Lead Opinion
PRM Energy Systems, Inc. (“PRM”), licensed certain gasification technology patents to Primenergy, L.L.C. (“Primenergy”). Through a network of agreements (the “1999 Agreements”), PRM licensed Primenergy to use the gasification technology and enter into sublicense agreements in a number of countries. After a series of disputes between PRM and Primenergy, PRM brought claims against Kobe Steel, Ltd. (“Kobe Steel”), a potential licensee, for tortious interference with, and inducement to breach, the 1999 Agreements and for conspiring with Primenergy to convert PRM’s intellectual property for their own use.
Kobe Steel moved to compel arbitration of PRM’s claims pursuant to arbitration provisions in the 1999 Agreements, and the district court
I.
To give context to this dispute, we set forth the facts as alleged in PRM’s complaint.
In the 1999 Agreements, PRM licensed Primenergy to use PRM’s gasification technology in a number of countries, including the United States but not including Japan. Although Primenergy’s license did not extend to Japan, Primenergy maintains that the 1999 Agreements gave it a right of first refusal for a license in Japan. In 2001, a U.S. subsidiary of Kobe Steel (a Japanese company) contacted PRM and expressed its interest in licensing the technology in the United States. PRM referred the subsidiary to Primenergy. In 2002, Kobe Steel began discussing licensing in Japan with PRM, but Kobe Steel declined to sign a confidentiality agreement, and the discussions stalled. At the same time, Kobe Steel was allegedly negotiating with Primenergy, inducing Primenergy to breach the 1999 Agreements by sublicensing the technology to Kobe Steel and planning joint projects in Japan. In 2003, Kobe Steel and Primenergy reached a collaboration agreement in violation of the territorial restrictions in the 1999 Agreements. Neither Primenergy nor Kobe Steel disclosed this agreement to PRM.
Unaware of the collaboration between Primenergy and Kobe Steel, PRM executed an option granting an unrelated company a license for the technology in Japan. In 2004, Primenergy filed a demand for arbitration seeking to force PRM to terminate the option, citing Primenergy’s purported right of first refusal. Primenergy also sought to invalidate certain royalty provisions of the 1999 Agreements because the underlying patents had expired. PRM asserted several cross-claims in the arbitration, including a claim that Primenergy breached the 1999 Agreements by having undisclosed dealings with Kobe Steel. In a final ruling on April 22, 2005, an arbitrator found that the royalty provisions were unenforceable and that both parties had breached the 1999 Agreements in regard to obligations concerning the territory of Japan. The arbitrator enjoined Primenergy from further discussions with Kobe Steel for a period of two years, but it did not award damages because PRM had not shown any.
In 2004, while the arbitration between PRM and Primenergy was pending, PRM
On November 18, 2005, PRM filed an amended complaint against Kobe Steel, asserting the existence of a confidentiality agreement and several exclusive collaboration agreements between Primenergy and Kobe Steel. PRM further alleged that Primenergy and Kobe Steel conspired to hide their dealings from PRM and that Primenergy and Kobe Steel, through their concerted actions, were attempting to negotiate lower royalty premiums and broader territorial rights for the licensing of PRM’s technology.
On March 21, 2006, the district court confirmed an April 2005 arbitration decision from the arbitration between PRM and Primenergy. Kobe Steel and PRM then filed cross-motions for judgment on the pleadings as to PRM’s claims against Kobe Steel. On June 19, 2006, the district court granted Kobe Steel’s motion in part, allowing Kobe Steel to compel arbitration. The district court also entered a stay of the proceedings. The district court held that Kobe Steel could enforce the arbitration provisions of the 1999 Agreements on an estoppel theory because “all of PRM’s claims either make reference to or presume the existence of the 1999 Agreements, and allege substantially interdependent and concerted misconduct by both the nonsignatory [Kobe Steel] and one or more of the signatories [Primenergy] to the contract.” An arbitrator subsequently dismissed the claims against Kobe Steel. The district court later confirmed the arbitrator’s dismissal of the claims, and PRM now appeals the June 19, 2006 order compelling the arbitration.
II.
“This court reviews de novo a district court’s grant of a motion to compel arbitration.” Donaldson Co., Inc. v. Burroughs Diesel, Inc.,
The Supreme Court issued Arthur Andersen, and our court issued Donaldson, however, long after the district court ordered and subsequently confirmed arbitration in the present case and after the parties briefed and argued this matter to our court. Below, the district court applied federal law to address Kobe Steel’s ability to invoke the arbitration provisions of the contract between PRM and Primenergy. In its brief on appeal, PRM argues that federal law applies, and Kobe Steel cites only federal law in its brief as to this issue. Accordingly, we rely primarily upon the federal law as discussed by the parties on appeal, and by the district court below, regarding the ability of a nonsignatory to compel arbitration.
