S. J. PRINCE et al., Respondents, v. WILLIAM J. HILL et al., Appellants
S. F. No. 6508
Supreme Court of California
May 13, 1915
Hearing in Bank denied June 12, 1915
170 Cal. 192
SHAW, J.
Department One
Rehearing denied.
MECHANIC‘S LIEN—VOID CONTRACT—LIEN OF SUBCONTRACTOR LIMITED TO AGREED PRICE.—Where the original contract for the erection of a building is void as between the owner and the contractor, a subcontractor, who has furnished materials and done work upon the building for the contractor at an agreed price, is entitled to a lien, under
ID. NOTICE OF LIEN—NAME OF PERSON TO WHOM MATERIALS WERE FURNISHED.—The notice of lien of a subcontractor sufficiently shows the name of the person to whom the materials were furnished, whеn it states that a designated person “is the name of the contractor,” who on a day certain “entered into a contract in writing with” the claimants, under which the latter were to perform labor and furnish materials to be used in the construction of the building, and then sets out the subcontract, states that it has been fully pеrformed by the claimant, and that the building has been completed.
APPEAL—PETITION FOR REHEARING—NEW POINTS NOT CONSIDERED.—The supreme court will not on a petition for a rehearing consider new points not mеntioned in the briefs upon which the case was submitted.
The facts are stated in the opinion of the court.
Charles B. Rosendale, and C. F. Lacey, for Appellants.
J. H. Andresen, and W. S. White, for Respondents.
SHAW, J.—The records presеnt an appeal from an order denying the defendants’ motion for a new trial.
The plaintiffs sued to foreclose a lien for work done and materials furnished by them to the defendant, Whitcomb, in the erection by Whitcomb of a building upon the land of the defendants, William J. and Isabelle A. Hill. The contract between Whitcomb аnd the Hills was for more than one thousand dollars and, although in writing, was not recorded. It was therefore void with respect to lien claimants.
The plaintiffs agreed with Whitcomb to do the carpenter work and furnish certain materials for the building for the sum of eight hundred and twenty dollars. It is alleged that certain extra work was done and additional materials furnished, at Whitcomb‘s request, of the value of $183.66 and that there remains unpaid of these two sums a balance of $217.66. Judgment was given declaring and foreclosing a lien on the land for this amount.
Upon the trial, the court below admitted evidence, over the defendants’ objection, tending to show thаt the value of the materials furnished and work done for Whitcomb by the plaintiffs, upon the building, was greater than the agreed price thereof. In admitting this evidencе the court below stated that the plaintiffs were entitled to a lien for the value of such work and materials although such value exceeded the contract price for which they had agreed with Whitcomb to do and furnish the same. In these rulings the court erred. Even with regard to the contract between the ownеr and the original contractor, the decision in Rebman v. San Gabriel etc. Co., 95 Cal. 395, [30 Pac. 564], to the effect that the original contractor may recover more than his contract pricе where such contract is void under the statute, has long been overruled and such recovery is limited to the contract price. (Laidlaw v. Marye, 133 Cal. 176, [65 Pac. 391]; Marchant v. Hayes, 117 Cal. 669, [49 Pac. 840]; Sullivan v. California
Our attention is called to the decision of the district court of аppeal in Panama etc. Co. v. Tingey, 26 Cal. App. 576, [147 Pac. 585], in which that court apparently held that under the statute requiring contractors for street work to give a bond to secure to laborers аnd materialmen the value of work done and materials furnished for the improvement, the actual value of the work or materials is the measure of the recovery and not the amount agreed upon. We need express no opinion as to the soundness of this opinion as applied to the street-wоrk law. It is of no binding force as an interpretation of the Mechanics’ Lien Law, and, so far as the latter is concerned, it is contrary to our own decisiоns, which are paramount in authority to those of the district court of appeal.
But although the court admitted this evidence, its finding was not based upon it. The findings set forth the subcontract and state that the value of the work done and materials furnished thereunder is the sum agreed upon therein. The error was therefore without injury to the appellants.
The order is affirmed.
Lawlor, J., and Sloss, J., concurred.
Hearing in Bank denied, and the following opinion rendered thereon on Junе 12, 1915:
THE COURT.—The defendants have filed a petition for rehearing in which they present arguments and points not mentioned in the briefs upon which the case was submitted. This cоurt has consistently declined to consider petitions for rehearing presenting new points. In Payne v. Treadwell (16 Cal. 247), it held that it was too late to urge a point for the first time in a petition for rehearing, after the case had been fully considered and decided by the court upon the points presented in the original briefs. In Kellogg v. Cochran (87 Cal. 200, 12 L. R. A. 104, [25 Pac. 677]), it said: “We havе decided—and with manifest propriety—that we will not grant a rehearing in order to consider points not made in the argument upon which the case was originаlly submitted.” In San Francisco v. Pacific Bank (89 Cal. 25, [26 Pac. 615, 835]), the court said: “The court will not consider a petition for rehearing that attempts to discuss the case on grounds not presented in the original argument, or discussed in its opinion.”
Upon these grounds it is clear that the petition must be denied. It is so ordered.
