133 Wash. App. 503 | Wash. Ct. App. | 2006
¶1 In these consolidated cases, Preserve Our Islands (POI) and King County (County) appeal the Shorelines Hearings Board’s (Board) order requiring the County to issue shoreline substantial development and conditional use permits to Glacier Northwest (Glacier) for its proposed barge-loading facility on Maury Island. The facility will allow Glacier to transport large quantities of sand and gravel off island from its adjacent upland mine. Appellants contend the facility is not water dependent, as required by the King County Shoreline Master Program (Master Program), because the mining operation is the principal use of Glacier’s property and it has functioned without barging for many years. They also maintain the facility is inconsistent with shoreline management policies.
¶2 But the County has zoned Glacier’s site for commercial mining and designated it as mineral resource land under the Growth Management Act, chapter 36.70A RCW, without any restrictions on the size of the use. The current principal use of the site is a commercially significant mining operation, regardless of how it was used in the past. Glacier’s mine is located on a small island without viable large-scale ground transportation options and cannot operate consistent with its designated principal use without
FACTS
¶3 Northwest Aggregates Company, a.k.a. Glacier Northwest, owns a 235-acre sand and gravel mine on the southeast shore of Maury Island.
¶4 Since 1978, the mine has produced between 10,000 and 20,000 tons per year, shipped by truck to sites around Maury Island and adjacent Vashon Island. The barge-loading facility has not been used since 1978 and has fallen into disrepair. Glacier has removed the facility’s electrical components, but the owners, including Glacier, have always timely renewed their aquatic lands leases from the Washington State Department of Natural Resources.
¶5 In May 1998, Glacier applied to the County for a shoreline exemption to repair the barge-loading facility in
Permits and SEPA Review
¶6 On August 11, 1998, the County issued a State Environmental Policy Act (SEPA), chapter 43.21C RCW, determination of significance requiring Glacier to prepare an Environmental Impact Statement (EIS) for the proposal. On July 21, 1999, the County issued a draft EIS (DEIS).
¶7 In September 2002, Glacier submitted applications for substantial shoreline development and shoreline condi
|8 Due to the extensive modifications to Glacier’s proposal, the County required additional SEPA review to evaluate the project changes and consider additional information from Glacier and the community.
¶9 That same day, March 16, 2004, the Director of the Department of Development and Environmental Services (DDES) denied Glacier’s shoreline permit applications, apparently concluding for the first time since Glacier filed its 1998 application that the proposed barge-loading facility was not water dependent. DDES also ruled that the facility was inconsistent with certain policies of the Master Program and was not a legal nonconforming use. But, confus
¶10 Glacier appealed the denial to the Board. POI also appealed the resource use determination and adequacy of the FEIS and Addendum. The Board granted summary judgment for Glacier on the water dependency and resource use issues. After an eight-day hearing, the Board reversed DDES’s conclusion that the proposed facility was inconsistent with shoreline management policies. Although it concluded the facility was an authorized permitted use, it went on to reverse the director’s ruling that the facility failed to meet the criteria for a legal nonconforming use. The Board concluded the FEIS was adequate and a supplemental EIS was not required. It ultimately reversed DDES’s denial of shoreline development permits and remanded with orders to issue the permits with the Board’s conditions. POI and the County appealed to this court.
DISCUSSION
¶ 11 POI and the County argue the Board made several errors of law in reversing DDES’s determination that Glacier’s proposed barge-loading facility fails to satisfy the requirements for shoreline permits. Glacier maintains the Board correctly determined that the facility meets all permit requirements. POI argues separately that the FEIS and Addendum were inadequate and a supplemental EIS is required.
Shoreline Permits
¶12 The Shoreline Management Act of 1971 (SMA), chapter 90.58 RCW, requires each local government to develop a master program for the use of shorelines within its jurisdiction.
¶l3 The County adopted its Master Program in 1978 (King County Ordinance 3692 (May 1, 1978)). The Master Program consists of the King County Shoreline Policies (Shoreline Policies) and King County Shoreline Code, chapter 25.04 King County Code (KCC) (Shoreline Code). The Master Program limits shoreline use and specifies criteria for issuing development permits within County shorelines. As modified to comply with the FEIS, Glacier’s barge-loading facility requires both a shoreline substantial development permit and a shoreline conditional use permit.
I. Standard of Review and Deference
¶14 As an initial matter, the parties disagree on the standard of review and to which agency, if any, this court should defer.
¶15 POI argues that if any deference is due, it should be accorded to the County rather than the Board because the County wrote the Master Program,
II. Water Dependency
¶16 Under KCC 25.32.010, the County issues shoreline substantial development permits if the proposed develop
a principal use which is not intrinsically dependent on a location abutting the ordinary high water mark but which:
A. Promotes the public’s enjoyment of or access to the water; or
B. Gains a cost savings or revenue-differentiating advantage, which is not associated with land rents or costs, from being located within the shorelines of the state that could not be obtained at an upland location;
such uses include but are not limited to residential development, boat sales or restaurants.[33 ]
¶17 Appellants argue the Board erred by ruling the proposed development is water dependent. They contend the term “principal use” is unambiguous, and the mining operation is water related because the barge-loading facility merely provides an economic advantage to the mine, which has operated for most of its existence without barging. Glacier argues the term “water dependent” is ambiguous because “principal use” is not defined. It contends the barge-loading facility is an integral part of the principal use because the mine could not function commercially without it.