As a starting point, we note that a nonsignatory may compel a signatory to arbitrate claims in limited circumstances. See, e.g., Finnie v. H & R Block Fin. Advisors, Inc.,
In CD Partners, we recognized two such circumstances. See CD Partners,
The specific theory or test for application of alternative estoppel that formed the basis of the district court’s decision in the present case relies on the interdependent and concerted misconduct of a nonsignatory and a signatory. Kobe Steel argues that the district court was correct in applying this test. In addition, Kobe Steel argues that other theories of alternative estoppel apply and that the close relationship or agency theory recognized in CD Partners provides an independent basis for compelling arbitration in the present case. Because we conclude that the district court correctly relied upon the theory of concerted misconduct, we confine our discussion to concerted misconduct.
In CD Partners, we relied upon MS Dealer in which the Eleventh Circuit set forth the theory of concerted misconduct as a basis to compel arbitration when there is no agency or other close relationship between the signatory plaintiff and nonsignatory defendant. MS Dealer,
Subsequently, in Donaldson, we discussed concerted misconduct at some length, described the type of claims and allegations that would be necessary to invoke this theory, but found the theory inapplicable on the facts of that case.
Here, we believe that the nature of the alleged misconduct and its connection to the contract demonstrates the requisite relationships between persons, wrongs, and issues necessary to compel arbitration. PRM “specifically allege[d] coordinated behavior between a signatory and a non-signatory.” Id. The 1999 Agreements anticipated that an entity such as Kobe Steel might enter into a licensing relationship with Primenergy, and the 1999 Agreements attempted to govern that expected relationship. This is not a situation, then, where the nonsignatory co-conspirator “is a complete stranger to the plaintiffs’ ... agreements!]] ... did not sign them, ... is not mentioned in them, and ... performs no function whatsoever relating to their operation.” Ross,
Collusive conduct between Kobe Steel and Primenergy allegedly arose from this potential relationship. PRM alleges that Kobe Steel and Primenergy concealed their actions from PRM, conspired to violate the terms of the 1999 Agreements, and attempted to undermine the 1999 Agreements’ contemplated authority over licensee and sub-licensee relationships. The alleged collusive actions not only arose out of and targeted the 1999 Agreements, they were “intimately founded in and intertwined with” Primenergy’s underlying contract obligations. Donaldson,
III.
PRM further contends that even if Kobe Steel can compel arbitration, PRM’s claims against Kobe Steel are outside of the scope of the arbitration clause of the 1999 Agreements. “[A]s a matter of federal law, any doubts concerning the scope of arbitrable issues should be resolved in favor of arbitration,” including “the construction of the contract language itself.” Moses H. Cone Mem’l Hosp. v. Mercury Constr. Corp.,
The arbitration clause here covers “all disputes arising under” the agreement, and PRM argues this language is substantially narrower than the corresponding language at issue in CD Partners. The CD Partners arbitration clause included
Arbitration may be compelled under “a broad arbitration clause ... as long as the underlying factual allegations simply ‘touch matters covered by’ the arbitration provision.” SM Co. v. Amtex Sec., Inc.,
IV.
For the foregoing reasons, we affirm the judgment of the district court.
Notes
. The Honorable Jimm Larry Hendren, Chief Judge, United States District Court for the Western District of Arkansas.
. The district court's interlocutory order directing arbitration and staying the proceedings was not an immediately appealable "final decision.” Green Tree Fin. Corp.-Ala. v. Randolph,
. Kobe Steel cited Arthur Andersen and an Arkansas case, American Insurance Company v. Cazort,
. In determining the arbitrability of a dispute, we generally apply these principles as matters of "federal substantive law,” Moses H. Cone,
Dissenting Opinion
dissenting.
I disagree with the court’s conclusion that the nature of PRM’s claims are connected to the contract and demonstrate the requisite relationships between persons, wrongs, and issues necessary to compel arbitration. The arbitration clause tangentially at issue here purports to cover “all disputes arising under” a technology licensing agreement between PRM and Primenergy.
The problem is, insofar as this appeal is concerned, that PRM asserts only a garden variety tort claim against Kobe Steel that does not directly touch either the subject matter or the geographic reach of the PRM/Primenergy contract itself. Indeed, according to PRM, the tortious activities of Kobe Steel deal with transactions beyond the scope, and purposefully outside of, the licensing authority granted Primenergy. To be sure, it is axiomatic that in order for Kobe Steel to have engaged in the alleged misconduct it must have had knowledge of the 1999 Agreements but that is the extent of the allegations’ involvement with those agreements.
Thus, the concerted misconduct requirements of Donaldson, the case that mainly drives the court’s analysis in this appeal, are almost totally absent.
I dissent.
