This appeal concerns the military contractor defense,
see Boyle v. United Technologies Corp.,
Background
On February 23, 1987, Scott Lewis was flying a United States Air Force F-lll-F jet fighter over England. When the plane malfunctioned, he initiated ejection of the self-contained crew module. The crew module is designed so that once the pilot initiates ejection, all subsequent operations until landing occur automatically. After the module separates from the aircraft, a parachute system deploys, and large bags on the bottom of the module cushion the landing. In this case, however, the forward repositioning cable, one of two cables that connect the parachute to the module, severed, causing the module to land at an incorrect angle without adequate cushioning. Lewis sustained spinal injuries.
The Air Force concluded, after a post-accident investigation, that the breaks in the forward repositioning cable were caused by corrosion. The cable was made of high carbon steel, which is corrosive unless protected. The cable was protected by a polyolefin coating, which adequately protects the steel as long as the coating is not cut. During normal operations, the cable rests under a light metal cover in a channel in the center of the windshield. General Dynamics Corp. designed and man
During the design phase, the entire crew module was designated a “critical item” by the Air Force. Items were designated critical by virtue of their unusual complexity, developmental nature, extreme cost, or relevance to safety. Because of their importance, the Air Force subjected the design and development of “critical items” to extensive review. The forward repositioning cable itself, however, was a "non-critical item.” The Government did not dictate the materials from which to make the cable, but only its required dimensions and strength. Early in the design process, the Government performed an extensive review of the entire crew module, as a critical item, during the so-called First Article Configuration Inspection (“the FACI”) and during tests of the module. The parties dispute the level of attention paid by the Government to the forward repositioning cable, a non-critical item, during the FACI and whether the Government was aware of the cable’s composition and susceptibility to corrosion at that time.
After General Dynamics delivered the F-111s to the Air Force, the Air Force made an initial redesign of the windshield of the F-lll for reasons not relevant to the pending appeal. The Air Force selected a different contractor for this redesign. The redesigned windshield was connected to the aircraft with clips located in the same channel as the forward repositioning cable. The Air Force eventually noticed corrosion of the cables in the aircraft with the new windshield design. After an investigation completed in 1980, the Air Force determined that the clips from the modified windshield were cutting the cable’s protective coating, thus allowing moisture to reach the carbon steel cable and cause corrosion.
The Air Force decided to replace the forward repositioning cables on all F-llls. The cable in the aircraft involved in Lewis’s accident was replaced on January 21, 1983, with a cable purchased from Babcock. The Air Force also changed its maintenance manual to warn its personnel to be careful not to cut the cable’s coating during maintenance operations. The Air Force did not change the windshield design, nor did it change the cable composition from that of the original Babcock cable. At least by this time, the Air Force was aware of the cable’s susceptibility to corrosion if its coating was cut. After the crash of Lewis’s plane, the Air Force performed more tests. Based on these tests, the Air Force decided to continue use of the Babcock cable and to make a second redesign of the windshield to avoid its cutting of the cable’s coating.
Lewis ejected from a plane equipped with a replaced cable and a windshield constructed according to the first redesign. The cable broke in two places, only one of which was in the portion of the cable resting in the channel where the windshield clips were located. The parties dispute whether the other break was caused by corrosion or whether it was the result of the added stress created as the portion of the cable originally located in the channel was breaking. Lewis and his wife, claiming derivatively, sued General Dynamics, McDonnell Douglas, and Babcock (collectively “appellees”) alleging negligence in their design of the cable because the high carbon steel chosen was susceptible to corrosion from moisture and the polyolefin protective coating was easily cut, thereby limiting its effectiveness. Their complaint also contained claims based on theories of strict liability and breach of warranty. Judge Cannella granted appellees’ motion for summary judgment based on the military contractor defense of Boyle.
Discussion
I. The military contractor defense
In
Boyle,
the Supreme Court held that the federal common law provides certain military contractors with a defense against suits based on state tort law. The defense is applicable only to those contractors for whom the duties of care imposed by state tort law conflict with the duties imposed by their federal contract. Under this defense,
The first element ensures that the design specification at issue actually was considered by a government official — or, in other words, that a government official had made the type of policy decision considered a discretionary function under the [Federal Tort Claims Act]. The second element ensures that the supplier actually acted upon the Government’s discretion. The final element encourages the contractor to provide all information at its disposal to the government official and in so doing facilitates a fully informed decision by the government official.
