24 Del. 3 | Del. Super. Ct. | 1909
delivering the opinion of the Court:
The Court have very carefully considered this question over night, and have reached a conclusion in which we feel quite clear.
This is a motion to quash the scire facias upon a mechanics’ lien issued in this case and is based upon the following ground; that while the statement of plaintiff’s claim should have been filed, as it was, within the thirty days after the expiration of the ninety days after the completion of the work and labor performed and delivery of materials, the affidavit required to be made by the plaintiff to the truth and correctness of the claim and of the facts stated therein, and filed with the said statement, is insufficient because it was made within the ninety days after the completion of the work and labor performed and the delivery of materials.
We think that that case is not at all analogous to the present one. Certainly the reason upon which it was based does not exist in the case now before us. It is admitted here that the affidavit could be made prior to the docketing of the scire facias provided it was within the thirty days within which such scire facias could be issued. We can see no reason why an affidavit could not be made at any time after the completion of the work or delivery of materials, for the recovery of the value of which the scire facias is brought. The plaintiff then had a right of action against the defendant although the time had not yet arrived for his invoking the special remedy of scire facias provided by the statute.
We decline to quash the scire facias sur le mechanics’ lien upon the ground of the insufficiency of the affidavit filed.