¶18 The Board ruled that the mining operation as a whole is the principal use, transportation of minerals is an
marine transportation of sand and gravel was necessary to provide a quantity of material similar to that which Glacier proposes to mine and export now and in the future. The fact that the site has been used to mine a lesser “local” annual quantity until demand resumes does not mean that the necessity for barge transportation has been lost or diminished. The “necessity of the land-water interface” at this facility is consistent not only with the prior use of the site as a source of sand and gravel in King County, but also serves to give purpose and effect to the site’s GMA mineral designations and to the KCSMP, which allows mining in the Conservancy Environment and acknowledges the marine location of sand and gravel as noted in King County’s master program policies.[34 ]
¶19 In reviewing an agency’s summary judgment ruling based on undisputed facts, we are governed by the APA standard of review. We may reverse the Board if it has erroneously interpreted or applied the relevant law.
A. Principal Use
¶20 The parties dispute whether the term “principal use” is ambiguous under the Master Program. Appellants argue that the term is unambiguous and does not include a barge-loading facility which is merely accessory to the mine itself, which is the principal use. But that argument is tautological because it presumes the answer the appellants
¶21 The Master Program does not define “principal use.” Thus, the definitions in Title 21A KCC (zoning), the SMA, and chapter 173-27 WAC (Department of Ecology’s Shoreline Regulations) could apply,
¶23 Both parties agree that the principal use is a mining operation. It is also largely undisputed that for the mine to operate at a commercially significant level, it requires barging. The issue then is whether the principal use is a commercially significant mining operation. To answer this question, we must consider the site’s land use designation and zoning under the GMA and comprehensive plan and how that meshes with the SMA and the Master Program.
B. Land Use Designation and Zoning
¶24 The GMA requires counties and cities to adopt a comprehensive plan and implement development regulations that are consistent with the plan.
¶25 In 1994, the County adopted its GMA comprehensive plan and designated Glacier’s Maury Island site as mineral resource lands. The plan’s “Resource Conservation Strategy” states that mineral resource lands of long-term commercial significance for the extraction of minerals are shown as designated mineral resource sites on the plan’s mineral resources map
¶26 The King County Zoning Code, Title 21A KCC (Zoning Code), implements the comprehensive plan’s policies and objectives. The County zoned Glacier’s site “M,” or “mineral.” Under KCC 21A.04.050, the purpose of the mineral zone “is to provide for continued extraction and processing of mineral and soil resources in an environmentally responsible manner.”
C. Relationship Between the GMA and the SMA
¶28 Appellants assert the upland site’s mineral use designation under the GMA, comprehensive plan, and Zoning Code does not dictate the principal use.
¶30 As the Board noted, the GMA includes a provision requiring that shoreline master programs and GMA comprehensive plans be harmonized:
(1) For shorelines of the state, the goals and policies of the shoreline management act as set forth in RCW 90.58.020 are added as one of the goals of this chapter as set forth in RCW 36.70A.020 without creating an order of priority among the fourteen goals. The goals and policies of a shoreline master program for a county or city approved under chapter 90.58 RCW shall be considered an element of the county or city’s comprehensive plan. All other portions of the shoreline master program for a county or city adopted under chapter 90.58 RCW, including use regulations, shall be considered a part of the county or city’s development regulations.
(2) The shoreline master program shall be adopted pursuant to the procedures of chapter 90.58 RCW rather than the goals, policies, and procedures set forth in this chapter for the adoption of a comprehensive plan or development regulations.
(3) The policies, goals, and provisions of chapter 90.58 RCW and applicable guidelines shall be the sole basis for determining compliance of a shoreline master program with this chapter*524 except as the shoreline master program is required to comply with the internal consistency provisions of RCW 36.70A.070, 36.70A.040(4), 35.63.125, and 35A.63.105.[56 ]
¶31 RCW 36.70A.480 specifically states that a county’s shoreline master program goals and policies are part of that county’s GMA comprehensive plan, and the County’s shoreline master program regulations are development regulations. Consistent with this provision, the GMA defines “[development regulations” as “the controls placed on development or land use activities by a county or city, including, but not limited to, zoning ordinances, critical areas ordinances, shoreline master programs, official controls, planned unit development ordinances, subdivision ordinances, and binding site plan ordinances together with any amendments thereto.”
¶32 While a specific development regulation may prevail over an inconsistent comprehensive plan pro
¶33 The barge-loading facility falls under the SMA and Master Program because it is located in a shoreline environment, and it must comply with their provisions. To this end, both the shoreline and GMA policies and regulations permit the County to impose conditions that will eliminate or diminish environmental impacts.
¶34 Because Glacier’s property is located on a small island without feasible large-scale ground transportation options, it cannot operate consistent with its principal use as a commercially significant mine without transporting materials by barge.
¶35 POI contends that the Board’s water dependency conclusion conflicts with its previous decision in Depart-
III. Commercial or Industrial Development
¶36 POI argues the Board erred by ruling on summary judgment that the barge-loading facility is a resource use rather than a commercial or industrial development. There are no disputed issues of fact, so if it is not an erroneous interpretation of the applicable law, we will uphold the Board’s interpretation.
¶37 The Shoreline Code prohibits commercial and industrial development in the conservancy environment,
¶38 The Board ruled, “[i]n order to construe the [Master Program] Regulations and Policies as a whole, it cannot be concluded that the County sought to prohibit sand and gravel mining in the conservancy designation as a ‘commercial’ or ‘industrial’ activity at the same time that it specifically stated that mining is not discouraged.”