In re Joint Eastern and Southern District New York Asbestos Litigation,
As to the first requirement, the District Court found that during the FACI, the Government examined and approved every component of the module, including the cable, and that the Government conducted extensive testing of the crew escape module, including the cable. The District Court found especially persuasive the fact that the Air Force continued to use the cable after it found out that it was susceptible to corrosion when it was cut. In effect, the District Court held that approval may be established by the Government’s continued use of a product after it learns of the defect. The District Court found that appellees met Boyle’s second requirement because the Government had inspected and accepted the aircraft when it was first delivered and had also inspected and accepted the replacement cables produced by Bab-cock. Finally, the Court held that appel-lees met Boyle’s third requirement because the Air Force, from its experience with the aircraft, had greater knowledge than appel-lees of the corrosion problem.
II. Does Boyle have prerequisites?
Lewis urges us to adopt an interpretation of Boyle under which the three-part test outlined above is not applied unless two prerequisites are established: a significant conflict between the requirements under the federal contract and state tort law, and the Government’s exercise of its discretion in accepting a safety risk. In rejecting this argument, the District Court concluded that it makes more sense to consider whether a significant conflict exists in determining the first element of the Boyle test, approval of reasonably precise specifications, rather than as a prerequisite, because “[b]y satisfying this element, the contractor establishes that a conflict exists between state law which imposes liability and the duty imposed by the Government contract.” In considering the first element, the District Court also examined whether the Government exercised discretion or merely “rubber stamped” the design.
Although, at the end of the analysis, federal common law provides the contractor with a defense only if there is both (a) a conflict between the requirements of state tort law and those of the Government contract and (b) an exercise of Government discretion in considering the design feature in question, we agree with the District Court’s approach that these inquiries are part of the
Boyle
test and not prerequisites to it. The purpose of the first part of the test, approval of reasonably precise specifications, is to determine whether a conflict with state law exists at all. As we indicated in
Grispo,
a federally imposed contract requirement displaces only a parallel state law requirement.
We also disagree with Lewis’s proposition that the Government’s exercise of discretion in accepting a safety risk should be considered a prerequisite to applying the three-part
Boyle
test. In its search for a limiting principle for the military contractor defense, the Supreme Court rejected the
Feres
doctrine,
see Feres v. United States,
III. At what point in time should the Boyle test be applied?
The parties’ dispute turns in large part on the time when the Boyle test is to be applied. Lewis asserts that a contractor can meet the requirements of Boyle, if at all, only during the design phase and argues that with reference to that time, summary judgment is not appropriate in this case. Appellees respond that they can satisfy the requirements of Boyle through Government approval that occurs at any time prior to the accident. We understand the District Court’s opinion to adopt the appellees’ approach to the time frame. Judge Cannella found the first element satisfied by events that happened at the design stage and by the Air Force’s responses to problems of which it learned during its experience with the F-lll after the aircraft were delivered. He found the second element satisfied based on the Government’s acceptance, after review, of the aircraft and the replacement cables. He found the third element established because the Air Force knew of the cable’s susceptibility to corrosion long before the accident occurred based on its analysis of the corrosion problem that led it to replace all the cables in the early 1980s. At least for the third requirement, the District Court did not determine whether appellees, during the design phase, adequately informed the Government of problems in the cable’s design of which their knowledge was superior to the Government’s. The Court made this determination only at the post-design stage.
The Fourth Circuit has twice dealt with situations presenting the question of when the
Boyle
test should be applied. In the first case,
Dowd v. Textron, Inc.,
The Court rejected the plaintiffs’ argument that since the manufacturer originally designed the rotor system without Army participation, the Government had not approved reasonably precise specifications. It reasoned that “[t]he length and breadth of" the Army’s experience with the 540 rotor system — and its decision to continue using it — amply establish government approval of the alleged design defects.” Id. at 412 (emphasis added). The Army required the manufacturer to use the original rotor system in the new version of the helicopter, and the manufacturer could not modify the design without Government approval. See id. The Court was also concerned that if the manufacturer’s negligence at the initial design stage created permanent future liability, the manufacturer’s incentive to propose safety modifications for its product would be diminished. See id.
