235 Pa. 443 | Pa. | 1912
Opinion by
The primary question for determination is whether the equitable doctrine of substantial performance under the terms of a building contract should be applied to the facts of the present case. The rigid rule as to strict performance may primarily be regarded as the law of Pennsylvania, but in many cases it has been relaxed in favor of the more equitable doctrine. While the cases in which substantial performance was held to apply may be said
There must in every case be substantial performance of the contract, and unless there be substantial compliance, there can be no recovery; but, whether there has been substantial performance, depends upon the character of the changes or alterations complained of, that is to say, do they materially affect the completed structure and were they in good faith honestly intended to fulfill the contract. Whether the party acted in good faith, and whether the departures were material are generally questions for the jury: Truesdale v. Watts, 12 Pa. 73; Pallman v. Smith, 135 Pa. 188; Cosgrove v. Cummings, 190 Pa. 525. This is always true if the facts relating to the good faith of the plaintiff and the materiality of the changes or alterations are in dispute. On the other hand, if the undisputed testimony shows a substantial variance, not authorized by the owner, and made without his knowledge or assent, it is the duty of the court to so declare as a matter of law: Harris v. Sharples, 202 Pa. 243. In the present case the facts are disputed, and, in our opinion, the learned court below committed no error in submitting to the jury the questions upon which the rights of the parties depend. Under the evidence it was a fair question whether the appellant had authorized the contractor to lower the elevation of the houses so as to better suit the contour of the ground upon which they were located. We must assume that the jury found this fact in favor of the contractor, and if this change was authorized, or assented to, the changes in the cellar windows, followed as a necessary consequence. The explanation of the failure to provide certain joists of the size specified is consistent with an honest intention to faithfully perform the contract and the evidence shows that this defect was easily remedied. On all these questions the case was for the
The third assignment raises a different question. It is contended that the learned trial judge committed reversible error in refusing to affirm the eighth point of the defendant upon the question of damages for failure to complete the houses at the time specified in the contract, and in failing to give any instructions to the jury upon this question. We cannot agree that the point should have been affirmed as submitted, because it assumed as a fact, that appellant had neither expressly, nor impliedly, by his acts waived this provision of the contract, and that the contractor had no justification for the delay in completing the houses. The point amounted to binding instructions to make the deductions claimed without reference to whether the owner had made any objection to the delay, or by his conduct, had given the contractor grounds for believing that, the penalty for delay would not be enforced. It was held as late as Philadelphia v. Tripple, 230 Pa. 480, that where a building contract provides a time limit, but the contractor after the expiration of the time limit has been permitted to continue the work, and receives payment therefor, the owner will be deemed to have waived the nrovision as to the time limit. To the same effect is Coryell v. Dubois Borough, 226 Pa. 103. It would have been better practice to have submitted this question to the jury, under proper instructions by the court, but the trial judge in the case at bar was not bound to affirm a point which did not fully and correctly state the law under the facts. The evidence shows that six different payments were made on account from December 7, 1906, to February 1, 1908. All of these payments were made after the time limit had expired, and there is no evidence to show that appellant made any objection to the delay. Under these circum
Assignments of error overruled and judgment affirmed.