¶39 Under KCC 25.32.050, the County may issue a shoreline conditional use permit only if: (1) the development is compatible with uses permitted in the master program environment in which the development is proposed, (2) the use will cause “no unreasonable adverse effects” on the shoreline or surrounding areas and uses, (3) the use will not interfere with public use of surface waters, and (4) the development of the site will not be contrary to the policies of the applicable master program. POI argues the facility fails to satisfy any of the four criteria. DDES ruled the facility is contrary to its Master Program policies for the conservancy environment.
¶40 Appellants do not object to any of the Board’s findings of fact;
¶41 POI argues the barge-loading facility is a highly intensive use of the shoreline that will directly conflict with ongoing recreational uses, including scuba diving and boating. It contends noise and aesthetic impacts also demonstrate incompatibility, and the Board’s restrictions on operating hours do not solve the problem. Preferred uses in the conservancy environment include those which are “nonconsumptive of the physical and biological resources of the area.”
¶42 The project area is used for many recreational activities, including motorboats, kayaks, scuba diving, canoes, beach walking, and watching wildlife. It is especially suited for scuba diving because of its underwater characteristics. The FEIS concluded that diving opportunities along the shoreline would be essentially eliminated during the facility’s operating hours, and the area’s attractiveness for recreational boaters would be reduced. It also concluded noise could be a problem but was not expected to significantly affect enjoyment of residential use or the quality of the environment. The Board relied in part on the FEIS for its findings and concluded the facility, as proposed, would interfere with permitted recreational and residential uses.
|43 But the Board also found that 90 percent of the recreational activity occurred on weekends
¶44 The Board ultimately concluded the facility would be compatible with permitted uses if it restricted Glacier’s hours of operation to 7:00 am to 7:00 pm, Monday through Friday. It included this condition in its order. While the Board’s restrictions cannot entirely alleviate the impact on other permitted uses, substantial evidence supports the Board’s conclusion that the restrictions make the facility compatible with permitted uses.
B. Unreasonable Adverse Effects
f45 POI argues the barge-loading facility will cause significant adverse impacts to near-shore critical habitat and the surrounding human population. It contends the facility will be imposed directly into the critical habitat and its noise and aesthetic impacts will impair nearby residents’ enjoyment of the area. Glacier contends substantial evidence supports the Board’s determination to the contrary that any adverse impacts on surrounding properties are not “unreasonable.” The Board agreed with DDES’s conclusion that “unreasonable adverse effects” in KCC 25.32.050(2) means essentially the same thing as “significant adverse environmental impacts” in SEPA.
¶47 The proposal approved by the Board requires greater distances between the new dock and sensitive eelgrass beds, specific tugboat approach and departure protocols, and a haulback system using winches and cables instead of tugboats to move the barges along the dock during loading. These are all measures designed to minimize impacts to eelgrass. The barge-loading facility intersects the mile-long shoreline in one location, the same place as the existing dilapidated facility, leaving the majority of the shoreline free from physical intrusion. It is located approximately in the middle of the shoreline, providing as much of a buffer as possible between it and adjacent residential communities. The portion of the conveyer system running over the beach and water will be enclosed to prevent spillage and reduce noise and dust. Further, as mentioned above, the dock itself will have less of a footprint, based on total square feet, open configuration, and number of pilings than did the original dock. Substantial evidence supports the Board’s conclusion that the barge-loading facility will not cause unreasonable adverse effects on the shoreline or surrounding areas and uses.
C. Interference with Public Use of Surface Waters
¶48 POI argues the barge-loading facility will interfere with normal public use of surface waters. The Board disagreed with DDES’s conclusion that the facility would not interfere with public use of surface waters, but it ruled that the condition it imposed limiting the hours of operation protects the recreational and aesthetic values that depend on public use of surface waters. As noted above, substantial
D. SMA and Master Program Policies
¶ 49 POI and the County argue the barge-loading facility is inconsistent with SMA and Master Program policies. DDES relies on the conservancy environment’s designation as the second-most restrictive shoreline designation and its earlier conclusion that the barge-loading facility would produce a level of activity to “rival even an intensive industrial use.”
¶50 The “Conservancy Environment” section of the Shoreline Policies states
The Conservancy Environment consists of. . . shoreline areas which are primarily free from intensive development. It is the most suitable designation for shoreline areas of high scenic or historical values, for areas unsuitable for development due to biophysical limitations and for commercial forest lands. Conservancy areas are intended to maintain their existing character. This designation is designed to protect, conserve, and manage existing natural resources and valuable historic and cultural areas. The preferred uses are those which are nonconsumptive of the physical and biological resources of the area.[89 ]
Developments should be “regulated so as to minimize the following: erosion or sedimentation, the adverse impact on aquatic habitats and substantial degradation of the exist
¶51 As we have already ruled, substantial evidence supports the Board’s conclusion that its conditions, combined with Glacier’s mitigation measures, minimize the adverse impact on aquatic habitat and prevent substantial degradation of the area’s existing character. Further, the shoreline area already includes the original, dilapidated barge-loading facility. Thus the aesthetic impact of the new facility is less than if the shoreline were pristine.
¶52 The “Mining” section of the Shoreline Policies states
The Puget Sound area is particularly rich in reserves of non-metallic minerals. Sand, gravel, clay, coal, cement, and stone are produced in quantity for the construction industry, and comprise over ninety-six percent of the total recorded mineral production value in the area.
Although the total amount of land that is presently occupied by mines or will be needed for future mineral industries is extremely small, the need for land for these industries is extremely critical.
