127 Wash. 69 | Wash. | 1923

Holcomb, J.

This action was commenced in December, 1921, by respondents, to recover of the appellant compensation under the constitution, in the sum of $62,000, for the taking and damaging by appellant of respundents’ lands along the Humptulips river, caused by the operations of appellant in splashing the river, *70and in/ going- upon the lands in question for the purpose of driving saw logs down the river. The complaint alleges that some two hundred fifty acres of land had thus been washed away, and appellant has used and occupied the remaining lands for roads over which to move donkey engines, and for engine locations in “sacking” the river, so that respondents were deprived of any beneficial use thereof. Past, present and future damages to the lands bordering on the river, owned by respondents, were included, by reason of the continued operations of appellant.

A demurrer was interposed to the complaint upon the ground that the action was barred by the statute of limitations. The demurrer being overruled, appellant, without waiving its demurrer, filed its answer, in which it set up, as an affirmative defense, that the action was barred by lapse of time. Several affirmative defenses were alleged by appellant, and were put in issue by reply, except as to certain matters, and the cause went to trial before a jury, which awarded damages in favor of respondents in the sum of $4,500. The court instructed the jury that the action was not barred; that respondents could not recover any damages occasioned prior to November 11, 1919, when respondents withdrew the permission they had theretofore granted to appellant to use the river and certain rights thereon. The court also instructed the jury that no damages could be allowed for continuing damages for a period longer than six years after judgment should be rendered in the case, for the reason that appellant had stipulated in open court that, at the end of six years, it would cease its operations upon the river and on the lands in question.

Appellant unsuccessfully moved for judgment notwithstanding the verdict, which, being denied, judgment upon the verdict was entered.

*71No statement of facts has been brought up to this court, and the three errors claimed by appellant are all based upon the ground that the action is barred by the statute of limitations.

Appellant contends that the action is barred by subd. 3, § 159, Rem. Comp. Stat. [P. C. § 8166], which reads:

“An action upon a contract or liability, express or implied, which is not in writing, and does not arise out of any written instrument; . ” [must be brought within three years].

It is contended that this section of the statute was held to apply in Jacobs v. Seattle, 100 Wash. 524, 171 Pac. 662, L. R. A. 1918E 131, upon which appellant places its main reliance.

That case was one brought against the city of Seattle for compensation for the construction of a nuisance, where the city, although having the power of eminent domain, did not condemn the right to interfere with Jacobs’ rights. The court there held that subdivision 3, § 159, supra, applied; and an action to recover compensation for damages resulting from the operation of the incinerator by the city in the exercise of its power of eminent domain where, however, it had not condemned, is not an action involving real property, but is an action arising from implied contract of liability, the action being one not arising from the taking of real property, but merely from damaging it.

On the other hand, respondents contend that this action is governed by the ten-year statute of limitations, § 156, Rem. Comp. Stat., and is governed by the case of Aylmore v. Seattle, 100 Wash. 515, 171 Pac. 659, which case was followed approvingly in Domrese v. Roslyn, 101 Wash. 372, 172 Pac. 243, and Irwin v. J. K. Lumber Co., 119 Wash. 158, 205 Pac. 424.

In the Jacobs case, supra, there was a resulting damage to the land. The land itself was left wholly *72intact. Hence it was not an action involving real property. In the Aylmore case, supra, it was held that the property having been taken by the city without condemnation, was a case involving real property, and that the property owner was not barred from the right of action to recover the land which had been taken by the municipality for a public use, without compensation, until such time as he had lost his title by adverse possession, that is, ten years. Irwin v. J. K. Lumber Co., 119 Wash. 158, 205 Pac. 424.

In the case at bar, the damage was all done, according to the allegations of the complaint and reply, subsequent to 1912, and therefore within ten years prior to the commencement of this action. The damage alleged in the complaint in the case at bar consists in the actual taking of the lands by washing them away, and by use of the banks for roadways. The damage alleged, therefore, is not consequential as flowing merely from the erection of the dam and the impounding of the water.

We must presume that the evidence followed the issues tendered by the pleadings in the case, and so far as this case is concerned, not having the evidence before us, we can consider nothing else. Under the issues thus presented, it is clear that the case falls within the rule announced in Aylmore v. Seattle, supra, and the subsequent cases following it. The judgment is therefore affirmed.

Main, C. J., TolmaN, Parker, and Mackintosh, JJ., concur.
© 2024 Midpage AI does not provide legal advice. By using midpage, you consent to our Terms and Conditions.