In this regulatory action, Power Resource Group (“PRG”) challenges Texas’s implementation of the Public Utility Regu *233 latory Policies Act of 1978 (“PURPA”). After purchase negotiations between PRG and Texas New Mexico Power Company (“TNMP”) failed, PRG sought to compel TNMP to purchase power pursuant to a legally enforceable obligation (“LEO”) from its still-unbuilt plant. The Public Utility Commission of Texas (“PUC”) determined that because its rules implementing PURPA provide for a legally enforceable obligation only if a facility is within ninety days of delivering power, TNMP had no obligation to purchase power from PRG. PRG sought relief in Texas courts, which denied its request to overturn the PUC’s decision. PRG then brought suit in federal district court, which held that it had jurisdiction only to determine whether the PUC had fully implemented PURPA, and dismissed PRG’s remaining claims. Finding that the PUC did, in fact, fully implement PURPA, including providing for the option of a LEO, the district court granted summary judgment in favor of the PUC and TNMP. PRG now appeals. For the reasons that follow, we affirm the judgment of the district court.
I. FACTS AND PROCEEDINGS
This case concerns Texas’s interpretation and implementation of a federal statutory and regulatory scheme governing the contracting for the purchase of energy between public utilities and certain energy production facilities. The facts are not in dispute. Congress enacted PURPA to reduce the dependence of electric utilities on foreign oil and natural gas, in part by encouraging development of alternative energy sources such as cogeneration and small power production facilities (“qualifying facilities” or “QFs”).
Brazos Elec. Power Coop. Inc. v. FERC,
PRG is a Delaware corporation and an experienced developer of independent power projects. TNMP is a Texas electric utility under the authority of the PUC. Prior to 1995, TNMP contracted with Texas Utilities Electric Company to purchase power. In 1995, TNMP issued a request for proposal for energy to fill its anticipated need for 1999 or 2000. PRG responded to the request, proposing construction of a QF, a natural gas-fired generation facility, to be located in Lewisville, Texas — the Lewisville Power Project. In March of 1996, PRG and TNMP entered into negotiations for the Lewisville Power Project to provide power to TNMP. The Lewisville Power Project was certified as a QF on September 20, 1996 pursuant to 18 C.F.R. § 292.207(a)(1). PRG secured sources of equity, identified a site, held zoning discussions, and undertook various other steps in furtherance of the Lewisville Power Pro *234 ject. On February 13, 1998, PRG made a final written commitment which, it argues, gave rise to a LEO. TNMP then denied the existence of a LEO and refused to execute an agreement with PRG. TNMP instead renegotiated with its previous provider at a rate higher than that offered by PRG.
On August 7, 1998, PRG petitioned the PUC to order TNMP to purchase power from PRG’s Lewisville Power Project. On March 25, 1999, the PUC dismissed PRG’s petition without prejudice, interpreting the applicable rule, PUC Subst. R. 25.242(f)(1)(B), such that utilities were required to purchase from a QF pursuant to a LEO only if the QF could deliver power within 90 days of notifying the utility that energy would be available. The PUC determined that under Texas law, because PRG’s QF was not yet completed and therefore incapable of producing power for delivery within 90 days, a LEO was not created when PRG offered to supply energy to TNMP.
PRG then sought judicial review of the PUC’s order in state court in Travis County, Texas. The Travis County District Court affirmed the PUC’s final order on March 8, 2001. PRG appealed the ruling to the Third Court of Appeals in Austin. On January 10, 2002, that court affirmed the Texas trial court and the PUC, holding that “the [PUCj’s interpretation of [Rule 25.242(f)(1)(B)] is reasonable and not preempted by federal law and that the [PUC] did not act arbitrarily or capriciously in refusing to compel TNMP to contract with [PRG].”
Power Res. Group, Inc. v. Pub. Util. Comm’n of Tex.,
PRG then petitioned FERC pursuant to 16 U.S.C. § 824a~3(h)(2)(B), requesting that FERC undertake an enforcement action against the PUC for its failure to implement PURPA’s regulatory scheme. After FERC had not acted on PRG’s petition for 60 days, PRG filed a complaint in the United States District Court for the Western District of Texas, as authorized under 16 U.S.C. § 824a-3(h)(2)(B) (providing that a United States District Court may “require such State regulatory authority ... to comply with such requirements [of section 824a-3(f)], and such court may issue such injunctive or other relief as may be appropriate”).
The PUC and TNMP, as an intervenor, moved to dismiss PRG’s action, arguing that (1) the Rooker-Feldman doctrine barred district court review of PRG’s claim because proper review of the federal question was available via a petition for certio-rari to the United States Supreme Court; (2) because the Texas state courts had decided the issues presented, res judicata and/or collateral estoppel barred the same claims in federal court; (3) PRG had no standing under § 824a~3(h)(2)(B) because it is not a QF; and (4) sovereign immunity barred pursuit of the claim in federal court. PRG responded that Rooker-Feld-man, res judicata, and collateral estoppel did not apply because federal courts have exclusive jurisdiction over claims under PURPA. It also argued that it was a certified QF and, therefore, had standing, and that the prospective relief it requested was not barred by sovereign immunity.