Many of the most valuable deposits of sand and gravel are located on the marine shoreline and in or near beds of rivers. The conflicts between economic interest and environmental concern in these situations is obvious, but with good management of both the shoreline resource and the mineral resource those conflicts can be addressed and resolved without harm to either. These policies do not attempt to disallow utilization of*535 the mineral resource. Rather, their intent is to protect the shoreline resource.[92 ]
Other mining policies provide that mining should not be allowed in unique and fragile areas, mining industries should allow “natural shoreline systems to function with a minimum of disruption during their operations and should return the site to as near natural a state as possible upon their completion,” and mining in or under shoreline waters should be discouraged.
¶53 The County asserts the balance struck by the mining policies dictates against allowing Glacier’s barge-loading facility. DDES reached this conclusion in its permit decision, stating “special protections apply to over-water uses in the conservancy environment. Unless such activities are water dependent, they are not allowed. This is even the case where, as here, best management practices are implemented and appropriate mitigation measures are implemented.”
f54 POI contends Glacier’s proposed development is inconsistent with additional Shoreline Policies which give lowest priority to nonshoreline dependent uses and encourage such uses to locate away from the shoreline,
¶55 POI also asserts the proposed development is inconsistent with the SMA’s policies for uses within shorelines of statewide significance. The SMA states, “it is the policy of the state to provide for the management of the shorelines of the state by planning for and fostering all reasonable and appropriate uses.”
¶56 While both local and statewide shoreline policies are important to implementing the SMA, they are only policies and, as such, cannot specify what uses and mitigation measures may be appropriate at a given site. Glacier seeks to extract an important material from its designated resource land, a use recognized and encouraged by both the SMA and the GMA. The County has designated this property to permit extraction, and transportation of the material is essential to that operation. Because the barge-loading facility is a necessary part of Glacier’s island-located commercially significant mining operation, it depends on using a state shoreline. It is a reasonable and appropriate use of that shoreline because it enables Glacier to use its site consistent with the site’s designated use under the GMA, comprehensive plan, and Zoning Code. The operating hour conditions and mitigation measures will preserve to the greatest extent feasible the public’s opportunity to enjoy the shoreline’s natural character and its other resources and ecology. Further, the SMA’s use preferences are just that, preferences. Although the mining facility may not be at the top of the SMA’s “preferred use” list, it is a permitted use nonetheless because it is dependent upon the shoreline and designed to exist compatibly with other preferred uses. Substantial evidence supports
V. Final Environmental Impact Statement
¶57 POI argues the Board erred in concluding that the SEPA review was adequate. It contends the FEIS failed to adequately address noise impacts and impacts to marine mammals. The County and Glacier contend DDES exceeded its obligation to conduct a reasonably thorough investigation of the significant, probable environmental consequences of Glacier’s proposal.
¶58 The adequacy of an EIS is a question of law, which this court reviews de novo.
¶59 The adequacy of an EIS focuses on the legal sufficiency of the data in the EIS.
“[A]n EIS is not a compendium of every conceivable effect or alternative to a proposed project, but is simply an aid to the decision making process. That is, the EIS need include only information sufficiently beneficial to the decision making process to justify the cost of its inclusion. Impacts or alternatives which have insufficient causal relationship, likelihood, or reliability to influence decisionmakers are ‘remote’ or ‘speculative’ and may be excluded from an EIS.”[111 ]
A. Noise Impacts
¶60 POI argues the FEIS failed to address the impact of increased noise levels on surrounding communities, used an insufficient standard for acceptable noise levels, failed to analyze actual expected noise, and completely failed to analyze noise impacts on recreational users and fish and marine mammals. The FEIS relied in part on a noise analysis submitted by acoustic engineers which used the
¶61 Noise modeling was completed for each of the six different expected mining phases. The FEIS compared anticipated noise levels with County standards for noise from an industrial noise source migrating to a residential area: 57 dBA (decibels) maximum during daytime and 47 dBA maximum during nighttime.
¶62 The FEIS also addressed noise impacts from pile driving and barge loading on fish and marine mammals.
B. Impacts on Marine Mammals
¶63 POI argues the FEIS failed to evaluate the project’s significant impacts on marine mammals. It relies on testimony first introduced in the Board hearing, well after the FEIS was issued. POI did not present the testimony to DDES, so the FEIS could not have possibly addressed the alleged impacts POI raised at the Board hearing. Moreover, the FEIS did address project impacts on marine mammals. Besides recognizing that marine mammals were accustomed to shipping and port activity in the Puget Sound area, the FEIS noted that the project site is not located at major feeding grounds, congregation points, breeding areas, or migration routes. It determined the most likely effect was that harbor seals would avoid the area during barge loading. It also determined that although killer whales, or oreas, travel throughout Puget Sound, the project was unlikely to affect them because they were accustomed to this type of activity. It noted that although orea populations have been declining in Puget Sound, no one cites activities such as this in central Puget Sound as a
VI. Supplemental EIS
¶64 Finally, POI argues the Board erred by concluding that a supplemental EIS was not necessary. It contends the FEIS Addendum failed to adequately address concerns about potential propeller wash impacts because uncertainties about those impacts remain. The County and Glacier argue that given Glacier’s mitigation measures in response to eelgrass concerns, the post-FEIS changes in its proposal did not result in probable new significant adverse environmental impacts. We accord substantial weight to the County’s and the Board’s determination that a supplemental EIS is not required.
¶65 SEPA requires a supplemental EIS if there are substantial changes to a proposal which are themselves likely to have significant adverse environmental impacts, or when new information indicates a proposal’s “probable significant adverse environmental impacts” were not previously covered by “the range of alternatives and impacts analyzed in the existing environmental documents.”
