Professional Electrical Contractors of Connecticut, Inc. v. Stamford HospitalProfessional Electrical Contractors of Connecticut, Inc. v. Stamford Hospital
Case Information
*1 ***********************************************
Thе “officially released” date that appears near the be- ginning of each opinion is the date the opinion will be pub- lished in the Connecticut Law Journal or the date it was released as a slip opinion. The operative date for the be- ginning of all time periods for filing postopinion motions and petitions for certification is the “officially released” date appearing in the opinion.
All opinions are subject to modification and technical correction prior to official publication in the Connecticut Reports and Connecticut Appellate Reports. In the event of discrepancies between the advance release version of an opinion and the latest version appearing in the Connecticut Law Journal and subsequently in the Connecticut Reports or Connecticut Appellate Reports, the latest version is to be considered authoritative.
The syllabus and procedural history accompanying the opinion as it appears in the Connecticut Law Journal and bound volumes of official reports are copyrighted by the Secretary of the State, State of Connecticut, and may not be reproduced and distributed without the express written permission of the Commission on Official Legal Publica- tions, Judicial Branch, State of Connecticut. ***********************************************
PROFESSIONAL ELECTRICAL CONTRACTORS OF
CONNECTICUT, INC. THE STAMFORD HOSPITAL ET AL.
(AC 41931) Bright, Moll and Bear, Js.
Syllabus The plaintiff, a second tier subcontractor, sought to recover damages from
the defendants H Co., a hospital, S Co., a generаl contractor, and E Co., a subcontractor, for, inter alia, quantum meruit or unjust enrichment, and to collect on a bond issued by the defendant F Co. posted pursuant to statute (§ 49-37), in connection with a dispute arising from a project relating to the expansion and renovation of H Co. Following the trial court’s granting of motions for summary judgment filed by F Co. and S Co., the plaintiff appealed to this court. Held : 1. The trial court erred in granting S Co.’s motion for summary judgment
on the count of the complaint in which the plaintiff alleged that H Co., S Co. and E Co. were liable in quantum meruit or unjust enrichment; the plaintiff alleged that it performed services at the request of H Co., S Co. and E Co., and that H Co., S Co. and E Co. accepted and benefited from the plaintiff’s work, and S Co. presented no evidence establishing that it paid E Co. or someone else for the plaintiff’s specific services, and, thus, there existed a genuine issue of material fact with respect to the plaintiff’s claim for quantum meruit or unjust enrichment. 2. The trial court erred in granting the motion for summary judgment filed
by S Co. and F Co. on the count of the complaint in which the plaintiff sought to collect on the surety bond issued by F Co.: under Connecticut’s mechanic’s lien statutes (§§ 49-33 and 49-36), recovery was not barred to the second tier subcontractor plaintiff solely because the first tier subcontractor had been paid in full by S Co.; moreover, S Co. and F Co. could not prevail on their alternative ground for affirmance that the lienable fund had been exhausted by the costs of the project and that the plaintiff did not have a contract with H Co., S Co. or F Co.; there was a lienable fund still available in the amount still owed by H Co. to S Co. at the time the plaintiff gave statutory notice (§§ 49-34 and 49-35) of its lien to H Co., regardless of whether H Co. continued to make payments to the nondefaulted S Co., a construction of the applicable statutes that was supported by the legislative history. Argued November 18, 2019—officially released March 17, 2020
Procedural History Action to recover damages for, inter alia, breach of contract, and for other relief, brought to the Superior Court in the judicial district of Stamford, where the plaintiff withdrew the action as to the named defendant; thereafter, the court, Hon. Edward R. Karazin, Jr. , judge trial referee, granted the motions for summary judgment filed by the defendant Skanska USA Building, Inc., et al., and rendered judgment thereon, from which the plaintiff appealed to this court. Reversed in part; further proceedings .
Kenneth A. Votre , for the appellant (plaintiff). Michael J. Donnelly , with whom was Kevin W. Munn , for the appellee (defendant Sanska USA Building, Inc.).
Charles I. Miller filed a brief for the appellee (defen- dant Fidelity and Deposit Company of Maryland).
Opinion
BRIGHT, J. The plaintiff, Professional Electrical Con- tractors of Connecticut, Inc., appeals from the summary judgment rendered by the trial court in favor of the defendants Fidelity and Deposit Company of Maryland (Fidelity) and Skanska USA Building, Inc. (Skanska). [2] On appeal, the plaintiff claims that the court erred in rendering summary judgment on counts two and three of its complaint because there were genuine issues of material facts and neither defendant was entitled to judgment as a matter of law. Specifically, the plaintiff claims that (1) Skanska failed to prove that there existed no issues of material fact on the plaintiff’s equitable claim of quantum meruit or unjust enrichment, and (2) neither defendant established that it was entitled to judgment as a matter of law on the plaintiff’s bond claim because the claim is viable pursuant to General Statutes §§ 49-33 and 49-36. We agree with the plaintiff on both claims. Accordingly, we reverse in part and affirm in part the judgment of the trial court. [3]
The following facts, which were uncontested for sum- mary judgment purposes, and procedural history are relevant to our consideration of the issues on appeal. The plaintiff commenced this action by service of pro- cess on January 4, 2017. In its complaint, the plaintiff alleged, in count one, that Semac Electrical Company, Inc. (Semac), Skanska, and The Stamford Hospital (hos- pital) were in breach of contract on the basis of the following alleged facts: the hospital had entered into a contract with Skanska to provide construction services to the hospital (project); Skanska entered into a subcon- tract agreement with Semac for electrical work on the project; Semac entered into a second tier subcontract agreement with the plaintiff to perform electrical work on the project; on October 3, 2015, the plaintiff began to furnish materials and services for the project; the plaintiff furnished materials and services in accordance with the terms of its contract; the рlaintiff has demanded payments in the amount of $38,509.07; and Semac, Skanska, and the hospital all have refused to pay the plaintiff for its materials and services in breach of contract.
In count two of its complaint, the plaintiff alleged that Semac, Skanska, and the hospital were liable under the theories of quantum meruit or unjust enrichment. In addition to the facts alleged in count one, which the plaintiff incorporated into count two, the plaintiff also alleged that it performed services and incurred costs at the request of Semac, Skanska, and the hospital; its services were worth at least $38,509.07; Semac, Skan- ska, and the hospital accepted and benefited from the plaintiff’s work; the plaintiff requested payment for the reasonable value of the services it rendered; Semac, Skanska, and the hospital have refused to pay the plain- tiff; and Semac, Skanska, and the hospital have been *4 unjustly enriched.
