Opinion by
The primary question for determination is whether the equitable doctrine of substantial performance under the terms of a building contract should be applied to the facts of the present case. The rigid rule as to strict performance may primarily be regarded as the law of Pennsylvania, but in many cases it has been relaxed in favor of the more equitable doctrine. While the cases in which substantial performance was held to apply may be said
There must in every case be substantial performance of the contract, and unless there be substantial compliance, there can be no recovery; but, whether there has been substantial performance, depends upon the character of the changes or alterations complained of, that is to say, do they materially affect the completed structure and were they in good faith honestly intended to fulfill the contract. Whether the party acted in good faith, and whether the departures were material are generally questions for the jury: Truesdale v. Watts,
The third assignment raises a different question. It is contended that the learned trial judge committed reversible error in refusing to affirm the eighth point of the defendant upon the question of damages for failure to complete the houses at the time specified in the contract, and in failing to give any instructions to the jury upon this question. We cannot agree that the point should have been affirmed as submitted, because it assumed as a fact, that appellant had neither expressly, nor impliedly, by his acts waived this provision of the contract, and that the contractor had no justification for the delay in completing the houses. The point amounted to binding instructions to make the deductions claimed without reference to whether the owner had made any objection to the delay, or by his conduct, had given the contractor grounds for believing that, the penalty for delay would not be enforced. It was held as late as Philadelphia v. Tripple,
Assignments of error overruled and judgment affirmed.
