13 Pa. Commw. 4 | Pa. Commw. Ct. | 1974
Opinion by
Plaintiffs filed this complaint in equity in our original jurisdiction praying that the defendants, the Secretary of Community Affairs and the Redevelopment Authority of the City of Nanticoke, be temporarily enjoined from entering into a contract to implement the Lower Broadway Disaster Urban Renewal Area Project No. Pa. R-668(c), a total clearance flood control project based on a capital grant of $2,342,561.00 from the Department of Housing and Urban Development under Title 1 of the Housing Act of 1949, as amended, 42 U.S.C.A. §1441 et seq., and a grant in aid of $733,332.00 by the Department of Community Affairs of the Commonwealth.
In addition, plaintiffs pray for a preliminary injunction against the defendant Secretary to restrain
After a hearing and argument, the request for preliminary injunction was denied. This case is now before us for disposition of the preliminary objections. Inasmuch as we must sustain the preliminary objection that there is an adequate remedy at law, we need not reach the question of this Court’s jurisdiction over defendant Authority.
The plaintiffs are citizens who are either property owners or tenants located witMn the boundaries of the proposed urban renewal project and would be displaced if, but only if, the properties they own or occupy as tenants are acquired as a result of the project. The plaintiffs recognize that the gravamen of their action is that defendant Authority will proceed with eminent domain actions to acquire the properties they own or occupy, for it is alleged in the complaint in paragraph C-5 that tMs project is a flood control project as mentioned in Section 602 of the Eminent Domain Code, Act of June 22, 1964, Special Sess., P. L. 84, as amended, 26 P.S. §1-602.
It is the plaintiffs’ position that the defendant Secretary, by Ms allegedly arbitrary and capricious actions, allegedly taken in bad faith, did improperly exercise influence over the City Council of the City of Nanticoke and the defendant Redevelopment Authority of the City of Nanticoke in their decision that the project be a total clearance project when, in fact, such a total clearance project is unnecessary. Plaintiffs heretofore
“It is clear, however, that although the Court may not decide the wisdom of the Lower Broadway Project, (citations omitted) the Plaintiffs will, at the proper time, be able to raise the question of whether the project area is in fact blighted and whether the Redevelopment Authority has the power to condemn, Faranda Appeal, 420 Pa. 295 [216 A. 2d 769] (1966), and also whether there has been fraud, palpable bad faith, or arbitrary action on the part of the condemnor, (citations omitted).” Lower Broadway Citizens Group v. City of Nanticoke, supra, at 176. Inasmuch as the lower court is the very court in which any eminent domain proceedings on this project will be litigated before any property rights of plaintiffs, either as owners or tenants, can be taken, plaintiffs are hardly in a position to assert that they do not have an adequate remedy at law.
In his brief and on oral argument, counsel for plaintiffs places great reliance on our decision in Haddington Leadership Organization, Inc. v. Sherman, 8 Pa. Commonwealth Ct. 309, 302 A. 2d 919 (1973), which was not reported until after the Luzerne County Common Pleas Court rendered its decision. Haddington is in no way contrary to the Luzerne County Common Pleas Court’s decision and is no precedent for plaintiffs’ position here. In Haddington, the plaintiffs sought injunctive relief to require the Development Authority to acquire possession. The property had been
Accordingly, we enter the following
Order
Now, April 1, 1974, the preliminary objection raising the question of equity jurisdiction is sustained and the complaint dismissed.