Power v. Utilities & Transp. Comm'nPower v. Utilities & Transp. Comm'n
This case is a challenge to a Washington Utilities and Transportation Commission decision to grant the Washington Water Power Company (WWP) a rate increase of $20,174,000 for its electric operations. Three organizations representing low income and senior citizen ratepayers residing in WWP‘s service area, together with a low income, senior citizen ratepayer (appellants), contend that the Commission erred by including construction work in progress (CWIP) in WWP‘s rate base. The trial court upheld the Commission‘s decision. We reverse on the ground that
On March 6, 1981, WWP filed tariff revisions designed to effect a rate increase of $21,115,000 for its electric operations.
In its presentation before the Commission, WWP argued that $48,427,000 of CWIP should be included in its rate base. This figure represented 50 percent of WWP‘s projected 1981 investment in Colstrip Units 3 and 4, coal-fired generating plants under construction near Colstrip, Montana, and in Washington Public Power Supply System (WPPSS) No. 3, a nuclear plant under construction in Grays Harbor County, Washington. Generally, “rate base” represents the total investment in, or fair value of, the facilities of a utility employed in providing its service. The rate base is multiplied by a percentage, called “rate of return,” to arrive at the revenue which the utility may earn. 1 A. Priest, Principles of Public Utility Regulation 139 (1969). Thus, inclusion of CWIP in rate base permits a utility to earn a current cash return upon capital invested in new facilities, even though the facilities are not yet producing energy for the consumer.
The Commission, however, adopted its staff‘s recommendation that only $15,627,000 of CWIP, representing 100 percent of WWP‘s investment in Colstrip Units 3 and 4 during 1980, be included in WWP‘s rate base. WWP was permitted to accrue an allowance for funds used during construction (AFUDC)1 on the remaining CWIP excluded
CWIP was included in WWP‘s rate base in yet another respect. To determine WWP‘s new rates, the Commission had adopted the calendar year 1980 as the “test period” during which WWP‘s rate base, revenues, and expenses would be evaluated. However, increased expenses and inflation can erode a rate of return established on the basis of a historic test year. The Commission‘s expert witness analyzed probable changes in rate base, revenue, and expenses from December 31, 1980 to November 30, 1982, and recommended an “attrition allowance” (i.e., additional rate increase) of $13,361,000. Of this amount, $10,829,000 was directly attributable to $59,722,000 of CWIP expected to be incurred on the Colstrip Units from December 31, 1980 to November 30, 1982.
The Commission adopted the recommended attrition allowance, stating that such action was necessary “in order to preserve and maintain the company‘s financial integrity and allow it to generate sufficient cash flow consistent with its needs for construction projects, and to attract investors at a reasonable cost“.
In the hearings before the Commission, appellants insisted that any inclusion of CWIP in WWP‘s rate base was prohibited by
We have determined that the propriety of including CWIP in rate base is a matter that lies within the discretion of the Commission and is to be determined on a case-by-case basis. In effect POWER argues that
RCW 80.04.250 forecloses the Commission from including any property of a regulated utility in rate base for ratemakingpurposes until that property either is capable of or actively rendering service to the customers of the utility. We are of the opinion that counsel‘s argument is not a valid interpretation of the statute and is without merit. See State ex rel. Pacific Telephone & Telegraph Company vs. Department of Public Service, 19 Wn.2d 200, 142 P.2d 498 (1943) wherein the court held that property held by a regulated utility for future use could properly be included in the company‘s rate base for ratemaking purposes.
On November 25, 1981, the Commission issued its decision allowing WWP a rate increase of $20,174,000 for electric operations. Appellants filed a petition for judicial review of the Commission‘s decision in the Superior Court for Thurston County, naming WWP and the Commission as respondents. The trial court entered a decree upholding the Commission. We accepted direct review.
Valuation of public service property. The commission shall have power upon complaint or upon its own motion to ascertain and determine the fair value for rate making purposes of the property of any public service company used and useful for service in this state and shall exercise such power whenever it shall deem such valuation or determination necessary or proper under any of the provisions of this title.
(Italics ours.)
