POWER AUTHORITY OF THE STATE OF NEW YORK, Plaintiff-Appellant, v. M/V ELLEN S. BOUCHARD, and the BARGE B NO. 280, their engines, apparel, tackle, boats, appurtenances, etc., in rem, BOUCHARD TRANSPORTATION CO., INC., MOTOR TUG ELLEN S. BOUCHARD, INC., B. NO. 280 CORP., Defendants-Appellees.
No. 19-1140-cv
United States Court of Appeals For the Second Circuit
DECIDED: JULY 30, 2020
ARGUED: APRIL 17, 2020
August Term, 2019
Appeal from the United States District Court for the Southern District of New York No. 1:14-cv-04462 — Paul A. Crotty, Judge
Defendants-Appellees.1
Before: LIVINGSTON, LOHIER, and NARDINI, Circuit Judges.
The plaintiff-appellant, the Power Authority of the State of New York (“the Authority“), appeals from an order and judgment of the United States District Court for the Southern District of New York (Crotty, J.), which granted summary judgment to the defendants-appellees, two vessels and their corporate owners, on the Authority‘s claims brought under the federal Oil Pollution Act (“OPA“),
VINCENT J. FOLEY (James H. Hohenstein, on the brief), Holland & Knight LLP, New York, NY, for Plaintiff-Appellant.
GINA M. VENEZIA (Wayne D. Meehan, John J. Walsh, on the brief), Freehill Hogan & Mahar, LLP New York, NY, for Defendants-Appellees.
Jeffrey Bossert Clark, Assistant Attorney General, Eric Grant, Deputy Assistant Attorney General, Ellen J. Durkee, Jennifer Scheller Neumann, Katherine W. Hazard, United States Department of Justice, Washington, DC, for Amicus Curiae United States of America, in support of Plaintiff-Appellant.
This appeal arises from the discharge of several thousand gallons of oil into Long Island Sound from a “submarine cable” — that is, an underwater system that transmits electricity, and through which dielectric fluid is pumped as a lubricant and coolant. The plaintiff-appellant, the Power Authority of the State of New York (“the Authority“), alleges that the dropped anchor of the Barge B. No. 280, which was being towed by the tugboat M/V Ellen S. Bouchard, ruptured the cable, which the Authority owns and operates. Following the containment and remediation of the oil discharge, the Authority sought compensation for its expenditures by suing the defendants-appellees: the two vessels and their corporate owners (collectively, “Bouchard“). The Authority brought claims pursuant to the federal Oil Pollution Act (“OPA“),
The Authority now appeals from an order and judgment of the United States District Court for the Southern District of New York (Crotty, J.), which determined that the OPA‘s statutory definition of a “facility,”
We hold that the submarine cable is indeed “used for” one of the enumerated “purposes” in the statute‘s definition of “facility.” It was therefore error for the district court to dismiss the Authority‘s OPA claims and to conclude that the Authority‘s NYOSL claims had to be brought in the parallel proceeding on that basis. Accordingly, we vacate the order of the district court and remand for further proceedings consistent with this opinion.
I. Background2
A. The Submarine Cables
The Authority owns and operates the Y-49 Cable System, a power transmission cable system that spans Long Island Sound. The cable system runs from the Sprain Brook Substation in Westchester County, which Consolidated Edison (“Con Edison“) operates, to the East Garden City Substation in Nassau County, which the Long Island Power Authority operates.
There are four submarine cables spanning Long Island Sound, with two self-contained fluid-filled (“SCFF“) pressurization plants located at the two ends of the cables. The four submarine cables are high-voltage transmission cables consisting of multiple layers, including the electrical conductor and a layer of “fluid-impregnated paper insulation.” Joint App‘x 479. Additionally, a central duct in each cable is filled with dielectric fluid, which is a “hydrocarbon, petroleum-based oil” that “acts as a coolant and lubricant to the electrical components of the submerged cables.” Id. at 603-04. The four cables combined hold approximately 10,000 gallons of the dielectric fluid at any given time.
The SCFF pressurization plants, meanwhile, are comprised of storage tanks holding reserve dielectric fluid, as well as equipment to monitor and regulate the pressure in the submarine cables. The plants are required to keep a constant static pressure in the cables to ensure the cables function properly. To do that, the plants increase or decrease the volume of dielectric fluid stored in the cables. Because the maintenance of constant pressure requires differing amounts of fluid depending on, among other things, the temperature of the water surrounding the cables, the dielectric fluid regularly flows through the plants and cables.
