Prote Contracting Co. v. Board of EducationProte Contracting Co. v. Board of Education
OPINION OF THE COURT
This appeal presents the issue of whether, in an action to recover payments allegedly due under work contracts with the Board of Education of the City of New York, a verdict in plaintiffs favor may stand in the face of posttrial evidence, not previously available, that plaintiffs principal had bribed a Board official to provide an interpretation of a contract specification that favored plaintiffs position on a key issue at trial.
Plaintiff commenced this action against the Board for contract balances and extra and protest work allegedly due on 13 similar window replacement contracts at various Queens schools. The Board counterclaimed for defective workmanship based on the premature and marked deterioration of the windows installed under the contracts.
This litigation’s origins go back to the 1980’s when the Board embarked on a City-wide, multi-million dollar window modern
By 1989, the Board began to detect a premature and marked deterioration of the windows installed by plaintiff, leading the Board, in October 1992, to add counterclaims for breach of contract and seeking damages for the rotting windows. The Board also commenced its own separate action against plaintiff for the rotting windows. The latter action, broader in scope than the instant one, encompassed contracts plaintiff had at some 70 schools and necessarily overlapped the counterclaims asserted herein.
Plaintiff’s theory in the instant case was that the Board’s refusal to pay it the contract balances and for extra work was part of a vendetta, based on Demetriades’ complaints about receiving multiple final punch lists with respect to plaintiff’s work at Bayside High School. Demetriades testified as to the contract balances and in support of plaintiff’s claim that work done under protest at Bayside High School was not required under the contract. Demetriades also testified that back puttying was not required by the contracts; he vouched for the custody and integrity of the only wood samples tested by plaintiff’s wood preservative expert and he presented plaintiff’s crucial damage evidence with respect to the Board’s counterclaim.
On its counterclaim, the Board présented evidence in the form of survey results of the contracts at issue showing that 698 of the sashes installed by plaintiff between 1984 and 1986, i.e., approximately 10%, were visibly decаyed as of July 1993. The Board showed that rotting became a problem as early as two years after installation. As it demonstrated, the proper installation of glass panes in windows requires that the pane be pressed into a bed of glazing compound placed on the sash where the pane is inserted. This is known as back puttying, a process that provides a seal between the wood and glass to prevent water penеtration, particularly from water condensation on the interior side of the glass. Putty is then applied to the side of the glass that is exposed to the elements; this is known as face puttying.
The Board presented witnesses who testified that the contracts, specifically section 13.28, required back puttying. A retired Board employee and former chief area manager in the Bureau of Maintenance during the 1980’s testified that the lack of back puttying would allow water to enter between the muntin bars, the wood strips that separate and hold the panes of glass within a grid-type sash, and the glass, subjecting wooden windows to premаture rotting. An expert in wood products and their preservation testified that the omission of back puttying contributed to window failure by allowing condensation caused by the heat within the school rooms to penetrate the sash.
Demetriades supported his claim that back puttying was not required under the contracts by testifying that when failure to back putty was indicated on punch lists for several of the 13 schools involved herein, Horowitz, the Board’s then Deputy Director of Maintenance, issued a memorandum, undated and not on Board letterhead, the original of which was found in plaintiff’s files, stating that back puttying was not required under the contracts. As the Board’s postverdict motion to set aside the verdict revealed, counsel for the Board, in preparing for the trial of this matter, contacted Horowitz to discuss the issue of back puttying. While Horowitz recalled ruling in plaintiff’s favor on the issue, he could not remember the basis of his determination. As he was to admit in an affidavit submitted in support of the Board’s postverdict motion, Horowitz had accepted a bribe from Demetriades to issue that determination.
Demetriades also testified that, notwithstanding the language of section 1.5 of the contracts’ standard specifications, since back puttying was not shown on the drawing applicable to all Board wоod window contracts, it was not required. Plaintiff also attempted to show that no other Board contractors had been required to back putty. In support of this position,
The Board also asserted that the wood windows installed by plaintiff had not, as required by the contract specifications, been treated with a water-repellent, antifungal wood preservative solution, thus causing the windows to deteriorate prematurely. The Board’s expert, who had analyzed a randomly selected sample of windows at each of the 13 schools involved, found, on the basis of his testing, that the windows had not been treated with preservatives. The Board’s specifications, he testified, were sufficient to preserve the windows. On the other hand, plaintiff’s expert testified that he tested two wood samples for the presence of the required preservative and that the results were positive. The samples, leftover window parts from one of the school projects, never installed, and kept, according to Demetriades, in the shop for some nine years until provided to plaintiff’s attorney, were not from the sash, the window part as to which rotting was a problem, but were from a part of the window that had not shown deterioration and did not involve back puttying. On the question of whether the requisite preservative had been used, the jury found in plaintiff’s favor.
The Board also attempted to show that plaintiff had breached its contracts by failing to paint the windоws with the number of coatings required to prolong the life of the wood. The Board’s expert, through a technique known as photomicrochromotography, showed that the wood had not been painted, as required. Plaintiff’s expert interpreted the photographs furnished by the Board’s expert as showing the contractually required layers of paint. The jury found that plaintiff had not breached its contracts in this regard.
The Board presented evidence that plaintiff had failed, as required by the contract, to use butyl caulking compound at the joints where the muntin bars meet the bottom sash rails,
In defending against the Board’s claim of rotting windows, plaintiff did not dispute that some 10% of the sashes it installed were rotting. It argued primarily that it had performеd the work in accordance with the terms of the contracts and that if some windows were rotting the fault lay with the specifications, not plaintiffs work. Plaintiff was allowed to present evidence of work done by other window contractors and to show that windows they installed had also rotted. The Board, however, was precluded from showing that, under the same specifications, contractors other than plaintiff had installed windows that, mоre than a decade later, showed no signs of rot.