On February 18, 2004, the district court ruled on the motion to dismiss, denying the motion as to PRG’s implementation claim. The district court analyzed the effect of PURPA’s unique “multi-layered” enforcement provisions on the defendants’ Rooker-Feldman and preclusion arguments. As the district court explained, “[t]he type of claim brought by the petitioner will determine whether state court,
*235
FERC or federal district court is the appropriate forum under the statute.”
See
16 U.S.C. § 824a-3(g)-(h). Subsection (g) of § 824a-3 mandates that state courts will review the state rules promulgated to implement PURPA and its associated FERC regulations.
See
16 U.S.C. § 824a-3(g)(1) — (2);
see also Windway Techs. v. Midland Power Coop.,
The district court then elucidated the distinction between two types of enforcement claims under PURPA, “as applied” claims and implementation claims: “ ‘An implementation claim involves a contention that the state agency ... has failed to implement a lawful implementation plan under § 824a-3(f) of the PURPA, whereas an “as-applied” claim involves a contention that the state agency’s ... implementation plan is unlawful, as it applies to or affects an individual petitioner.’ ”
Power Res. Group, Inc. v. Klein,
No. A-03-CA-762-H, slip op. at 12 (W.D.Tex. Feb. 18, 2004) (quoting
Windway Techs.,
at *5,
Federal jurisdiction over implementation claims, the district court held, is exclusive.
Id.
at *4,
The district court then construed PRG’s other claims requesting injunctive relief against the PUC as “as applied” claims and held that they had been determined by the Texas state courts. It concluded that the only issue properly before it was whether the PUC failed to implement PURPA. The court further held that PRG did have standing under § 824a-3(h)(2)(B) because it was a QF, and that the PUC’s motion to dismiss on the ground of sovereign immunity was without merit.
On July 15, 2004, the district court issued a memorandum opinion and order on three pending dispositive motions, all centering on one issue: whether in codifying Substantive Rule 25.242(f)(1)(B), the PUC fully implemented the regulations promulgated by FERC pursuant to PURPA. The court held in the affirmative and entered summary judgment in favor of the PUC and TNMP. Power Res. Group v. Hudson, No. A-03-CA-762-H (W.D.Tex. July 15, 2004).
PRG timely appealed the district court’s determinations (1) that the 90-day rule does not violate PURPA and (2) that the district court lacked jurisdiction to grant relief of PRG’s as-applied claims. The PUC and TNMP argue, as an alternative ground upon which this Court could affirm the judgment of the district court, that the district court erred in determining that PRG’s claims were not barred by collateral estoppel.
II. STANDARD OF REVIEW
This Court reviews the district court’s grant of summary judgment
de novo. Smith v. United States,
State regulatory authorities such as the PUC are required to implement PURPA pursuant to the rules and regulations promulgated by FERC.
See
16 U.S.C. § 824a-3(f). We review the PUC’s implementation with deference because “[a] state has broad authority to implement PURPA with respect to the approval of purchase contracts between utilities and QFs.”
N. Am. Natural Res., Inc. v. Mich. Pub. Serv. Comm’n,
*237 III. DISCUSSION
A.
The primary issue before this Court is whether the PUC’s rule that a legally enforceable obligation arises only when a qualified facility can deliver power within 90 days runs afoul of PURPA and its associated federal regulations. Pursuant to 16 U.S.C. § 824a-3(a), FERC must promulgate regulations to effectuate PURPA’s goal of encouraging the development of cogeneration and small power production facilities.
FERC v. Mississippi
The Supreme Court has held that a state may comply with its obligation to implement PURPA and its associated FERC regulations in one of three ways: “by issuing regulations, by resolving disputes on a case-by-case basis, or by taking any other action reasonably designed to give effect to FERC’s rules.”
Id.
at 751,
The FERC regulation that applies to the issue in this case is § 292.304(d), which provides:
Purchases “as available” or pursuant to a legally enforceable obligation. Each qualifying facility shall have the option either:
(1) To provide energy as the qualifying facility determines such energy to be available for such purchases, in which case the rates for such purchases shall be based on the purchasing utility’s avoided costs calculated at the time of delivery; or
(2) To provide energy or capacity pursuant to a legally enforceable obligation for the delivery of energy or capacity over a specified term, in which case the rates for such purchases shall, at the option of the qualifying facility exercised at the beginning of the specified term, be based on either:
(i) The avoided costs calculated at the time of delivery; or
(ii) The avoided costs calculated at the time the obligation is incurred.
18 C.F.R. § 292.304(d). This provision allows QFs to provide energy to utilities either by entering into a contract or pursuant to a LEO.
See Small Poiver Prod, and Cogeneration Facilities; Regulations Implementing Section 210 of the Public Utility Regulatory Policies Act of 1978,
45 Fed.Reg. 12,214, 12,224 (Feb. 25, 1980). FERC has explained: “Use of the term
*238
‘legally enforceable obligation’ is intended to prevent a utility from circumventing the requirement that provides capacity credit for an eligible qualifying facility merely by refusing to enter into a contract with the qualifying facility.”
