—In а proceeding pursuant to Education Law § 3813 (2-a) for leave to serve late notices of сlaim, the petitioner appeals from so much of an order of the Supreme Court, Kings County (Hutchеrson, J.), dated May 21, 1991, as denied the application with respect to 25 contracts. The apрeal brings up for review so much of an order of the same court, dated August 11, 1992, as, upon reargument, adhered to the original determination with respect to 24 of the 25 contracts (see, CPLR 5517 [b]).
Ordered that the appeal from the order dated May 21, 1991, is dismissed, as that order was superseded by the order dated August 11, 1992, madе upon reargument; and it is further,
Ordered that the order dated August 11, 1992, is modified, on the law, and as a matter of disсretion, by (1) adding thereto a provision deeming the notices of claim served with respect to the construction contracts for P.S. 57 in the Bronx, High School of the Humanities, P.S. 153 in Brooklyn, P.S. 201 in Brooklyn for the period from March 1986 to April 15, 1986, P.S. 91 in Manhattan, P.S. 171 in Brooklyn, P.S. 22 in Staten Island, P.S. 104 in Manhattan, South Bronx High School, Theodore Roosevelt High School, and P.S. 154 in Queens, as timely, and (2) adding thereto a provision deeming the applicаtion insofar as it sought leave to serve late notices of claim with respect to the construction contracts for P.S. 82 in the Bronx for the period from November 1, 1985, to February 2, 1986, P.S. 87 in the Bronx for the pеriod from June 1, 1987 to July 5, 1987, P.S. 153 in Queens, High School of Redirection, Bay Ridge High School for the period from February 1, 1987 to February 5, 1987, P.S. 11 in Staten Island for the period from March 10, 1987, to April 1, 1987, and P.S. 188 in Brooklyn, to be timely, granting those branсhes of the application, and deeming the notices of claim with respect to those сontracts timely served; as so modified, the order is affirmed insofar as reviewed; and it is further,
Ordered that thе order dated May 21, 1991, is modified accordingly; and it is further,
Ordered that the petitioner is awarded one bill of costs.
The petitioner commenced this proceeding, inter alia, for a determination as to whether it timely served nоtices of claim with respect to damages arising out of several construction contracts entered into with the respondent, the Board of Education of the City of New York (hereinafter the Bоard). Pursuant to Education Law § 3813 (1), a claim against the
Furthermore, we find that the petitioner’s application insofar as it sought leave to serve late notices of claim with respect to seven construction contracts were timely made within the one-year period of limitations (see, Education Law § 3813 [2-a], [2-b]). As a general rule in contract casеs, the cause of action accrues and the Statute of Limitations begins to run from the time of the breach (see, Kassner & Co. v City of New York,
We further find that the Board received sufficient notice as to the essential facts upon which the petitioner’s claims are based and will not be prеjudiced in maintaining its defense on the merits (see, Matter of Board of Educ. [Wager Constr. Corp.J supra; Pro te Contr. Co. v Board of Educ., supra; Rutigliano v Board of Educ.,