¶66 The FEIS specifically identified propeller wash as a potential significant impact to eelgrass in the dock area.
¶67 Glacier and POI submitted voluminous, conflicting text and analysis about expected propeller wash velocities, distances, and effects on eelgrass. They offered conflicting expert technical modeling equations to simulate expected propeller wash velocities and impacts at Glacier’s site. DDES brought in a third party environmental consultant to evaluate the information and decide which model better replicated expected conditions. It adopted the consultant’s findings and conclusions, including that eelgrass impacts remained uncertain because neither party’s model could
¶68 Ultimately DDES relied on Glacier’s model, deemed the more accurate of the two by the consultant, in concluding a reasonably “safe” distance between the dock and eelgrass beds was 115 feet.
¶69 A supplemental EIS was not required.
¶70 We affirm.
Cox and Dwyer, JJ., concur.
Northwest Aggregates Company is owned by Glacier Northwest Holding, Inc., a wholly-owned subsidiary of Glacier Northwest, Inc. Both the County and Board refer to the company as “Glacier Northwest” or “Glacier.”
The aquatic lands lease was initiated in 1968 and renewed in 1978 and 1988. Glacier applied for lease renewal in 1999 and 2001.
Glacier also owns a sand and gravel mine in Steilacoom on which it has relied heavily in recent years. Glacier has held the Maury Island mine in reserve while it focused activity at the Steilacoom site, which is now depleted and ending operations.
Eight years ago when Glacier filed its application, this figure was premised on the mine being used to provide sand and gravel for the third runway expansion project at SeaTac International Airport. As the phase of that project for which Glacier’s product was to be used is essentially complete, it expects current mining levels to be lower.
The DEIS was the subject of extensive public comments, and over 1,600 people attended community meetings about the proposal and the DEIS.
1 FEIS at S-12.
On May 28, 2003, the County issued an initial addendum to the FEIS. Shortly thereafter, it withdrew the addendum because it did not include materials POI submitted after the deadline, raising concerns about noise and propeller wash impacts on eelgrass.
Under RCW 2.06.030, parties may appeal from a final quasi-judicial decision directly to this court if the appeal is certified by the superior court.
RCW 90.58.080; Weyerhaeuser Co. v. King County, 91 Wn.2d 721, 729, 592 P.2d 1108 (1979).
RCW 90.58.140(1). The “[m]aster program” is the “comprehensive use plan for a described area, and the use regulations together with maps, diagrams, charts, or other descriptive material and text, a statement of desired goals, and standards developed in accordance with the policies enunciated in RCW 90.58.020.” RCW 90.58.030(3)(b).
RCW 90.58.140(2)(b); Weyerhaeuser, 91 Wn.2d at 729.
RCW 90.58.170, .180.
KCC 25.32.010(B) (substantial development permit); KCC 25.32.050(A) (conditional-use permit).
See Ex. 8, King County Shoreline Environments Map (Vashon and Maury Islands); ch. 25.24 KCC.
As we explain in section V, infra, a different standard applies to an agency’s determination under SERA that an EIS is adequate. RCW 43.21C.090.
RCW 90.58.180(3).
RCW 34.05.558; Batchelder v. City of Seattle, 77 Wn. App. 154, 158, 890 P.2d 25 (citing Franklin County Sheriff’s Office v. Sellers, 97 Wn.2d 317, 323-24, 646 P.2d 113 (1982), cert. denied, 459 U.S. 1106 (1983)), review denied, 127 Wn.2d 1022 (1995).
Quadrant Corp. v. Cent. Puget Sound Growth Mgmt. Hearings Bd., 154 Wn.2d 224, 233, 110 P.3d 1132 (2005) (citing City of Redmond v. Cent. Puget Sound Growth Mgmt. Hearings Bd., 136 Wn.2d 38, 46, 959 P.2d 1091 (1998)).
Id. (quoting City of Redmond, 136 Wn.2d at 46).
RCW 34.05.570(3)(c), (d).
RCW 34.05.570(1)(a).
This court also defers to an agency’s interpretation of its own regulations. Port of Seattle v. Pollution Control Hearings Bd., 151 Wn.2d 568, 593, 90 P.3d 659 (2004) (citing Postema v. Pollution Control Hearings Bd., 142 Wn.2d 68, 77, 11 P.3d 726 (2000)).
RCW 90.58.050. The Department of Ecology “shall act primarily in a supportive and review capacity with an emphasis on providing assistance to local government and on insuring compliance with the policy and provisions of this chapter.” Id.
Weyerhaeuser, 91 Wn.2d at 736. See also Bellevue Farm Owners Ass’n v. Shorelines Hearings Bd., 100 Wn. App. 341, 351, 997 P.2d 380 (citing Buechel v. Dep’t of Ecology, 125 Wn.2d 196, 202, 204, 884 P.2d 910 (1994)), review denied, 142 Wn.2d 1014 (2000).
Buechel, 125 Wn.2d at 203 (citing Kitsap County v. Dep’t of Natural Res., 99 Wn.2d 386, 392, 662 P.2d 381 (1983)).
Id. (citing William H. Chapman, Substantive Decision-Making Under the Washington Shoreline Management Act, 9 U. Puget Sound L. Rev. 337, 377 (1986)).
RCW 36.70A.3201.
Quadrant, 154 Wn.2d at 245 (citing Richard L. Settle, Washington’s Growth Management Revolution Goes to Court, 23 Seattle U. L. Rev. 5, 34 (1999)).