In the third count of its complaint, the plaintiff sought to collect on the bond pursuant to General Statutes § 49- 37. Specifically, it alleged in count three that Skanska submitted a bond in the amount of $38,509.07 in substi- tution for the mechanic’s lien that had been filed against the hospital in the original amount of $42,359.97; on January 27, 2016, Fidelity issued the surety bond in the amount of $42,359.97; Skanska has failed to pay the plaintiff, despite repeated demands for the sum of $38,509.07; and Fidelity has refused to pay the plaintiff on the bond.
Fidelity filed an answer and set forth a special defense in which it alleged that the lienable fund had been exhausted by the costs of the project, and that the plaintiff did not have a contract with the hospital, Skan- ska, or Fidelity. Skanska also filed an answer in which it, inter alia, denied having any type of contract with the plaintiff, and it left the plaintiff to its proof on other allegations set forth in the complaint. Skanska did not file a special defense.
On March 29, 2018, Skanska filed a motion for sum- mary judgment on the plaintiff’s complaint. In its motion, Skanska argued that it was entitled to judgment as a matter of law because (1) there was no lienable fund available because all funds had been exhausted in completing the project, (2) there existed no contract between it and the plaintiff, and (3) its payment to Semac, the party with whom the plaintiff had con- tracted, barred the plaintiff’s claims for quantum meruit or unjust enrichment. In support of its motion for sum- mary judgment, Skanska submitted the affidavit of Michael J. Smerglio, the executive director of facilities management for the hospital. Smerglio averred that the hospital and Skanska had entered into a contract for the construction and renovation of the hospital, which required Skanska to act as the construction manager for the project. He also averred that Skanska would send the hospital periodic requests for payment on the basis of the work that had been completed, and that the hospital would produce the payments after making any necessary adjustments. Further, he averred that the hospitаl and Skanska had entered into a series of change orders that expanded and refined the work to be done on the project, which then adjusted the final contract price to a maximum price of $284,091,867. Smerglio acknowledged that the plaintiff served the hospital with a notice of mechanic’s lien on January 13, 2016, and that, as of that date, the hospital had paid to Skanska the sum of $216,637,556.56 on the project, and that it had not paid any other entity for work done on the project. Smerglio additionally averred that, after Janu- ary 13, 2016, the hospital paid Skanska an additional $67,354,375.44 for work on the project, for a total of $283,991,932, with the remaining $99,935 held as *5 retainage, pending completion of some punch list items. Smerglio also declared that Skanska had not been in default on its contract with the hospital. Appended to Smerglio’s affidavit were several exhibits, the first of which provided that the original amount of the contract between the hospital and Skanska, before the series change orders, was $267,706,729.
Skanska also submitted the affidavit of Mark Miller, its senior vice president and the director for the project. Miller averred in relevant part that in October, 2015, Semac breached its subcontract with Skanska and aban- doned the project, requiring Skanska to hire replace- ment subcontractors to complete the work at an increased cost, which was borne by Skanska and not by the hospital. Miller further attested that there never was a contract between Skanska and the plaintiff, the hospital and the plaintiff, or Fidelity and the plaintiff in relation to the project, and that the plaintiff was a second tier subcontractor on the project.
On April 2, 2018, Fidelity filed a motion for summary judgment, specifically joining Skanska’s motion and memorandum as to count three of the plaintiff’s com- plaint, which is the bond claim.
The plaintiff filed an opposition to the motions for summary judgment, arguing that there were genuine issues of material fact that prohibited the granting of the motions for summary judgment and that there was no merit to the motions as to the bond claim because it is uncontested that the lienable fund was not exhausted at the time the plaintiff filed its mechanic’s lien. No affidavits or other evidence were attached to the plaintiff’s memorandum in opposition.
On July 11, 2018, the court rendered summary judg- ment in favor of the defendants, concluding that there were no genuine issues of material fact and that the defendants were entitled to judgment as a matter of law. As to the plaintiff’s claim for breach of contract, the court stated that the plaintiff had conceded that it did not have a contract with Skanska and, therefore, that count one of the complaint was not viable as to Skanska. As to the plaintiff’s claim for quantum meruit or unjust enrichment, set forth in count two of the complaint, the court, referencing and taking judicial notice of the related case of Semac Electric Co. Skan- ska USA Building, Inc. , Superior Court, judicial district of Hartford, Complex Litigation Docket, Docket No. X07-CV-15-6076107-S (August 23, 2017), aff’d, 195 Conn. App. 695, A.3d (2020) ( Semac ), pointed out that ‘‘[t]he record in Semac [was] silent on whether Skanska dealt with the plaintiff prior to Semac’s breach, directed the plaintiff’s performance and knowingly accepted its services, or represented that Skanska [would] compen- sate the plaintiff for work done.’’ Nonetheless, the court concluded that judgment was appropriate on this count of the plaintiff’s complaint because it concluded that *6 there was no evidence of an implied contract between Skanska and the plaintiff.
As to the bond claim, the court concluded that the defendants’ argument that the lienable fund had been exhausted was not compelling, but, relying on Brian’s Floor Covering Supplies, LLC v. Spring Meadow Elderly Apartments , Superior Court, judicial district of Fairfield, Docket No. CV-00-0375810-S (March 22, 2006), concluded that Skanska already had paid Semac for the plaintiff’s work, and, therefore, the plaintiff could not recover under the bond. The court, thereafter, rendered judgment in favor of the defendants. This appeal followed.
‘‘In seeking summary judgment, it is the movant who
has the burden of showing the nonexistence of any
issue of fact. The courts are in entire agreement that
the moving party for summary judgment has the burden
of showing the absence of any genuine issue as to all
the material facts, which, under applicable principles
of substantive law, entitle him to a judgment as a matter
of law. The courts hold the movant to a strict standard.
To satisfy his burden the movant must make a showing
that it is quite clear what the truth is, and that excludes
any real doubt as to the existence of any genuine issue
of material fact. . . . As the burden of proof is on the
movant, the evidence must be viewed in the light most
favorable to the opponent. . . . When documents sub-
mitted in support of a motion for summary judgment
fail to establish that there is no genuine issue of material
fact, the nonmoving party has no obligation to submit
documents establishing the existence of such an issue.
. . . Once the moving party has met its burden, how-
ever, the opposing party must present evidence that
demonstrates the existence of some disputed factual
issue. . . . It is not enough, however, for the opposing
party merely to assert the existence of such a disputed
issue. Mere assertions of fact . . . are insufficient to
establish the existence of a material fact and, therefore,
cannot refute evidence properly presented to the court
under Practice Book § [17-45]. . . . Our review of the
trial court’s decision to grant [a] motion for summary
judgment is plenary.’’ (Citations omitted; footnote omit-
ted; internal quotation marks omitted.)
