided it.” New England Power Co. v. Selectmen of Amesbury,
So ordered.
Notes
As explained in greater detail infra,
The Department of Public Utilities became the Department of Telecommunications and Energy with the enactment of St. 1997, c. 164.
The statute refers to
It is not necessary to address whether the board’s power to authorize a taking in connection with an existing oil pipeline under
The presiding officer is essentially a hearing officer. See 980 Code Mass. Regs. § 1.04(2) (2002).
Although the board filed a notice of appearance with the single justice, it did not submit a brief or participate in oral argument before the full court. On appeal, Mobil, as intervener, defends the board’s decision.
Because the presiding officer granted P&W intervener status in the proceedings below, a decision which has not been challenged, P&W may seek judicial review under
In a footnote to its brief, Mobil suggests that this court lacks jurisdiction to decide this appeal, because
For its part, Mobil suggests this well-settled proposition has been abrogated by Kelo v. New London,
Mobil makes a similar argument that the interpretation urged by P&W, which we adopt today, is irrational. It contends that it could invoke the board’s power to authorize the exercise of eminent domain under
Mobil made this same argument to the board. The board rejected it in its final decision as inconsistent with its cases and regulations.
Mobil concedes that it has no present intention to rebuild the portion of the pipeline at issue in this case. However, it argues that the pipeline comes within the purported exception for “rebuil[t]” existing pipelines because “from time to time, the pipeline . . . obviously will need repair and replacement work, including in this 120-foot segment,” and because it is willing to rebuild this segment of the pipeline if doing so is necessary to allow the board to exercise its condemnation power under
Were we to accept the expansive interpretation of the “except” clause Mobil urges, see note 13, supra, it is difficult to imagine how any pipeline greater than one mile in length would not be an “oil facility,” regardless of whether it were “new” or “existing.” That this reading of the clause renders the word “new” virtually meaningless supplies an additional reason for rejecting Mobil’s interpretation. See Wolfe v. Gormally,
We find additional support for this reading of the “except” clause in the board’s regulations implementing analogous statutory provisions for natural gas and electric “facilities” under
The interpretation we adopt today makes it unnecessary for us to decide whether the filing of a notice of intention is also a prerequisite under