Id.
This requirement is FERC’s response to the reluctance of traditional electric utilities to purchase power from nontraditional electric generation facilities, a problem identified by Congress which could hinder the development of such nontraditional facilities.
See Windway Tech.,
at *3,
The PUC argues that the 90-day rule properly implements the FERC regulation regarding LEOs. The 90-day rule provides, in relevant part, as follows:
Each electric utility shall purchase energy and capacity from a qualifying facility with a design capacity of lOOkw or more within 90 days of being notified by the qualifying facility that such energy and capacity are or will be available, provided that the electric utility has sufficient interconnection facilities available.... Nothing in this subsection shall be construed in a manner so as to preclude a qualifying facility from notifying and contracting for energy and/or capacity with a utility prior to 90 days before delivery of such energy and/or capacity.
PUC Subst. R. 25.242(f)(1)(B). PRG claims that the 90-day rule does not meaningfully implement the FERC regulation’s mandate for the option of a legally enforceable obligation. PRG argues that the 90-day rule eviscerates the LEO option for unbuilt QFs, because a new facility cannot be financed and constructed in only 90 days. It claims that denying unbuilt QFs the opportunity “to lock-in a purchase rate prior to the development, financing, and actual construction of the facility, even where the utility has projected a need and the QF can meet that projected need at a rate at or below the utility’s avoided cost” denies unbuilt QFs their right to LEOs under PURPA.
PRG has failed to show that PURPA and the FERC regulations mandate that all QFs, including unbuilt ones, must be able to create a LEO at any time. To the contrary, states must provide for legally enforceable obligations as distinct from contractual obligations, but “[i]t is up to the States, not [FERC], to determine the specific parameters of individual QF power purchase agreements, including the date at which a legally enforceable obligation is incurred under State law.” W. Penn Power Co., 71 F.E.R.C. ¶ 61,153, 61,495 (May 8, 1995). West Penn and its progeny Jersey Central Power & Light Co., 73 F.E.R.C. ¶ 61,092, 61,297 (Oct. 17, 1995), and Metropolitan Edison Co., 72 F.E.R.C. ¶ 61,015, 61,050 (July 6, 1995), support the proposition that the FERC regulations grant the states discretion in setting specific parameters for LEOs.
Certain states may be more generous than Texas toward QFs in their allowance for the creation of LEOs. We agree with the district court’s reasoning that the fact that some states have implemented the FERC regulations pursuant to their respective state laws such that a LEO may arise prior to construction of a QF does not compel Texas to do so. Other states have concluded that LEOs did not arise when the QF was not completed.
Compare Armco Advanced Materials Corp. v. Pa. Pub. Util. Comm’n,
PRG argues that the 90-day rule completely eviscerates the LEO option mandated by the FERC rule, but PRG makes no such showing. On its face, the 90-day rule implements PURPA and its regulations regarding LEOs by allowing QFs to create LEOs and secure pricing based on the LEOs, once the QF notifies the purchasing utility that energy will be available from the QF within 90 days. PURPA allows states discretion in determining when a LEO is created, and Texas’s 90-day rule falls within that discretion.
PRG points to the Third Circuit’s statement that “16 U.S.C. § 824a~3 [of PURPA] requires the FERC to prescribe ‘such rules as it determines necessary to encourage cogeneration and small power production,’ including rules requiring traditional utilities to purchase electricity from QFs.”
Freehold Cogeneration
As
socs., L.P. v. Board of Regulatory Comm’rs,
In sum, in codifying Texas Substantive Rule 25.242(f)(1)(B), the PUC acted within its discretion and properly implemented FERC’s regulations regarding when a LEO is created. We affirm the decision of the district court granting summary judgment on this issue to the PUC and TNMP.
B.
PRG also argues that the district court erred in determining that it lacked jurisdiction to grant relief on PRG’s as-applied claims. Because we affirm the district court’s decision on the 90-day rule issue, the judgment in favor of the PUC and TNMP is upheld and our analysis need go no further.
C.
Finally, we turn to the argument of the PUC and TNMP that the district court could have dismissed this case on grounds of collateral estoppel. The PUC and TNMP, who come before this Court as prevailing parties, did not cross-appeal the district court’s decision that collateral es-toppel did not bar the implementation *240 claim; rather, they merely raise the issue as an alternative ground upon which this Court could affirm the judgment of the district court. In that we deny PRG relief on its appeal of the district court’s decision on implementation, we need not address this issue.
IV. CONCLUSION
Because Texas’s 90-day rule regarding LEOs implements PURPA and its associated regulations within the discretion granted to Texas, the decision of the district court granting summary judgment in favor of the PUC and TNMP is AFFIRMED.
Notes
. This Rule was previously codified at PUC Subst. R. 23.66(d)(1)(C). We refer to the Rule by its current citation, PUC Subst. R. 25.242(f), oras the “90-day rule.”
. In
Independent Energy,
the Court of Appeals for the Ninth Circuit ultimately concluded that this authority was limited with respect to the exclusive federal authority to certify QFs.