Buechel, 125 Wn.2d at 203 (citing Weyerhaeuser, 91 Wn.2d at 736; English Bay Enters., Ltd. v. Island County, 89 Wn.2d 16, 21, 568 P.2d 783 (1977); Hayes v. Yount, 87 Wn.2d 280, 289, 552 P.2d 1038 (1976); 4 Washington Real Property Deskbook, § 84-58, at 84-45 (2d ed. 1986); Hama Hama Co. v. Shorelines Hearings Bd., 85 Wn.2d 441, 448-49, 536 P.2d 157 (1975); Chapman, supra, at 351-52).
Notably, the County does riot argue that its interpretations warrant deference.
KCC 25.24.030(A).
KCC 25.08.590.
KCC 25.08.600.
Preserve Our Islands v. King County, Shorelines Hr’gs Bd., SHB Nos. 04-009 & 04-010, at 29, Order Granting and Den. Mots, to Dismiss and for Partial Summ. J. (Wash. Aug. 10, 2004).
RCW 34.05.570(3)(d).
Quadrant, 154 Wn.2d at 238 (citing King County v. Cent. Puget Sound Growth Mgmt. Hearings Bd., 142 Wn.2d 543, 555, 14 P.3d 133 (2000)).
Id. at 239 (citing King County, 142 Wn.2d 555, 560).
State ex rel. Citizens Against Tolls v. Murphy, 151 Wn.2d 226, 242-43, 88 P.3d 375 (2004).
See KCC 25.08.010.
Spokane County Health Dist. v. Brockett, 120 Wn.2d 140, 154, 839 P.2d 324 (1992) (citing Johnson v. Morris, 87 Wn.2d 922, 926, 557 P.2d 1299 (1976); Fisher Flouring Mills Co. v. State, 35 Wn.2d 482, 490, 213 P.2d 938 (1950)).
KCC 21A.06.1345.
See Quadrant, 154 Wn.2d at 239 (citing Dahl-Smyth, Inc. v. City of Walla Walla, 148 Wn.2d 835, 842-43, 64 P.3d 15 (2003)).
Webster’s Third New International Dictionary 1802 (1961).
This definition is the functional equivalent of the definition of “principal use” in former KCC 21.04.685. Appellants do not dispute that this definition is appropriate, and the County even acknowledges it in its reply brief on appeal.
RCW 36.70A.040(3).
RCW 36.70A.170(1)(c).
Conservation in this context means “to assure that the natural resource lands will remain available to be used for commercial production of the resources designated.” WAC 365-195-825(1)(b).
Ex. 296; King County Comprehensive Plan 2000, at 3-25.
Ex. 8; 1 FEIS at 9-8.
Ex. 296; King County Comprehensive Plan 2000, at 3-25. Notably, the Plan posits that “Conflicts with surrounding land uses and environmental problems can arise even with the best of precautions. Resource-based industries need reasonable certainty that operations can continue if activities are performed in an environmentally sound manner.” Ex. 296; King County Comprehensive Plan 2000, at 3-26. To this end, the Plan states that conditions to mitigate significant adverse environmental impacts associated with mining operations should be required for, among other things, surface water quality, noise levels, vibration, land and shoreline uses, and visual impacts. Ex. 296; King County Comprehensive Plan 2000, at 3-39.
Ironically, the Master Program’s former definition of “principal use,” which appellants argue should be applied here, provides further support for the conclusion that a site’s principal use is based on its designated use, not its past use. Former KCC 21.04.510 defined “principal use” as “the primary or predominant use to which the property is or may be devoted.” (Emphasis added.) Appellants cite no authority for the proposition that zoning designations limit future uses to those employed in the past. In fact, zoning regulations are designed to do just the opposite — designate the use to which the owner may put its property now or in the future.
Appellants argue that this court should not give deference to the Board’s water dependency interpretation because it is based on an interpretation of the County’s GMA-related provisions, which are not within the Board’s area of expertise. See Quadrant, 154 Wn.2d at 233 (citing City of Redmond, 136 Wn.2d at 46). As we discuss below, the Board cannot make SMA decisions in a vacuum, ignoring GMA and its implementing regulations. But we need not decide the deference question here because it would have no impact on our holding.
Biggers v. City of Bainbridge Island, 124 Wn. App. 858, 103 P.3d 244 (2004), review granted, 156 Wn.2d 1005 (2006).
Id. at 867.
RCW 36.70A.040(4).
RCW 36.70A.480 (emphasis added). Similarly, the goals and policies of the GMA into which the shoreline goals are incorporated, are all created equal with no priority given to any one goal. “The following goals are not listed in order of priority . . . .” RCW 36.70A.020; Viking Props. v. Holm, 155 Wn.2d 112, 127, 118 P.3d 322 (2005); Whidbey Envtl. Action Network v. Island County, 122 Wn. App. 156, 173, 93 P.3d 885 (2004), review denied, 153 Wn.2d 1025 (2005).
RCW 36.70A.030(7) (emphasis added).
See KCC 25.04.025.
RCW 36.70A.040(4)(d). This is one of the “internal consistency provisions” imposed on shoreline plans and regulations by the GMA. RCW 36.70A.480(3). The Board has previously concluded that shoreline master program provisions should be construed to work in concert with the GMA. Yakama Indian Nation v. Cent. Pre-Mix Concrete Co., SHB No. 98-42, at 13, Shorelines Hr’gs Bd., Final Findings of Fact, Conclusions of Law, and Order (Wash. Jan. 28, 1999), 1999 WA ENV LEXIS 136.
