188 Ind. 204 | Ind. | 1919
— Leona Prather and others filed their petition in the Sullivan Circuit Court for a drain and levee in Sullivan county, Indiana. Such proceedings were had as resulted in an order establishing the work and referring the same to Salathiel Boone, as commissioner for construction, who on March 18, 1911, let the contract for the construction of said work- to appellant Edwin E. Watts. The contract between Watts and the construction commissioner was in writing, and provided that the contractor should construct and complete the work by January 1, 1912, at and for the price of $23,-634.70. It also provided for a bond to be given by the contractor and for the payment of eighty per cent, of estimates to be made as the work progressed, and the remaining twenty per cent, on completion of the contract.
The contractor failed to complete the work by the
After the resignation of Boone as superintendent of construction, the court appointed William L. Sisson to that position. On January 30,1914, Sisson, as superintendent of construction, gave notice, as provided by statute, that on February 10, 1914, he would annul the contract of Edwin E. Watts theretofore existing for the construction of the improvement, and that he would let the contract for the completion of the work to the best bidder. On the day fixed the contract for the completion of the work was let to Salathiel Boone, and cn March 6, 1914, Salathiel Boone entered into a written contract and gave bond for the completion of said work.
Section 5 of the act, supra, under which the proceedings were instituted, provides for the letting of the contract, the construction of the work and the collection of assessments. This section provides that, in case any contractor shall fail or refuse to construct the part of'
Appellant filed a petition in the original proceeding asking that the court, under the provisions of this statute, allow him a fair price on his contract for the work performed by him up to the time when his contract was annulled. He alleged that prior to that time a large amount of the work had been done under his contract, and that he had been allowed and paid.only eighty per cent, of the estimated value of the work done, and that the remaining twenty per cent, of the value of the work so done, amounting to $3,504.03, was still due him and remained unpaid.
It is also alleged that on December 1, 1913, a further extension of time was granted for the completion of the work by William L. Sisson, and that the time so granted had not expired when Sisson, as superintendent of construction; attempted to annul his contract and to relet the same.
After hearing the evidence on. appellant’s petition, the court refused to allow him anything on his contract. Appellant Watts filed a motion for a new trial on the
The evidence of appellant shows that he claims a balance due him of $3,501.64 for'work done on the Prather levee between station 80 and station 209-10 at the Wabash river. It shows that the levee between those stations was brought up to grade except as to certain creek crossings and road crossings. He testified that there were eleven creek crossings, of which he constructed nine, and that he constructed two of the road crossings. He further testified that the work was measured and the number of cubic yards estimated, and that he was allowed and received eighty per cent, of the estimated value of the work amounting to $12,929.11, leaving twenty per cent, of the estimated value of the work performed by him still due. Mr. Sisson, the last superintendent of construction, who was also the county surveyor, corroborated the appellant to the extent of saying that the levee between station 80 and station 209-10 was practically brought up to grade by appellant, except as to the creek crossings, and that after deducting 4,000 cubic yards for those crossings the amount of earth claimed by appellant was actually put into the levee; but this witness testifies that, after the levee between those stations was brought up to grade, it was washed away by the flood of 1918, and that at the time he relet the contract to Boone an estimate made by him showed that it would require 24,600 cubic yards of earth to bring the work up to grade between the stations mentioned. There is other evidence showing the extent of damage done to the work between those stations by the flood,— one witness testifying .that the levee was almost entirely washed away in places, and that in other places \
The finding of the court is fully sustained by the evidence and is in accordance with the law.
Any seeming exception to the rule thus stated will be found to rest on the construction placed on the contract with reference to the subject-matter or on account of che conditions of the parties rather than on a denial of the principle stated. To illustrate, if A contracts with B to build a house according to certain plans and specifications, furnishing all labor and material, the fact that it may be destroyed by an act of God or inevitable casualty when almost completed will not excuse A from the obligation to furnish labor and material and to rebuild it; but, if A contracts to furnish and install an elevator in a building owned by B already in existence, the destruction of the building in which the elevator was to be installed will excuse performance. Siegel v. Eaton, etc., Co. (1897), 165 Ill. 550, 46 N. E. 449. The
The trial court did not err in overruling appellant’s motion for. a new trial.
. Judgment affirmed.
Note. — Reported in 122 N. E. 721. Contracts: excuses for nonperformance, validity, 18 Am. Dec. 452. See under (2) 13 C. J. 639.