In the second case,
Ramey v. Martin-Baker Aircraft Co.,
Our ease presents a factual scenario that is less compelling for the application of the military contractor defense at the post-design phase than Dowd, but more compelling than Ramey. In Dowd, the Army was in the process of ordering a new helicopter that would modify certain aspects of the previous version of the helicopter. The Army’s experience with the rotor system, a design that it had not originally approved, came from its experience with the prior versions of the helicopter. In addition, to aid the Army’s evaluation of the alleged design defect, the manufacturer presented alternative designs. In effect, the decision in Dowd to continue use of the rotor system was made at the design stage of the new version of the helicopter and was informed by alternative designs. In our ease, by contrast, the Air Force was evaluating an alleged design defect in an aircraft that had already been produced, and alternative designs for the cable were not evaluated until after Lewis’s accident.
Consideration of these Fourth Circuit cases leads us to agree with the District Court and appellees that a contractor may satisfy the Boyle test after the design stage has been completed, at least in the situation presented here. Although the Government was not in the process of designing a new aircraft as in Dowd, the Government reordered the same cable to replace existing ones. It was one of these replacement cables that failed in the accident at issue. This reorder occurred after the Government had completed its investigation into the problem and while it knew that the Babcock cable was susceptible to corrosion if the protective coating was cut. We hold that when the Government reordered the specific Babcock cable, with knowledge of its alleged design defect, the Government approved reasonably precise specifications for that product such that the manufacturer qualifies for the military contractor defense for any defects in the design of that product. 3
The Air Force exercised its discretion in deciding that changes in the maintenance manual along with replacement of the existing cables were a sufficient response to the corrosion problem. After Lewis’s accident, faced with alternative designs for the cable, the Air Force chose to redesign the windshield a second time and to continue use of the Babcock cable. Whether or not these decisions were ill-advised, or should have been made earlier, it is not our role to second-guess the Air Force’s judgment. And since the Government specifically requested the cable that failed despite awareness of its alleged design defect, thus precluding characterization of the cable as a stock item that happens to have a design defect, we also cannot second-guess the contractor's decision regarding the materials to be used for the cable. Based on the reorder, the contractor can claim: “ ‘The Government made me do it.’ ”
Grispo,
The remaining two parts of Boyle were also appropriately determined in appellees’ favor on motion for summary judgment. Appellees have met the second part of the Boyle test, conformity with reasonably precise specifications, because when the Government reordered the cable, it received exactly what it sought — a cable that had certain dimension and strength characteristics, made of carbon steel coated by polyolefin. The Government also approved the replacement cable shipments it received.
Moreover, since we are evaluating the
Boyle
test at the time the Government reordered the cable, it is clear that the third requirement is also met. There is no
Conclusion
Because the District Court correctly granted appellees’ motion for summary judgment under the military contractor defense based on the Government’s actions and knowledge in the post-design stage, we affirm.
Notes
. This proposition was illustrated by the Supreme Court in
Boyle
when it noted that there would be no conflict between a federal contract for the purchase of an air conditioner that speci-
. The Court alternatively ruled that the Navy’s participation in the design amounted “to more than a rubber stamping," and thus was sufficient to qualify as approval of reasonably precise specifications. Id. at 950.
. We do not decide whether the contractor can invoke the military contractor defense where the Government merely tolerates a defect through continued use of a product in the face of knowledge of a design defect acquired after the design stage ended. The District Court may have relied primarily on the Government’s continued use of the cables, though it did refer to replacement.
. We need not decide whether the initial windshield redesign was, as a matter of law, an intervening cause of the cable’s failure such that appellees would be relieved of liability.
Furthermore, Lewis has not presented a claim or a sufficient factual basis supporting a claim that the defense should not apply because the appellees’ actions at the design stage so constricted the Government’s discretion when it reordered the cable that the Government was precluded from making the same decision (to reject or demand modification) that it would have made if presented with the issue at the design stage.