See Citizens for Mount Vernon v. City of Mount Vernon, 133 Wn.2d 861, 873, 947 P.2d 1208 (1997).
Waste Mgmt. of Seattle, Inc. v. Utils. & Transp. Comm’n, 123 Wn.2d 621, 869 P.2d 1034 (1994).
Philippides v. Bernard, 151 Wn.2d 376, 385, 88 P.3d 939 (2004) (citing State v. Wright, 84 Wn.2d 645, 650, 529 P.2d 453 (1974)).
See, e.g., Ex. 296, King County Comprehensive Plan 2000, at 3-39. And of course SEPA remains available, as it was here, to examine environmental impacts as the basis for conditions on permitted uses. See RCW 43.21C.030.
POI contends barges are not necessary because trucks could transport mining materials off the island using the car ferries. This argument is not well-taken. As the Board noted, when the Glacier site operated at a commercially significant level at varying times between 1968 and 1978, it required transportation of material by barge. Further, Glacier stated it would require 300 30-ton trucks to transport approximately the same amount as one 10,000 ton barge. The potential environmental impacts of transporting sand and gravel in these quantities by truck would be extremely significant. POI disputes neither this figure nor that the primary market for the sand and gravel from Glacier’s mine is off-island.
Viewing the principal use as the integrated mining operation, including the shoreline-located barge loading facility and the upland-located mine, also comports with the rule that “the intended use of adjacent lands should be considered when taking any action under the SMA in order to achieve the coordinated development of the shorelines which is the object of the SMA.” Weyerhaeuser, 91 Wn.2d at 736 (citing Merkel v. Port of Brownsville, 8 Wn. App. 844, 509 P.2d 390 (1973)).
WAC 173-26-020(36).
SHB No. 115, Shorelines Hr’gs Bd., Final Findings of Fact, Conclusions of Law, and Order (Wash. July 2, 1976), 1976 WA ENV LEXIS 87 (1976).
RCW 34.05.570(3)(d).
See KCC 25.24.070 (prohibiting commercial development); KCC 25.24.120 (prohibiting industrial development).
Shoreline Policies at 27.
Shoreline Policies at 20.
Shoreline Policies at 30.
See Shoreline Policies at 27 (commercial development), 30 (mining), and 33 (ports and industries).
The Shoreline Code is intended to be consistent with and implement the Shoreline Policies. See KCC 25.04.010.
The Board made 76 findings of fact.
State v. Rankin, 151 Wn.2d 689, 709, 92 P.3d 202 (2004) (citing State v. Hill, 123 Wn.2d 641, 644, 870 P.2d 313 (1994)).
RCW 34.05.570(3)(d).
RCW 34.05.570(3)(e); Ferry County v. Concerned Friends of Ferry County, 155 Wn.2d 824, 833, 123 P.3d 102 (2005).
See Bellevue Farm Owners, 100 Wn. App. at 362-63 (citing Lund. v. Dep’t of Ecology, 93 Wn. App. 329, 333, 969 P.2d 1072 (1998)).
Ferry County, 155 Wn.2d at 833 (citing Honesty in Envtl. Analysis & Legislation (HEAL) v. Cent. Puget Sound Growth Mgmt. Hearings Bd., 96 Wn. App. 522, 526, 979 P.2d 864 (1999)).
Shoreline Policies at 20.
This contrasts with DDES’s conclusion that the facility would not interfere with the public’s use of surface waters.
Preserve Our Islands v. King County, Shorelines Hr’gs Bd., SHB Nos. 04-009 & 04-010, at 34, Findings of Fact, Conclusions of Law, and Order (Wash. Nov. 3, 2004) (Board’s Order), Finding of Fact 63. In its conclusions of law, the Board stated that evidence showed that most recreational activity occurs during the summer and on weekends. Board’s Order at 52, Conclusion of Law 20.
Glacier’s 2002 proposal listed the overall surface area of the new dock as 7,340 square feet, compared to the 8,490 square feet of the old dock. Since that time, Glacier has agreed to increase the distance the new dock extends from shore to mitigate impacts on eelgrass beds.
Webster’s defines “compatible” as “capable of existing together without discord or disharmony.” Webster’s Third New International Dictionary 463 (1961).
Board’s Pinal Order at 54, Conclusion of Law 24.
King County Report and Decision for Shoreline Conditional Use Permit, p. 15, ¶ 20 (Mar. 16, 2004).
Glacier had proposed prohibiting operations from 6 am Saturday until 8 pm Sunday. The Board ruled that this was inadequate to be fully compatible with the SMA and Master Plan policies. See Board’s Order at 59, Conclusion of Law 32.
Shoreline Policies at 20.
Shoreline Policies at 21.
POI points out that maintaining a shoreline’s existing character does not include maintaining existing nonnatural characteristics. Even if that were true, it does not change the fact that the aesthetic impact of Glacier’s proposed development is lessened because it improves upon a barge-loading facility which already exists in the same area.
Shoreline Policies at 30.
Shoreline Policies at 31.
DDES Director’s Report and Decision at 15, ¶ 20 (emphasis added). Because we reject this argument on other grounds, we do not need to decide whether only-water dependent resource extraction operations are permitted.
Shoreline Policies at 2, Shoreline Use Element, Objectives 4(e), 8.
Shoreline Policies at 5, Economic Development Element, Objective 7.
Shoreline Policies at 10, Recreation Element, Objective 1.
Shoreline Policies at 34, Ports and Industries, General Policy 7.