B. The Discharge
On January 6, 2014, the defendant Barge B. No. 280, in the course of being towed by the M/V Ellen S. Bouchard through Long Island Sound, dropped anchor. Shortly thereafter, Submarine Cable No. 3 experienced an electrical fault; at the same time, the system‘s monitors reported a sudden pressure drop in the cable, which indicated a leak of dielectric fluid was underway. The Authority alerted local and federal authorities, while also working with Con Edison and the Long Island Power Authority to initiate a response.
Over the next several weeks, these entities, along with the Authority‘s environmental response contractor, Miller Environmental Group, took efforts to contain and then clean up the spill, in consultation with the U.S. Coast Guard and New York officials. Among the required containment steps was the continued pumping of dielectric fluid into Cable No. 3, to maintain pressure and prevent water from entering the cable and potentially destroying it. Because of this ongoing need to pump fluid into the cable, the total discharge from Cable No. 3 was well above the cable‘s
C. Statutory Framework
Congress enacted the OPA in 1990 in the aftermath of the Exxon Valdez disaster, with an aim to unify and supplement the then-existing patchwork of federal regulations governing oil pollution. See Pub. L. No. 101-380, 104 Stat. 484 (codified at
Of central importance to this appeal, the OPA defines a “facility” as follows:
[A]ny structure, group of structures, equipment, or device (other than a vessel) which is used for one or more of the following purposes: exploring for, drilling for, producing, storing, handling, transferring, processing, or transporting oil. This term includes any motor vehicle, rolling stock, or pipeline used for one or more of these purposes.
Finally, the OPA contains a savings clause, which governs the effect of the statutory scheme on state law. See
Nothing in this Act or the Act of March 3, 1851 [the Limitation Act] shall . . . affect, or be construed or interpreted as preempting, the authority of any State or political subdivision thereof from imposing any additional liability or requirements with respect to . . . (A) the discharge of oil or other pollution by oil within such State; or (B) any removal activities in connection with such a discharge.
The Limitation Act effectively caps the liability of vessel owners for claims for certain damages caused by their vessels, limiting recovery to the value of the vessel
II. Procedural History
Shortly after the rupture, on February 26, 2014, the corporate defendants in this case5 started a Limitation Act proceeding in the United States District Court for the Southern District of New York.
See In re Bouchard Transp. Co., No. 14-cv-01262-PAC. The Authority and its insurers filed claims in the Limitation Act proceeding in April 2014 but expressly reserved the right (and expressed the intent) to separately bring claims against Bouchard under the OPA and the NYOSL. In June 2014, the Authority did just that, bringing this action against Bouchard.
After discovery, the parties filed cross-motions for summary judgment. Bouchard sought summary judgment on the Authority‘s OPA claims, as well as dismissal without prejudice of the remaining state-law claims with an order directing the Authority to pursue those claims in the Limitation Act proceeding.
On March 27, 2019, the district court granted Bouchard‘s motion for summary judgment and denied the Authority‘s cross-motion. See Power Auth. of N.Y. v. Tug M/V Ellen S. Bouchard, 377 F. Supp. 3d 230, 239 (S.D.N.Y. 2019). Acknowledging that there was “virtually no applicable case law elaborating” on the scope of the OPA‘s “facility” definition, the district court concluded that the submarine cables did not come within that definition. Id. at 236. In so concluding, the district court first determined that its analysis was limited to the submarine cables themselves, excluding the pressurization plants. Id. The district court determined that the cables were not “used for” any of the enumerated purposes in the definition, meaning that they were not a “facility.” It thus held that the discharge did not come within the OPA‘s scope. Lastly, because the Authority did not have a valid OPA claim, the district court concluded that the OPA‘s savings clause did not preempt the Limitation Act, so that the Authority could pursue its NYOSL claim only in the parallel proceeding.