Allstate Ins. Co.
Barron
,
I The plaintiff claims that the court erred in rendering summary judgment on count two of its complaint because Skanska failed to prove that there exists no issue of material fact on the equitable claim of quantum meruit or unjust enrichment. The plaintiff argues that it sufficiently alleged in its complaint that Skanska knew of and accepted the plaintiff’s work, and that this allega- tion, which has not been rebutted sufficiently by the defendants’ evidence, alone demonstrates the existencе of an issue of material fact as to whether there was an *7 implied contract between the plaintiff and Skanska, which would support count two of its complaint sound- ing in the theories of quantum meruit and unjust enrich- ment. The plaintiff also argues that the issue of whether Skanska paid Semac in full for the work done by the plaintiff has no bearing on its claims for quantum meruit or unjust enrichment because Semac did not pay the plaintiff, and Skanska accepted the benefit of the plain- tiff’s work. Skanska argues that the plaintiff’s claim sounds only in unjust enrichment, not in quantum meruit, which the plaintiff disputes vigorously in its reply brief. On the merits of the plaintiff’s claim, Skan- ska argues that, because it paid Semac for the work done by the plaintiff, the plaintiff cannot recover from Skanska but must seek its recovery from Semac. We agree with the plaintiff.
‘‘Quantum meruit and unjust enrichment are noncon-
tractual means of recovery in restitution. Quantum
meruit is a theory of recovery permitting restitution in
the context of an otherwise unenforceable contract. In
contrast, recovery under a theory of unjust enrichment
applies in the absence of a quasi-contractual relation-
ship. . . . Because both doctrines are restitutionary,
the same equitable considerations apply to cases under
either theory. The terms of an unenforceable contract
will often be the best evidence for restitution of the
reasonable value of services rendered in quantum
meruit, although sometimes the equities may call for a
more restrictive measure. . . . [Our Supreme Court]
has used quantum meruit and unjust enrichment inter-
changeably, or as equivalent terms for recovery in resti-
tution.’’ (Citations omitted.)
Walpole Woodworkers, Inc.
v.
Manning
,
‘‘Quantum meruit is a theory of contract recovery
that does not depend upon the existence of a contract,
either express or implied in fact. . . . Rather, quantum
meruit arises out of the need to avoid unjust enrichment
to a party, even in the absence of an actual agreement.
. . . Quantum meruit literally means as much as he has
deserved . . . . Centered on the prevention of injus-
tice, quantum meruit strikes the appropriate balance
by evaluating the equities and guaranteeing that the
party who has rendered services receives a reasonable
sum for those services. Unjust enrichment applies
whenever justice requires compensation to be given for
property or services rendered under a contract, and no
remedy is available by an action on the contract . . . .
Indeed, lack of a remedy under the contract is a precon-
dition for recovery based upon unjust enrichment. Not
unlike quantum meruit, it is a doctrine based on the
postulate that it is contrary to equity and fairness for
a defendant to retain a benefit at the expense of the
plaintiff.’’ (Citations omitted; internal quotation marks
omitted.)
Gagne Vaccaro
,
‘‘[A] right of recovery under the doctrine of unjust enrichment is essentially equitable, its basis being that in a given situation it is contrary to equity and good conscience for one to retain a benefit which has come to him at the expense of another. . . . With no other test than what, under a given set of circumstances, is just or unjust, equitable or inequitable, conscionable or unconscionable, it becomes necessary in any case where the benefit of the doctrine is claimed, to examine the circumstances and the conduct of the parties and apply this standard. . . .
‘‘Unjust enrichment is a very broad and flexible equi- table doctrine that has as its basis the principle that it is contrary to equity and good conscience for a defen- dant to retain a benefit that has come to him at the expense of the plaintiff. . . . The doctrine’s three basic requirements are that (1) the defendant was benefited, (2) the defendant unjustly failed to pay the plaintiff for the benefits, and (3) the failure of payment was to the plaintiff’s detriment. . . . All the facts of each case must be examined to determine whether the circum- stances render it just or unjust, equitable or inequitable, conscionable or unconscionable, to apply the doctrine.’’ (Citations omitted; internal quotation marks omitted.) Id., 408–409.
In the present case, in count two of its complaint, the plaintiff alleges that Skanska is liable to it under the theories of quantum meruit or unjust enrichment. Specifically, the plaintiff alleges in count two that Skan- ska entered into a contract with the hospital to provide construction services on the project; Skanska entered into a subcontract agreement with Semac to perform electrical work on the project; Semac entered into a second tier subcontract agreement with the plaintiff to perform electrical work on the project; the plaintiff, on October 3, 2015, began to furnish materials and services for the project; the plaintiff performed services and incurred costs at the request of Skanska ; Skanska accepted and benefited from the plaintiff’s work; the plaintiff demanded payment in the amount of $38,509.07 for its services from Skanska ; and Skanska refused to pay the plaintiff .
In its motion for summary judgment as to count two of the plaintiff’s complaint, Skanska argued that, because it had paid Semac, the party with whom the plaintiff had a written contract, the plaintiff’s claims against Skanska were barred. In support of its motion for summary judgment, Skanska relied on the affidavit of Miller and the court’s decision in the Semac case.
Miller averred in relevant part that in October, 2015, Semac breached its subcontract with Skanska and aban- doned the project, requiring Skanska to hire replace- ment subcontractors to complete the electrical work at an increased cost, which was borne by Skanska and *9 not by the hospital. Miller further attested that the plain- tiff was a second tier subcontractor on the project, and that there existed no contract between Skanska and the plaintiff. In the Semac case, the court held that Semac had overbilled Skanska, and it rendered judg- ment in favor of Skanska and against Semac in the amount of $4,262,390.56. Semac Electrical Co. Skan- ska USA Building, Inc. , suрra, Superior Court Docket No. X07-CV-15-6076107-S. Skanska argues that because it is undisputed that it paid Semac and replacement contractors more than the amount it contractually was required to pay Semac, as a matter of law, it cannot have been unjustly enriched by not paying the plaintiff for any work it performed. We are not persuaded.