The jury returned a verdict in plaintiffs favor for $264,089, reduced to $257,405, before interest, by the $6,684 awarded to the Board on its counterclaim. After several meetings between the court, plaintiff and representatives of the Board, the Corporation Counsel and the Comptroller of the City of New York, agreement was reached, in light of the jury’s verdict, that a proposed resolution settling аll disputes between plaintiff and the Board, including controversies regarding other schools, would be submitted to the Board for consideration. On May 16, 1994, two days before the Board was to meet to consider the proposal, a Special Assistant United States Attorney then employed as the First Assistant Inspector General of the New York City School Construction Authority notified the Board’s trial counsel that, based on allegations of illegаl conduct by plaintiff and Demetriades bearing directly on the
On May 19, 1994, the United States Attorney for the Southern District of New York, culminating a four-year joint Federal, City and State investigation into allegations of bribery, fraud and racketeering involving Board employees and contractors doing business with the Board, announced the filing of criminal charges against 18 persons, including Horowitz. On May 26, 1994, Horowitz pleaded guilty to each count of a felony information charging him with various crimes arising out of his activities in connection with private asbestos abatement contracts and a Board renovation project. Prior to entering the plea, Horowitz had advised law enforcement officials of criminal conduct by plaintiff and its president, Demetriades, bearing directly on this lawsuit. Horowitz set forth this conduct in a December 7, 1994 affidavit, which was to become the basis of the Board’s motion to set aside the verdict.
In the affidavit, Horowitz stated that his contemporaneous 1986 review of the contract specifications supported the Board’s interpretation that plaintiff’s installation of windows without the use of back puttying was in violation of the contract, but that Demetriades subsequently visited him at his home and paid him a $10,000 cash bribe to rule, in his capacity as Deputy Director of Maintenance, in plaintiff’s favor on the issue. In his affidavit, Horowitz told of other improper payments paid to him and to members of his family to influence the administration of contracts between the Board and plaintiff. When contacted by Board attorneys prior to the commencement of the trial herein as to the issue of back puttying, Horowitz, according to his affidavit, told them that he could not recall the basis of his earlier determination that back puttying was not required by the contract. In his affidavit, Horowitz also noted that Mahla, who testified favorably for plaintiff at the trial, had worked part time for plaintiff while still employed by the Board. According to Horowitz, Mahla, who had access to the Board’s own cost estimates, would prepare bid estimates for plaintiff. Mahla also had the responsibility of evaluating change order requests submitted by contractors, including plaintiff.
CPLR 5015 (a) vests courts with the discretionary power to relieve a party from a judgment or order upon the grounds of, inter alia, "newly-discovered evidence which, if introduced at the trial, would probably have produced a different result and which could not have been discovered in time to move for a new trial under section 4404” or "fraud, misrepresentation, or other misconduct of an adverse party.” (CPLR 5015 [a] [2], [3].) The party seeking relief on the basis of newly discovered evidence must show that the evidence is material, not merely cumulative, not of a kind as would merely impeach an adverse witness’s credibility, thаt it would probably have changed the result and that the material could not have been previously discovered by the exercise of due diligence. (Olwine, Connelly, Chase, O’Donnell & Weyher v Valsan, Inc.,
The newly discovered evidenсe in this case satisfies the criteria for CPLR 5015 (a) (2) relief as set forth in Olwine, Connelly, Chase, O’Donnell & Weyher v Valsan, Inc. (supra). The
As a matter of substantive law, Horowitz’s allegations do more than merely provide the basis for granting a new trial. If established, they would require dismissal of the complaint. It is well settled that contracts, although legal in their inducement and сapable of being performed in a legal manner, which have nonetheless been performed in an illegal manner, will not be enforced. (McConnell v Commonwealth Pictures Corp.,
The courts of this State have consistently followed this principle. (See, e.g., Ross Bicycles v Citibank,
Whether the Board is entitled to a dismissal of the complaint will, of course, be determined by a resolution of the allegations of wrongdoing, which, as noted, plaintiff denies. In light of the serious nature of the allegations, on the retrial, the Board, as requested, should be allowed to assert a claim for punitive damages.
Accordingly, the judgment of the Supreme Court, New York County (Edward Lehner, J.), entered May 9, 1995, awarding plaintiff the sum of $360,877.40, should be reversed, on the law and the facts, without costs or disbursements, аnd the matter remanded for a new trial. The appeal from the order of the same court and Justice, entered on or about April 10, 1995, denying defendant’s cross motion, inter alia, to set aside the verdict, should be dismissed as subsumed in the appeal from the judgment.
Judgment, Supreme Court, New York County, entered May 9, 1995, which awarded plaintiff the sum of $360,877.40, reversed, on the law and the facts, without costs or disbursements, and the matter remanded for a new trial. The appeal from the order of the same court and Justice, entered on or about April 10, 1995, is dismissed as subsumed in the appeal from the judgment.
Notes
. Plaintiff instituted a third-party action, which was discontinued, against the supplier of the wood windows on the Board’s counterclaims.
. Indeed the conduct alleged is violative of criminal statutes (see, e.g., Penal Law §§ 180.00, 180.03, 200.00, 200.20, 105.05), as well as conflict of interest rules. Similarly, plaintiffs alleged use of Mahla, a Board employee, to obtain confidential information in the bidding process, if established, would constitute criminal conduct and violate conflict of interest rules.