PPM FINANCE, INCORPORATED, in its capacity as agent for Jackson National Life Insurance Company, Plaintiff-Counter-Defendant-Appellee,
v.
NORANDAL USA, INCORPORATED, Defendant-Counter-Plaintiff-Appellant,
v.
PPM America Special Investments CBO II, L.P. and PPM America Special Investments Fund, L.P., Counter-Defendants-Appellees.
No. 04-1401.
United States Court of Appeals, Seventh Circuit.
ARGUED September 15, 2004.
DECIDED December 16, 2004.
COPYRIGHT MATERIAL OMITTED Forrest B. Lammiman (argued), Lоrd Bissell & Brook, Chicago, IL, for Plaintiff-Appellee.
Dennis E. Quaid (argued), Fagel & Haber, Forrest B. Lammiman, Lord Bissell & Brook, Chicago, IL, for Defendants-Appellees.
Before EVANS, WILLIAMS, and SYKES, Circuit Judges.
TERENCE T. EVANS, Circuit Judge.
In this commercial dispute, one creditor, Jackson National Life Insurance Company, sued another, Norandal USA, Incorporated, demanding that Norandal fork over a substantial sum of money it obtained from a common debtor, who we will simply call Scottsboro. The district court аgreed with Jackson and granted its motion for summary judgment to the tune of $4.4 million, including prejudgment interest. Aggrieved by this decision, Norandal appeals.
Norandal is a processor of aluminum products. In February of 1999, it agreed to sell its Alabama processing plant to Scottsboro for apprоximately $92 million. To fund the acquisition, Scottsboro secured $69 million from Jackson, plus additional credit extensions. It got another $7.5 million loan from PPM America Special Investments CBO II, L.P. and PPM America Special Investments Fund, L.P. (collectively PPM). To cover the remainder, Scottsboro executed а promissory note to Norandal for $7.8 million. Thus, Jackson, PPM, and Norandal all became Scottsboro creditors.
To determine their relative rights, these creditors and Scottsboro entered into a subordination agreement giving Jackson a senior security interest in Scottsboro's assets. Under the agreement, Norandal was required to turn over to Jackson any payments it received from Scottsboro while Scottsboro was in default to Jackson. During negotiations, Norandal requested a provision that would require Jackson to notify Norandal of any defaults by Scottsboro. Jackson refused.
From October of 1999 through January of 2001, Scottsboro defaulted on several obligations to Jackson. Despite these defaults, Jackson continued to loan Scottsboro money, which Scottsboro in turn used to make 15 scheduled payments to Norandal. Jackson did not notify Norandal of Scottsboro's defaults until July of 2001. Only days later, Jackson and PPM filed involuntary petitions for relief in bankruptcy against Scottsboro.
In November of 2002, Jackson filed this suit against Norandal to recover the money Norandal received from Scottsboro. Jackson's complaint alleged thаt Norandal breached the subordination agreement by not turning over the payments it received from Scottsboro at a time when Scottsboro was in default to Jackson. In response, Norandal filed three counterclaims, including one seeking a declaratory judgment that Jackson had no right to recover because it had failed to give prompt notice that Scottsboro had defaulted. We review the district court's entry of summary judgment to Jackson de novo, Fix v. Quantum Indus. Partners LDC,
This case presents rather straightforward questions of contract interpretation. Under Illinois law, courts must ascertain parties' intentions exclusively from an agreement's language if it is clear and unambiguous. Kaplan v. Shure Bros., Inc.,
Under the subordination agreement, Norandal could not accept or retain payments from Scottsboro if Scottsboro was in default to Jackson:
2.3. Restriction on Payments. Notwithstanding any provision of any Subordinated Debt Document to the contrary, no Obligor [Scottsboro] may make, and no Subordinated Creditor [Norandal] may receive, accept or retain any payment of principal, interest or any other amount with respect to the Subordinated Debt until the Senior Debt is paid in full ... except that (I) [Scottsboro] may make аnd [Norandal] may receive scheduled payments of principal and interest ... under the Subordinated Note on an unaccelerated basis so long as no Senior Default shall have occurred and be continuing or would result therefrom....
The agreement further provides that Norandal must turn оver to Jackson any funds it received in violation of section 2.3:
2.5. Incorrect Payments. If any payment or distribution on account of the Subordinated Debt not permitted to be made by any Obligor [Scottsboro] or received by any Subordinated Creditor [Norandal] under this Agreement is received by [Norandal] before all Sеnior Debt is paid in full in cash, such payment or distribution shall not be commingled with any asset of [Norandal], shall be held in trust by [Norandal] for the benefit of [Jackson] and shall be paid over to [Jackson], or [its] representatives, for application on a pro rata basis... to the payment of thе Senior Debt then remaining unpaid, until all of the Senior Debt is paid in full in cash.