The Miller affidavit and the court’s decision in the Semac case do not speak to the plaintiff’s allegations in count two that it began working on the project on October 3, 2015, that it obtained materials and provided services in the amount of $38,509.07 for the project, that it completed its work, that Skanska accepted and benefited from the plaintiff’s work , that the plaintiff performed services and incurred costs at the request of Skanska and that Skanska has never paid for the plaintiff’s work . The trial court, in its decision in the Semac case, calculated damages due to Skanska based on the court’s analysis of the percentage of work com- pleted by Semac compared to how much Semac was paid. Id. The trial court in that case made no finding that Semac had been paid for the work performed by the plaintiff. The lack of such a finding is particularly significant because the court specifically found that Semac had been compensated for the work performed by two other subcontractors. Additionally, as the trial court in the present case stated, it also is unknown whether Skanska ‘‘dealt with the plaintiff prior to Sem- ac’s breach, directed the plaintiff’s performance and knowingly accepted its services, or represented that [it would] compensate the plaintiff for work dоne.’’
The fact that Skanska paid replacement electrical contractors more than it was contractually obligated to pay Semac, as averred to by Miller, or overpaid Semac, as found by the trial court in the Semac case, says nothing about whether Skanska ever paid Semac or anyone else for the work performed by the plaintiff. Without evidence to the contrary, it is entirely possible that the additional costs incurred by Skanska for electri- cal work were unrelated to the work performed by the plaintiff. If that is the case, then Skanska was unjustly enriched because it received the benefit of the plaintiff’s work without ever paying anyone for it. The court was not in a position to resolve this issue on summary judg- ment because Skanska failed to present evidence estab- lishing that there was no genuine issue of material fact that it had paid Semac or someone else for the plaintiff’s specific services.
The cases relied on by Skanska are consistent with
our analysis. In
Providence Electric Co.
v.
Sutton Place,
Inc.
,
It is the movant’s burden at the summary judgment
stage to prove that there exists no disputed issue of
material fact and that it is entitled to judgment as a
matter of law. See, e.g.,
Allstate Ins. Co. Barron
,
supra,
II The plaintiff next claims that the court erred as a matter of law in rendering summary judgment on count three of its complaint. Specifically, the plaintiff argues that its bond claim is viable under a proper reading of *11 our mechanic’s lien statutes, including §§ 49-33, 49-36, and 49-37. [6] The defendants argue that the court properly granted the motion for summary judgment on the third count of the plaintiff’s complaint, but for the wrong reason. Specifically, they argue that they were entitled to judgment as a matter of law on count three of the plaintiff’s complaint because the lienable fund was exhausted in completing the project, and there were no funds remaining to give to the plaintiff. We agree with the plaintiff that its claim remains viable.
‘‘Those who provide services or materials in connec-
tion with the construction of a building are entitled to
claim a lien on the land that they have improved if they
fall into one of two categories. Lienors are protected
if they have a claim either (1) by virtue of an agreement
with or the consent of the owner of the land, or (2) by
the consent of some person having authority from or
rightfully acting for such owner in procuring labor or
materials. General Statutes § 49-33. Lienоrs in the sec-
ond category must give timely notice of their intent to
claim a lien in order to perfect their lien, while those
in the first category need not give such notice. General
Statutes § 49-35. Lienors in the second category include
subcontractors and persons who furnish materials or
services by virtue of a contract with the original contrac-
tor or with any subcontractor, that is to say at least
first and second tier subcontractors. General Statutes
§ 49-35. No mechanic’s lien may exceed the price which
the owner has agreed to pay for the building being
erected or improved, and the owner is entitled, further-
more, to credit for payments made in good faith to the
original contractor
before receipt of notice of such a
lien or liens
. General Statutes §§ 49-33 and 49-36. If
the contract price which the owner agreed to pay the
original contractor is insufficient to cover all the liens,
claimants other than the original contractor are to be
paid first
, and, if necessary, on a pro rata basis. General
Statutes § 49-36.’’ (Emphasis added; footnote omitted.)
Seaman
v.
Climate Control Corp.
,
‘‘General Statutes § 49-33 establishes a lien in favor
of subcontractors by virtue of an agreement with or by
consent of the owner of the land upon which the build-
ing is being erected . . . . It is well established that
[i]t is not necessary to their lien status that [a subcon-
tractor] have any direct contractual relationship either
with the owner or with the general contractor . . . .
All that is necessary is that the defendant consented to
have a building erected on its property and that the lien
was for materials or services provided in the erection
of said building.’’ (Citations omitted; internal quotation
marks omitted.)
Connecticut Carpenters Benefit Funds
Burkhard Hotel Partners II, LLC
,
We first address the reasoning set forth by the trial court in rendering summary judgment on the bond claim. The court held that ‘‘because Skanska already paid Semac . . . it was not obligated to pay the plaintiff . . . .’’ But see footnote 4 of this opinion. We disagree with the premise of this holding. Our Supreme Court in Seaman v. Climate Control Corp. , supra, 181 Conn. 596–97, addressed this precise question and clearly held that, under our mechanic’s lien statutes, recovery would not be barred to a second tier subcontractor solely because ‘‘the first tier subcontractor with whom they contracted has been paid in full by the general contrac- tor.’’ The trial court, therefore, erred in rendering sum- mary judgment on this ground. We next consider the alternative ground for affirmance raised by the defen- dants on appeal.
We have examined all of the cases raised by the
parties, as well as conducted our own examination of
our appellate case law, and we have found nothing
factually analogous with the present case. Accordingly,
we must determine, as a matter of first impression,
whether a lienable fund is exhausted when,
after proper
notice
that a subcontractor has filed a mechanic’s lien
on the property, the property owner continues to pay
the general contractor for work on the project until the
general contraсtor has been paid the full contract price.
Guided by our General Statutes, relevant legislative his-
tory, and our relevant case law, we conclude that when
the general contractor
is not in default
, unless there
were payments made in bad faith, the lienable fund is
the amount still owed by the property owner to the
general contractor at the time the property owner
receives notice of the lien pursuant to General Statutes
§ 49-34,
[9]
regardless of whether it continues to make
payments to the nondefaulted general contractor. See
General Statutes § 49-36 (c) (in determining amount of
lienable fund, property owner allowed credit for what-
ever good faith payments it has made to general contrac-
tor
before it received notice of lien
); see generally Gen-
eral Statutes § 49-35 (regarding subcontractor’s notice
of intent);
H & S Torrington Associates Lutz Engi-
neering Co.