The issue which appellants pose is this: is CWIP “used and useful” for service within the meaning of
[1, 2] The primary objective of statutory construction is to carry out the intent of the Legislature. The intent of the Legislature must be determined primarily from the language of the statute itself. Department of Transp. v. State Employees’ Ins. Bd., 97 Wn.2d 454, 458, 645 P.2d 1076 (1982). Where the language of a statute is plain, free from ambiguity, and devoid of uncertainty, there is no room for construction because the meaning will be discovered from
Relying on these principles, we turn to the statutory language at issue here. “Used” is defined as “employed in accomplishing something“; “useful” is defined as “capable of being put to use: having utility: advantageous: producing or having the power to produce good: serviceable for a beneficial end or object“. Webster‘s Third New International Dictionary 2524 (1976). Thus,
Our interpretation of
From the broader perspective, however, I believe it to be very important, whenever the commission has a question before it, for the commission to have the necessary discretion to adapt and accommodate the delicate balance between utility interests and consumer interests. I also believe that all the key elements sought by proponents of the bill are within the present discretion of the commission. I have been in contact with the commission, and am certain that the commission will consider those specific elements on the appropriate occasions.
[3] The Governor‘s veto message does not persuade us. Although the message claims that inclusion of CWIP in rate base is already within the Commission‘s discretion, the source of this alleged discretion is not identified or otherwise explained. We are more impressed by the fact that the Legislature thought it necessary to amend
Our interpretation of
The commission has not previously allowed the cost of uncompleted construction projects to be included in a company‘s rate bases since rate base has normally consisted of the total of plant facilities actually used to provide the service customers pay for ... We have heretofore held that customers should not pay, through rates, for plant not providing service to them ...
However, upon submission of the company‘s direct case, the staff of the commission determined that it has now become necessary in limited cases to transfer some of the burden of current plant financing to the present ratepayers rather than postponing the entire burden to the future until after the plant is actually in service ...
Notably absent from this opinion is any discussion of
WWP asserts that our reading of the plain language of
Next, WWP relies heavily on State ex rel. Pac. Tel. & Tel. Co. v. Department of Pub. Serv., 19 Wn.2d 200, 142 P.2d 498 (1943). In Pacific Telephone, the Department of Public Service (the Commission‘s predecessor) appealed from a trial court order which directed it to include in the rate base of the Pacific Telephone and Telegraph Company three undeveloped parcels of real estate and an underground conduit which had been installed for future use. The Department argued that the parcels and conduit were not “used and useful” for service within the meaning of a predecessor statute virtually identical to
Curiously, the Pacific Telephone court failed to analyze the plain language of the predecessor statute. Instead, it followed Denver Union Stock Yard Co. v. United States, 57 F.2d 735, 746-49 (D. Colo. 1932). Denver Union held that undeveloped tracts of real estate were improperly
Pacific Telephone is not on point. The issue in that case was whether undeveloped land was a completed conduit — property held for future use — should be included in rate base. Pacific Telephone did not decide the issue we now confront, that is, whether an uncompleted utility plant may be included in rate base while it is still under construction. Thus, it is not controlling here.
Nevertheless, WWP contends that a literal reading of
In any event, Pacific Telephone does not seem to truly reflect the position of either WWP or the Commission with respect to inclusion of CWIP in rate base. WWP does not
Reviewing
Whether inclusion of CWIP in rate base is an appropriate or even necessary response to the financial problems created by large construction programs is not a question which we have the power to decide. Such policy determinations must be made by the Legislature. Our role is necessarily limited to determining whether
Appellants contend that the Commission‘s findings of fact in support of including CWIP in rate base were legally insufficient. Since
Reversed and remanded to the Commission for proceedings
WILLIAMS, C.J., ROSELLINI, UTTER, DORE, DIMMICK, and PEARSON, JJ., and BEVER and CUNNINGHAM, JJ. Pro Tem., concur.
Notes
The department of public works shall have power upon complaint or upon its own motion to ascertain and determine the fair value for rate making purposes of the property of any public service company used and useful for service in this state and shall exercise such power whenever it shall deem such valuation or determination necessary or proper under any of the provisions of this act.