III. Discussion
The Authority appeals from the district court‘s order and judgment, challenging its conclusion that the submarine cables were not a “facility” within the meaning of the OPA because the cables were not “used for” one of the purposes that the OPA enumerates. In the alternative, the Authority challenges the district court‘s determination that the OPA‘s savings clause did not allow the remaining state-law
As explained below, we agree with the Authority that the submarine cables are “used for” at least one purpose enumerated in the OPA‘s definition of “facility.” We therefore hold that the district court erred in granting Bouchard summary judgment on the OPA claims and transferring the state-law claims to the Limitation Act proceeding on that basis.
A. Standard of Review
We review a grant of summary judgment de novo; specifically, where the “disposition presents only a legal issue of statutory interpretation,” as here, “we review de novo whether the district court correctly interpreted the statute.” Hayward v. IBI Armored Servs., Inc., 954 F.3d 573, 575 (2d Cir. 2020) (quoting City of Syracuse v. Onondaga Cty., 464 F.3d 297, 310 (2d Cir. 2006)).
B. Analysis
The district court‘s decision was premised on the determination that the submarine cable was not a “facility” within the meaning of the OPA. We disagree. Even assuming arguendo that the relevant unit of inquiry here is limited to the cables themselves and does not include the pressurization plants, as the district court held, we conclude that the cables are “used for” an enumerated purpose within the OPA‘s “facility” definition.
In interpreting a statutory provision, our analysis begins with “the plain meaning of [the] law‘s text, and, absent ambiguity, will generally end there.” United States v. Balde, 943 F.3d 73, 81 (2d Cir. 2019) (internal quotation marks omitted); see also Artis v. District of Columbia, 138 S. Ct. 594, 603 (2018) (“In determining the meaning of a statutory provision, we look first to its language, giving the words used their ordinary meaning.” (internal quotation marks omitted)). Only if the text is ambiguous do we “turn to canons of statutory construction for assistance in interpreting the statute.” Greathouse v. JHS Sec. Inc., 784 F.3d 105, 111 (2d Cir. 2015).
Here, we find that the plain meaning of the OPA‘s definition of “facility” encompasses at least one of the purposes for which the submarine transmission cables are used. To recall, the OPA defines a “facility” as follows:
[A]ny structure, group of structures, equipment, or device (other than a vessel) which is used for one or more of the following purposes: exploring for, drilling for, producing, storing, handling, transferring, processing, or transporting oil. This term includes any motor vehicle, rolling stock, or pipeline used for one or more of these purposes.
The crux of the question, then, is whether the utilization of this capability suffices for the cables to be considered “used for” that “purpose[].”
Bouchard urges — and the district court adopted — a more restrictive reading of this language, but Bouchard‘s proffered limitations would narrow the scope of the OPA beyond what the words of the statute support. First, Bouchard‘s assertion that the cables are “primarily” or “substantially” used for power transmission, and only incidentally for one of the statutorily enumerated purposes, is beside the point. The definition contains no primacy requirement. To the contrary, the law expressly provides that equipment may serve multiple purposes and still count as a “facility“: a facility may be “used for one or more of” the enumerated purposes.
Similarly, we are not persuaded by Bouchard‘s argument that the OPA is “aimed at facilities that are engaged in oil exploration, production and transportation[,] as opposed to facilities that merely use oil incidental to other industrial uses.” Appellant‘s Br. at 16. Even if the Exxon Valdez oil spill prompted Congress to enact the OPA, and that many incidents triggering the OPA will relate to commercial oil exploration, production, and transportation, Congress did not write such a limitation into its definition of “facility.” To the contrary, other portions of the OPA demonstrate that the term “facility” is more encompassing than that. For example, the definition of “oil” coming within the OPA‘s scope is indisputably broad, with the statute
Because we hold that these cables are used for at least one of the purposes specified in the OPA‘s definition of “facility,” the district court‘s conclusion that the Authority did not have a viable OPA claim was error.10 Further, the district court‘s decision to transfer the Authority‘s NYOSL claims to the Limitation Act proceeding, predicated as it was on the finding that the Authority did not have a viable OPA claim, was error as well.11
IV. Conclusion
To summarize, we hold as follows:
The submarine cables here are used at least for the purpose of transferring dielectric fluid within the meaning of the OPA‘s definition of “facility” because they are used to transfer dielectric fluid along the length of the cables and between the cables and the pressurization plants. As a result, the district court erred in concluding that the cables were not a “facility” on the basis that they were not used for any such purpose, and that the Authority thus did not have a viable claim under the OPA.