,
Although, as noted previously in this opinion, neither this court nor our Supreme Court has addressed the precise issue before us, certain decisions by our Supreme Court interpreting the relevant statutes at issue in this case inform our analysis. We start with our Supreme Court’s decision in Seaman , a case quite similar in many respects to the present case, and one relied on by all parties on appeal. In Seaman , the plain- *13 tiff, who was the рroperty owner, contracted with a general contractor to construct apartment style hous- ing. Seaman Climate Control Corp. , supra, 181 Conn. 593. The general contractor then entered into a subcon- tract agreement for the installation of plumbing equip- ment on the project, and the subcontractor, thereafter, entered into two second tier subcontract agreements, one with a supplier and one with a servicer. Id., 593–94. The second tier subcontractors, who were the defen- dants in the case, had no contractual relationship with the plaintiff or the general contractor, and their work was not directed or controlled by either of them. Id., 594. The general contractor had paid the subcontractor nearly the full amount of its subcontract price when the subcontractor defaulted and walked off the job. Id., 594 and n.3. Although having been paid by the general contractor, the subcontractor had not paid the defen- dants. Id., 594–95. The defendants notified the property owner of their intention to file a mechanic’s lien; at that time, the property owner still owed the general contractor $89,157, with an additional cost of $8005.91 to complete the work left unfinished by the defaulting subcontractor. Id., 594. The defendants each filed a mechanic’s lien, one in the amount of $40,697.66 and the other in the amount of $7702, the total of which was ‘‘substantially less than the amount remaining due . . . to the general contractor . . . .’’ Id., 595. The par- ties thereafter stipulated that the $7702 amount should be $6526. Id. Unlike the hospital in the present case, the property owner in Seaman did not pay the general contractor the outstanding balance he owed, but, rather, he retained that money after receiving notice of the liens. Id., 596.
Our Supreme Court explained in Seaman : ‘‘The sub- contractors, even though they are second tier rather than first tier subcontractors, are prima facie within the ambit of the mechanic’s lien law. It is not necessary to their lien status that they have any direct contractual relationship either with the owner or with the general contractor (denominated the original contractor in the statutes). They have concededly given timely notice to the owner, in proper form, of their liens. There is an identifiable fund which appropriate claims for mechan- ic’s liens may reach, since the owner has retained an unpaid balance due under his contract with the general contractor that exceeds in amount the totality of the mechanic’s lien claims.’’ Id. Our Supreme Court then explained that the defendants, which were second tier subcontractors, were not barred from recovery on their liens simply because the first tier subcontractor, with whom they had contracted, had been paid in full by the general contractor. Id., 596–97.
Our Supreme Court then set forth its analysis of § 49- 33: ‘‘In interpreting this section, the complexity of which should not be underestimated . . . we are guided by [well settled] principles of construction. Although the *14 mechanic’s lien law creates a statutory lien in deroga- tion of the common law, its rеmedial purpose to furnish security for a contractor’s labor and materials requires a generous construction. . . . Even bearing in mind the statute’s beneficent purpose, we are, however, con- strained by the language of the statute as we find it, and cannot rewrite the statute or adopt the reasoning of precedents in other jurisdictions with different stat- utes. . . .
‘‘Two sentences in § 49-33 are central to the argu- ments of the parties. ‘[A] mechanic’s lien shall [not] attach to any . . . building . . . in favor of any sub- contractor to a greater extent in the whole than the amount which the owner has agreed to pay to any person through whom [the] subcontractor claims . . . . [General Statutes § 49-33 (e).] Any such subcon- tractor shall be subrogated to the rights of the person through whom such subcontractor claims . . . .’ [Gen- eral Statutes § 49-33 (f).] The plaintiff urges that the second sentence subrogates the second tier subcontrac- tor to the rights of the first tier subcontractor while the defendants claim to be subrogated to the rights of the general contractor. These disparate interpretations are crucial to this appeal, since the first tier subcontractor, having been fully paid, has no right to which anyone could be subrogated, while the general contractor, as yet partially unpaid, remains a suitable candidate for subrogation. The parties are at odds both about the significance of the exact wording of § 49-33 and about its relationship to our existing case law.’’ (Citations omitted; footnоte omitted.) Id., 597–99. The court explained that a second tier subcontractor is subro- gated to the rights of the general contractor when the first tier subcontractor defaults after having been paid, leaving unpaid the second tier subcontractor. Id., 603– 604. Our Supreme Court explained that it is significant that under our legislative scheme ‘‘all subcontractors are preferred to the general contractor if the lienable fund is inadequate to cover [all] outstanding claims.’’ [12] Id., 605; see General Statutes § 49-36. When considering the plaintiff’s argument in Seaman that the court’s con- struction of § 49-33 would result in the ‘‘unjust enrich- ment of second tier subcontractors,’’ our Supreme Court stated the following: ‘‘How the risk of defaulting first tier subcontractors should be allocated between the owner and the general contractor is not an issue presently before us, although we observe that contrac- tors generally are deemed to make a number of implied warranties, including the warranty that there are no outstanding liens. Cf. Uniform Commercial Code §§ 2- 312 and 3-417, General Statutes §§ 42a-2-312 and 42a- 3-417.’’ Id., 606.
The significant difference between the facts in Sea- man and the facts in the present case is that the prop- erty owner in Seaman , after he received notice of the second tier subcontractors’ liens, retained the balance *15 due to the nondefaulted general contractor, whereas, in the present case, the hospital, after it received notice of the plaintiff’s lien, continued to make payments to the nondefaulted general contractor, Skanska. The dеfendants argue that, pursuant to the language in §§ 49- 33 (e) and (f) and 49-36, this fact makes all the difference because the lienable fund became exhausted when the hospital paid the full contract price to Skanska.
In support of this argument, the defendants princi-
pally rely on our Supreme Court’s decision in
Rene Dry
Wall Co. Strawberry Hill Associates
,
The defendants argue that, applying the reasoning of Rene Dry Wall Co. , the plaintiff cannot collect on the bond because the combination of the amounts paid by the hospital in good faith prior to notice of the plaintiff’s lien and the amounts paid to Skanska to complete the construction project equal the amount the hospital agreed to pay for the project. Thus, they argue, there is no lienable fund available to the plaintiff. The plaintiff argues in response that Rene Dry Wall Co. is distinguish- able and inapplicable to this case because Skanska was never in default of its contract with the hospital. According to the plaintiff, pursuant to § 49-33, an owner is entitled to credits against the lienable fund only for payments made after notice of a subcontractor’s lien when it is required to make such payments because of the general contractor’s default. We agree with the *16 plaintiff.
Section 49-33 provides in relevant part: ‘‘(e) A mechanic’s lien shall not attach . . . in favor of any subcontractor to a greater extent in the whole than the amount which the owner has agreed to pay to any person through whom the subcontractor claims subject to the provisions of section 49-36.
‘‘(f) Any such subcontractor shall be subrogated to the rights of the person through whom the subcontrac- tor claims, except that the subcontractor shall have a mechanic’s lien or right to claim a mechanic’s lien in the event of any default by that person subject to the provisions of sections 49-34, 49-35 and 49-36, provided the total of such lien or liens shall not attach . . . to a greater amount in the whole than the amount by which the contract price between the owner and the person through whom the subcontractor claims exceeds the reasonable cost, either estimated or actual, as the case may be, of satisfactory completion of the contract plus any damages resulting from such default for which that person might be held liable to the owner and all bona fide payments, as defined in section 49-36, made by the owner before receiving notice of such lien or liens.’’