The mineral resource occurs naturally and must be taken from its natural location. The development cannot be moved because the resource cannot be extracted elsewhere. As the King County Master Program recognizes, these deposits are often found on or near the shorelines of the state. See Shoreline Policies at 30.
RCW 90.58.020.
RCW 90.58.020.
RCW 90.58.020(7).
RCW 90.58.020.
poi Qounty also argue the barge-loading facility is an illegal nonconforming use, but because it is water dependent, it is also conforming. KCC 25.08.310 defines nonconforming uses or developments as “those uses and structures that have been lawfully established or constructed prior to November 22, 1976, which no longer conform to the applicable regulations of the master program.” A nonconforming use is not necessarily an illegal use. Many nonconforming uses are permitted to remain. See City of Univ. Place v. McGuire, 144 Wn.2d 640, 648, 30 P.3d 453 (2001) (“Lawful nonconforming uses are allowed to continue for some period of time, though the local government may regulate or even terminate the nonconforming use, subject to constitutional limits”) (citing Rhod-A-Zalea & 35th, Inc. v. Snohomish County, 136 Wn.2d 1, 8, 959 P.2d 1024 (1998)). Water dependent uses are permitted in the conservancy environment. See KCC 25.24.030(A). When the County designated Maury Island’s shoreline a conservancy environment, the barge-loading facility remained a permitted use because it was, and is, a water dependent use.
As the Board noted, DDES’s nonconforming use analysis was based on its conclusion that because the principal use, the mine, did not require the barge-loading facility, the facility was not water dependent and was thus a nonconforming use. When the Board reversed the County and determined the facility is water dependent, it also ruled the facility is an authorized permitted use, not a nonconforming use. It addressed the nonconforming use issue “solely for the purpose of providing a complete decision on all issues raised in the appeal.” Board’s Order at 61. We need not consider whether the barge-loading facility is an illegal nonconforming use because the Board did not err in ruling that the facility, including Glacier’s mitigation measures and the Board’s required conditions, conforms to the applicable regulations and policies of the Master Program.
Klickitat County Citizens Against Imported Waste v. Klickitat County, 122 Wn.2d 619, 632-33, 860 P.2d 390, 866 P.2d 1256 (1993) (citing Solid Waste Alternative Proponents v. Okanogan County, 66 Wn. App. 439, 441, 832 P.2d 503, review denied, 120 Wn.2d 1012 (1992); Citizens for Clean Air v. City of Spokane, 114 Wn.2d 20, 34, 785 P.2d 447 (1990)).
RCW 43.21C.090; Klickitat County, 122 Wn.2d at 633 (citing RCW 43.21C.090; Citizens for Clean Air, 114 Wn.2d at 34).
Kettle Range Conservation Group v. Dep’t of Natural Res., 120 Wn. App. 434, 456, 85 P.3d 894 (2003) (quoting Anderson v. Pierce County, 86 Wn. App. 290, 302, 936 P.2d 432 (1997)), review denied, 152 Wn.2d 1026 (2004).
Klickitat County, 122 Wn.2d at 633 (citing Richard L. Settle, The Washington State Environmental Policy Act: A Legal and Policy Analysis §14(a)(i) (1987)).
Id. (quoting SEAPC v. Cammack II Orchards, 49 Wn. App. 609, 614, 744 P.2d 1101 (1987)).
Id. (quoting Cheney v. Mountlake Terrace, 87 Wn.2d 338, 344-45, 552 P.2d 184 (1976)).
Id. at 641 (alteration in original) (quoting Settle, supra, § 14(a)(i), at 157).
Average existing community noise levels ranged from 43 to 53 dBA (decibels) during the day and 37 to 46 dBA during the evening.
POI does not dispute the validity of the science behind the PEIS’s noise analysis.
See 1 FEIS at 7-7. POI contends that an industrial noise standard is incorrect considering the County classified the mining operation as a “resource use.” But the operation’s designation as a resource use has nothing to do with the nature of the sounds it emits. There are no noise standards for “resource uses” as such.
In discussing noise impacts on recreational uses, the FEIS states: “Noise and activity at the mine may detract from the recreational experiences currently available at the site and adjacent lands.” 1 FEIS at 12-3. This, like the noise analysis discussed above, is a reasonable prediction of the limited impact a slight increase in existing ambient noise levels will have.
See 1 FEIS at 6-28 through 6-32.
Citizens for Clean Air, 114 Wn.2d at 33-34.
WAC 197-11-600(3)(b)(ii).
FEIS add. at 12.
FEIS add. at 8. DDES properly considered Glacier’s mitigation measures in making its determination that a supplemental EIS was not required. WAC 197-ll-330(l)(c).
See 1 FEIS at 6-21, 6-47. The Addendum noted that since the FEIS had been issued, the distribution and density of eelgrass had been further surveyed and described in greater detail. The smallest of the three patches identified in the FEIS was no longer present.
1 FEIS at 6-21, 6-22.
1 FEIS at 6-22.
Mitigation measures included using a winch and cable system instead of tugs to position the barges along the dock, extending the dock farther into the water so that its face is never closer than 120 feet to the eelgrass beds, requiring tugs to follow a specific barge approach and departure protocol to direct propeller wash away from the eelgrass beds, and extensive monitoring during operations.
FEIS add. at 7.
FEIS add. at 7-8. DDES reached this number by extrapolating from Glacier’s model’s conclusion that propeller wash velocities at 100 feet from the dock were 10 centimeters per second greater than the velocity at which damage to eelgrass was known to occur.