The district court concluded that this language is clear and unambiguous and requires Norandal to disgorge the money it received from Scottsboro. A contract provision is ambiguous only if it is subject to more than one reasonable interpretation. Commonwealth Ins. Co. v. Stone Container Corp.,
Norandal argues that the subordination agreement is ambiguous. Specifically, it claims that the payments made by Scottsboro to Norandal must have been permitted under section 2.3 because Jackson actually facilitated these payments by loaning Scottsboro more money. In support, Norandal cites the testimony of John Krupinski, Scоttsboro's former CFO, who testified that Jackson knowingly permitted Scottsboro to make payments to Norandal despite it being in default to Jackson. But Jackson's post-default loans had no bearing on the parties' rights and obligations under section 2.3. Indeed, section 3 of the agreement exрressly allowed Jackson to increase the amount of Scottsboro's senior debt without affecting Norandal's obligations under the agreement.
Norandal's primary argument is that Jackson was required to notify it that Scottsboro was in default and that Jackson's failure to do so bars it from recovering the money paid to Norandal. As the district court aptly noted, however, nothing in the subordination agreement required Jackson to notify Norandal of Scottsboro's default. Indeed, Norandal admits that it asked for a notice provision during contract negotiations, a request that Jackson rebuffed.
Faced with this situation, Norandal advances three arguments, which we reject. First, it argues that the agreement's silence regarding notice is a "gap," and that a notice requirement should be read into it. We initially note that Norandal forfeited this argument because it failed to mаke it before the district court. E.g., Ocean Atl. Dev. Corp. v. Aurora Christian Schs., Inc.,
Norandal also argues that notice is required because "senior default notice" is included in the subordination agreement's definition section. But this definition provision did not give Norandal the right tо be notified because "senior default notice" did not appear anywhere else in the agreement. In contrast, the phrase "subordinated default notice" is defined in the agreement but also appears in section 6, which requires Norandal to notify Jackson if Scottsboro defaults. Despite Norandal's аrguments to the contrary, there simply is no provision in the agreement imposing a reciprocal obligation.
Norandal's final argument on this point is that the district court erred by failing to consider extrinsic evidence showing that Jackson was required to provide notice under the subordination аgreement. But courts look to extrinsic evidence to determine the parties' intentions only if an agreement is ambiguous, e.g., Air Safety,
Norandal's next attack is factual. It contends that the district court erred by concluding that there is no genuine issue of material fact as to whether Scottsboro defaulted. Krupinski, aided by financial statements, testified that Scottsboro failed tо maintain the minimum debt service coverage ratio, interest coverage ratio, and tangible net worth ratio; made unauthorized capital expenditures; failed to disclose certain inventory; and experienced a labor strike. All of these events violated the subordination agreement. In response to this evidence, Norandal advances only the testimony of Jeff Podwika, a PPM loan officer who testified that prior to December of 2000 he was "comfortable with the situation" as to Scottsboro. He also testified generally that when one of his accounts is in default, he typically sends some form of communication informing the borrower that it has defaulted. But this testimony was not specific enough to refute the evidence supplied by Jackson. Notably, Podwika did not specifically refute the testimony and financial statements offered by Jacksоn establishing that Scottsboro was in default nor did he say at any point that Scottsboro was not in default. Norandal failed to offer specific, concrete evidence suggesting that Scottsboro was not in default, which is fatal to its assertion that the case must be resolved by a jury. Salvadori v. Franklin Sch. Dist.,
Norandal also argues that the district court erred in crediting Krupinski's testimony because he lacked personal knowledge about whether Scottsboro defaulted. But that is simply untrue. Krupinski directly partiсipated in calculating the financial statements which demonstrated that Scottsboro was in default. Moreover, Norandal does not identify which portions of Krupinski's testimony fell outside of his personal knowledge. And in any event, as Jackson correctly points out, Krupinski was designated as a witness under Fed.R.Civ.P. 30(b)(6), which authorized him to testify not only to matters within his personal knowledge but also to "matters known or reasonably available to the organization." See Pugh v. City of Attica, Ind.,
Next, Norandаl claims that Jackson waived its right to recover by facilitating Scottsboro's payments to Norandal. In Illinois, "waiver" is a voluntary and intentional relinquishment of a known right. E.g., Chatham Corp. v. Dann Ins.,
Finally, Norandal objects to the district court's award of prejudgment interest, a decision we review for an abuse of discretion. E.g., Ameritech Info. Sys., Inc. v. Bar Code Resources,
All of these requirements were met here. Norandal claims that the district court abused its discretion because the subordination agreement did not specify a due date when payments must be turned over. But under the plain terms of the agreement, money became due once Norandal failed to remit the payments it received from Scottsboro while Scottsboro was in default to Jackson. Thus, the time of default is clear — the contract contains an inherent due date. See Reserve Ins. Co. v. Gen. Ins. Co. of Am.,
For these reasons, the judgment of the district court is AFFIRMED.