Section 49-36 provides in relevant part: ‘‘(a) No mechanic’s lien may attach . . . to a greater amount in the whole than the price which the owner agreed to pay for the building and its appurtenances or the development of any such lot, or the development of any such plot of land. . . .
‘‘(c) In determining the amount to which any lien or liens may attach . . . the owner of the [property] . . . shall be allowed whatever payments he has made, in good faith, to the original contractor or contractors, before receiving notice of the lien or liens . No pаyments made in advance of the time stipulated in the original contract may be considered as made in good faith, unless notice of intention to make the payment has been given in writing to each person known to have furnished materials or rendered services at least five days before the payment is made.’’ (Emphasis added.)
The plaintiff argues that, under a proper reading of these statutes, when the general contractor is not in default , the lienable fund must be determined at the time the lien is filed and notice given to the property owner. The defendants argue that the plaintiff’s inter- pretation of the statutes ‘‘would create a perverse incen- tive by encouraging property owners to terminate the general contractor when a subcontractor gives notice of a lien in order to take advantage of the reduction for the cost to complete the work. In other words, because [the plaintiff’s] interpretation of the statute[s] would permit the lienable fund to be reduced when the general contractor defaults or is terminated, a property owner who otherwise had no intention to terminate the *17 general contractor may do so after receiving notice of a lien in order to reduce the amount available to the lienor.’’ The defendants contend that the plain language of § 49-33 (f) ‘‘provides that the lienable fund is reduced by the cost to complete the contract, and that reduction applies whether or not the general contractor defaults.’’
During oral argument before this court, the plaintiff explained that it believed that the defendants’ construc- tion of our statutory scheme regarding mechanic’s liens would lead to absurd results because a lien or a bond, specifically meant to protect the subcontractors, includ- ing second tier subcontractors, would be useless because a nondefaulted general contractor, after a prop- erly noticed lien had been filed by a subcontractor, could get paid fully, including profit, thereby exhausting the fund, and the subcontractors would be left with no secured claim, despite their preference in the statute. During questioning by the appellate panel, this court asked Skanska’s counsel whether a nondefaulted gen- eral contractor essentially could just ask for full pay- ment from the property owner in exchange for bonding off every subcontractor lien, including second tier sub- contractors, thereby reducing the lienable fund to zero and avoiding the preference in the statutes in favor of the subcontractors. Skanska’s counsel responded that the second tier subcontractors still could bring a claim against the party with whom they had a written con- tract, and, he argued, if the situation were similar to the present case, where ‘‘there’s a bad actor sub[contractor, then] somebody gets the short end of the stick . . . .’’ We conclude that the defendants’ construction of our statutes is not only inconsistent with the language of the statutes, but it would lead to absurd results, incon- sistent with the legislative purpose of those statutes.
Although in derogation of the common law, the reme-
dial purpose of § 49-33 is to ‘‘furnish security for a
contractor’s labor and materials . . . .’’
Seaman Cli-
mate Control Corp.
, supra,
‘‘In [General Statutes (1918 Rev.) §] 5220 [(now § 49-
36)], the opening provision clearly applies to all
mechanics’ liens by whomsoever held, and provides
that they shall nоt exceed the total which the owner
was to pay under his contract. It then explicitly provides
that
the contractor’s own lien shall be subordinated
to those of subcontractors
,
entitling them to payment
before him
, and if the available fund does not pay the
subcontractor liens in full, the fund must be appor-
tioned between them. The subcontractor’s right to a
lien, though inchoate comes into existence when he
.
and becomes per-
begins furnishing materials .
.
fected when he files his lien
having complied with all
statutory requirements. These rights which are given
the subcontractor cannot be taken from him or abridged
by act of the contractor or the owner.’’ (Citation omit-
ted; emphasis added; internal quotation marks omitted.)
Purcell, Inc. Libbey
,
The defendants contend that older case law is not controlling because there was an important change in our statutes that occurred in 1953; see Public Acts 1953, No. 502, § 1; that modified what is now § 49-33. They contend that No. 502 of the 1953 Public Acts ‘‘add[ed] the language in what is now . . . § 49-33 (f) providing that the amount available to subcontractors is reduced by the ‘reasonable cost . . . of satisfactory completion of the contract . . .’ ’’ and that this language applies ‘‘whether or not the general contractor defaults.’’ The legislative history of No. 502 of the 1953 Public Acts does not support the defendants’ position.
In 1953, the House of Representatives introduced House Bill No. 1733, 1953 Sess., which ultimately became No. 502 of the 1953 Public Acts, modifying General Statutes (Cum. Supp. 1951) § 1273b (formerly General Statutes (1949 Rev.) § 7217), now § 49-33. In 1953, the legislature added the language, ‘‘except that such subcontractor shall have such a liеn or right to claim such a lien in the event of any default by such person . . . provided the total of such lien or liens shall not attach . . . to a greater amount in the whole than the amount by which the contract price between the owner and such person exceeds the reasonable cost . . . of satisfactory completion of the contract plus any damages resulting from such default for which such person might be held liable to the owner and all bona fide payments . . . made by the owner before receiv- ing notice of such liens or liens’’; see No. 502 of the 1953 Public Acts; which remains a part of § 49-33 today, specifically, § 49-33 (f). The defendants contend that the legislature meant this language to apply even when *19 the general contractor is not in default. The plaintiff contends that this language applies only when the gen- eral contractor is in default. In light of the legislative history of No. 502 of the 1953 Public Acts and the pur- pose for which it was enacted, we agree with the plaintiff.
House Bill No. 1733 was introduced to correct a statu-
tory problem that was uncovered by our Supreme Court
in
Rowley Salladin
,
In response to Rowley , members of the legislature introduced House Bill No. 1733. Representative Kenyon W. Greene, in moving for acceptance of the bill, explained that it was introduced to ‘‘provid[e] [that] the subcontractor’s right of [a] mechanic’s lien shall not be lost by default of the general contractor . . . .’’ 5 H.R. Proc., Pt. 8, 1953 Sess., pp. 3313–14; see also Conn. Joint Standing Committee Hearings, Judiciary, Pt. 3, 1953 Sess., pp. 760–63. Thus, what is now § 49-33 was amended to ensure that an owner could not use a gen- eral contractor’s default as an excuse not to pay a sub- contractor for work that benefitted the owner. At the same time, the amendment protected the owner who was forced to incur additional costs due to the general contractor’s default. There simply is nothing in the lan- guage or legislative history of the 1953 amendment that suggests that an owner is entitled to take credit for payments made to a general contractor not in default after having received notice of the subcontractor’s lien. In fact, such an interpretation would run contrary to the 1953 amendment’s intent to provide greater protec- tion to subcontractors.
Prior to the 1953 amendment to what is now § 49- 33, the only amounts the owner was entitled to credit against the lienable fund were ‘‘whatever payments he shall have made, in good faith, to the [general] contrac- tor or contractors before receiving notice of such lien or liens.’’ Gеneral Statutes (1949 Rev.) § 7220. The 1953 amendment gave the owner an additional credit for any funds it had to pay after notice of the subcontractor’s lien, due to the general contractor’s default . Such pro- tection for the owner makes sense because, once the general contractor defaults, the owner would be forced to find someone else to complete the project and would be required to pay that third party for their work. Under that specific circumstance, the legislature chose to *20 place the risk of the defaulting general contractor on the subcontractor and not the owner, to the extent the owner’s costs of completing the construction project equaled or exceeded the amount he had contracted to pay the general contractor. However, where the general contractor is not in default, there is no need to protect the owner by permitting it to continue to pay the general contractor at the expense of subcontractors who have filed valid mechanic’s liens on the owner’s property. The owner need only withhold payments from the general contractor until the subcontractor’s mechanic’s liens are resolved. There is no third party who was previously a stranger to the construction project that must be compensated for its work. In such a circumstance, the risk of not getting paid properly is placed on the general contractor, consistent with the preferеnce in favor of subcontractors expressly set forth in § 49-36 (b). Put another way, expanding the language of § 49-33 to pay- ments made when the general contractor is not in default, as suggested by the defendants, would eviscer- ate the protections provided to subcontractors in § 49- 36 (b) and (c).
Furthermore, the defendants’ interpretation of the relevant statutes would lead to absurd results in that it would permit an owner and a general contractor to render a subcontractor’s lien essentially meaningless. The facts of this case show exactly how such a result can be accomplished. It is undisputed that at the time the plaintiff filed its mechanic’s lien there were more than sufficient funds still unpaid by the hospital to Skan- ska to cover the plaintiff’s claim. Rather than withhold- ing money from Skanska to pay any amounts duly owed to the plaintiff pursuant to its lien, the hospital paid the full contract amount to Skanska. Under the defendants’ interpretation of § 49-33, doing so wiped out the lienable fund, and, with it, the plaintiff’s lien, and created a preference in favor of the general contractor at the expense of a subcontractor . Not only is there nothing in the language or legislative history of § 49-33 that remotely suggests such a result; the result is flatly con- trary to the preference in favor of subcontractors set forth in § 49-36 (b). We cannot conclude that the legisla- ture intended a result that is so completely at odds with the remedial purpose of the mechanic’s lien statutes.
Finally, the defendants’ claim that the plaintiff’s read- ing of §§ 49-33 and 49-36 would lead to the perverse result that owners would be incentivized to find a rea- son to hold general contractors in default makes little sense. According to the defendants, an owner who has received notice of a mechanic’s lien from a subcontrac- tor would be motivated to manufacture a default by the general contractor in order to terminate the general contractor in order to reduce the size of the lienable fund available to the subcontractor. There are several problems with this hypothesis. First, it ignores what could be significant transaction costs the owner would *21 incur by replacing a performing contactor with a new contractor unfamiliar with the project. Second, it ignores the fact that, by engaging in such conduct, the owner would expose itself to liability to the general contractor for breach of contract. Third, to the extent the owner concluded that it would be profitable to breach its contract with the general contractor, whether a subcontractor filed a mechanic’s lien likely would not change that conclusion. Finally, the defendants have not described a precise scenario that would lead an owner to manufacture a default by the general contrac- tor, and we cannot think of a scenario in which the owner would not be acting against its economic interest by terminating the general contractor simply to reduce thе amount available to a subcontractor lienor. The amount available to the subcontractor lienor would only be reduced to the extent that the owner paid an amount equal to or greater than its contract price with the defaulted general contractor. It would defy logic for an owner to terminate a general contractor just so it can incur more costs to avoid paying the subcontractor lienor.
On the basis of the foregoing analysis, we conclude that the lienable fund was the amount owed by the hospital to Skanska at the time the plaintiff gave notice of its mechanic’s lien to the hospital in accordance with §§ 49-34 and 49-35. Accordingly, the defendants’ alternative ground for affirmance fails.
The judgment is reversed with respect to counts two and three of the plaintiff’s complaint, and the case is remanded to the trial court for further proceedings according to law; the judgment is affirmed in all other respects.
In this opinion the other judges concurred.
[1]
The plaintiff withdrew the matter as to the named defendant, The Stam-
ford Hospital. Fidelity is the surety that issued a bond in substitution for
the mechanic’s lien that the plaintiff had filed against the hospital. See
General Statutes §§ 49-33 and 49-37.
[2]
Semac Electrical Company, Inc. (Semac), also is a defendant in this
matter. Although Semac initially had appeared by counsel in the trial court,
the court, on December 12, 2017, granted counsel’s motion for permission
to withdraw its appearance. No further action appears to havе been taken
against Semac, who now is a nonappearing defendant, and the matter
remains pending as to Semac in the trial court. For purposes of this appeal,
we refer to Skanska and Fidelity as the defendants unless further clarification
is necessary.
[3]
The court also rendered summary judgment in favor of Skanska as to
count one of the plaintiff’s complaint, which alleged that Skanska had
breached a contract with the plaintiff. The plaintiff does not challenge that
judgment in this appeal. Thus, we affirm the judgment in favor of Skanska
as to count one.
[4]
Although Skanska had alleged in its answer that it fully had paid Semac
for the plaintiff’s work, Miller made no such attestation in his affidavit. In
fact, he averred that ‘‘[t]he total amount paid to the replacement electrical
contractors exceeded
the remaining amount
of the original subcontract
with Semac.’’ (Emphasis added.)
to whether Skanska ever paid for the plaintiff’s services, we need not address
Because we conclude that there is a genuine issue of material fact as
whether the plaintiff could prevail on its claim in the event that Skanska
fully had paid Semac for the plaintiff’s work, if the plaintiff proves that
Skanska, despite such payment, had requested that the plaintiff continue
*22
performing work on the project. We also need not determine whether there
are additional issues of material fact that rendered summary judgment inap-
propriate.
[6]
General Statutes § 49-33 provides in relevant part: ‘‘(a) If any person has
a claim for more than ten dollars for materials furnished or services rendered
in the construction, raising, removal or repairs of any building or any of its
appurtenances or in the improvement of any lot or in the site development
or subdivision of any plot of land, and the claim is by virtue of an agreement
with or by consent of the owner of the land upon which the building is
being erected or has been erected or has been moved, or by consent of the
owner of the lot being improved or by consent of the owner of the plot of
land being improved or subdivided, or of some person having authority from
or rightfully acting for the owner in procuring the labor or materials, the
building, with the land on which it stands or the lot or in the event that the
materials were furnished or services were rendered in the site development
or subdivision of any plot of land, then the plot of land, is subject to the
payment of the claim. . . .
‘‘(e) A mechanic’s lien shall not attach to any such building or its appurte-
nances or to the land on which the same stands or to any lot or to any plot
of land, in favor of any subcontractor to a greater extent in the whole than
the amount which the owner has agreed to pay to any person through whom
the subcontractor claims subject to the provisions of section 49-36.
‘‘(f) Any such subcontractor shall be subrogated to the rights of the person
through whom the subcontractor claims, except that the subcontractor shall
have a mechanic’s lien or right to claim a mechanic’s lien in the event of
any default by that person subject to the provisions of sections 49-34, 49-
35 and 49-36, provided the total of such lien or liens shall not attach to any
building or its appurtenances, or to the land on which the same stands or
to any lot or to any plot of land, to a greater amount in the whole than the
amount by which the contract price between the owner and the person
through whom the subcontractor claims exceeds the reasonable cost, either
estimated or actual, as the case may be, of satisfactory completion of the
contract plus any damages resulting from such default for which that person
might be held liable to the owner and all bona fide payments, as defined
in section 49-36, made by the owner before receiving notice of such lien or
liens. . . .’’
General Statutes § 49-36 provides in relevant part: ‘‘(a) No mechanic’s
lien may attach to any building or its appurtenances, or to the land on which
the same stands, or any lot, or any plot of land, in favor of any person, to
a greater amount in the whole than the price which the owner agreed to
pay for the building and its appurtenances or the development of any such
lot, or the development of any such plot of land. . . .
‘‘(c) In determining the amount to which any lien or liens may attach
upon any land or building, or lot or plot of land, the owner of the land or
building or lot or plot of land shall be allowed whatever pаyments he has
made, in good faith, to the original contractor or contractors, before receiving
notice of the lien or liens. No payments made in advance of the time stipu-
lated in the original contract may be considered as made in good faith,
unless notice of intention to make the payment has been given in writing
to each person known to have furnished materials or rendered services at
least five days before the payment is made.’’
General Statutes § 49-37 provides in relevant part: ‘‘(a) Whenever any
mechanic’s lien has been placed upon any real estate pursuant to sections
49-33, 49-34 and 49-35, the owner of that real estate, or any person interested
in it, may make an application to any judge of the Superior Court that the
lien be dissolved upon the substitution of a bond with surety, and the judge
shall order reasonable notice to be given to the lienor of the application.
. . .’’
[7]
Pursuant to Practice Book § 63-4, Skanska and Fidelity submitted this
argument as an alternative ground for affirmance.
, supra,
‘‘(2) A warranty under subsection (1) will be excluded or modified only
by specific language or by circumstances which give the buyer reason to
know that the person selling does not claim title in himself or that he is
purporting to sell only such right or title as he or a third person may have.
‘‘(3) Unless otherwise agreed a seller who is a merchant regularly dealing
in goods of the kind warrants that the goods shall be delivered free of the
rightful claim of any third person by way of infringement or the like but a
buyer who furnishes specifications to the seller must hold the seller harmless
against any such claim which arises out of compliance with the specifi-
cations.’’
General Statutes § 42a-3-417, as amended by No. 91-304 of the 1991 Public
Acts, provides: ‘‘(a) If an unaccepted draft is presented to the drawee for
payment or acceptance and the drawee pays or accepts the draft, (i) the
person obtaining payment or acceptance, at the time of presentment, and
(ii) a previous transferor of the draft, at the time of transfer, warrant to the
drawee making payment or accepting the draft in good faith that: (1) The
warrantor is, or was, at the time the warrantor transferred the drаft, a person
entitled to enforce the draft or authorized to obtain payment or acceptance
of the draft on behalf of a person entitled to enforce the draft; (2) the draft
has not been altered; and (3) the warrantor has no knowledge that the
signature of the drawer of the draft is unauthorized.
‘‘(b) A drawee making payment may recover from any warrantor damages
for breach of warranty equal to the amount paid by the drawee less the
amount the drawee received or is entitled to receive from the drawer because
of the payment. In addition, the drawee is entitled to compensation for
expenses and loss of interest resulting from the breach. The right of the
drawee to recover damages under this subsection is not affected by any
failure of the drawee to exercise ordinary care in making payment. If the
drawee accepts the draft, breach of warranty is a defense to the obligation
of the acceptor. If the acceptor makes payment with respect to the draft,
the acceptor is entitled to recover from any warrantor for breach of warranty
the amounts stated in this subsection.
‘‘(c) If a drawee asserts a claim for breach of warranty under subsection
(a) based on an unauthorized endorsement of the draft or an alteration of
the draft, the warrantor may defend by proving that the endorsement is
effective under section 42a-3-404 or 42a-3-405 or the drawer is precluded
under section 42a-3-406 or 42a-4-406 from asserting against the drawee the
unauthorized endorsement or alteration.
‘‘(d) If (i) a dishonored draft is presented for payment to the drawer or
an endorser or (ii) any other instrument is presented for payment to a party
obliged to pay the instrument, and (iii) payment is received, the following
rules apply: (1) The person obtaining payment and a prior transferor of the
instrument warrant to the person making payment in good faith that the
warrantor is, or was, at the time the warrantor transferred the instrument,
a person entitled to enforce the instrument or authorized to obtain payment
on behalf of a person entitled to enforce the instrument. (2) The person
making payment may recover from any warrantor for breach of warranty
an amount equal to the amount paid plus expenses and loss of interest
resulting from the breach.
‘‘(e) The warranties stated in subsections (a) and (d) cannot be disclaimed
with respect to checks. Unless notice of a claim for breach of warranty is
given to the warrantor within thirty days after the claimant has reason to
know of the breach and the identity of the warrantor, the liability of the
warrantor under subsection (b) or (d) is discharged to the extent of any
loss caused by the delay in giving notice of the claim.
when the claimant has reason to know of the breach.’’
‘‘(f) A cause of action for breach of warranty under this section accrues
We note that § 49-33, referenced in
Rene Dry Wall Co. Strawberry
Hill Associates
, supra,