*1 CONSTRUCTORS, POWDER HORN
INC., and Paul Fire and Marine St. Petitioners, Company,
Insurance FLORENCE, Respondent. OF
CITY
No. 85SC502. Colorado,
Supreme Court
En Banc.
April 1988.
Rehearing June Denied
Conover, P.C., & Heppenstall, McClearn Hugh McClearn, Lemon, J. Catherine A. Denver, petitioners. for Krassa, P.C., F.T. Law Office of Robert Krassa, Pueblo, respon- Robert F.T. for dent. Grover, Denver,
Charles E. for amicus Ass’n, curiae Colorado Contractors’ Inc. KIRSHBAUM, Justice. In City Florence v. Powder Horn
Constructors, Inc., (Colo.App. P.2d 1985), Appeals affirmed a trial Court ordering judgment court forfeiture of a bid bond executed for the benefit of the (the City) by petitioners, Florence Pow Constructors, Horn) (Powder der Horn Inc. surety, Fire Powder Horn’s St. Paul (St. Paul). Insurance Co. Marine requesting action the for filed a civil damages feiture as for Powder Horn’s re fusal, bidder, City’s to accept low public improvement construc award tion Powder Horn as a contract. asserted equitable right defense a from the relief provisions ground on the that it of the bond bid; reject had rescinded its trial court ed this claim. The Court of held certain circumstances a low bid under for construction contract der the trial rescind its but affirmed Having judgment. granted court’s certio- decision, rari to reverse and review we remand directions.
I 1981, 24, City publish- On December for ed an sealed bids advertisement on a construction work water treatment facility. initially were due The bids January 14, but that was subse- date On quently January extended 6, 1982, January obtained Horn from, detailing set of documents engineering specifications project. sub- Powder Horn January
On
$699,500
project.
for the
mitted a
doc-
required by
As
the terms
the bid
uments,
a bid bond
submitted
it also
sum
percent
of five
its total bid.1 When
der Horn asserted as a defense
it
had
publicly opened
the bids were
late that
rescinded its bid and therefore could not be
day,
same
Powder Horn was identified as
held liable under the terms of the bid bond.
the low bidder. The second lowest bid
The trial court found that Powder Horn
$754,330.
price was
pre-
had not exercised reasonable care in
Gilbert,
day, January
The next
Paul
paring
finding,
its bid. Based on this
it
*3
City’s consulting engineer
charge
the
determined that Powder Horn was liable to
administering
project, telephoned
the
Mi-
City
the
in the amount of the bid bond.
O’Clair,
estimator,
a
chael
Powder Horn
The trial court also determined that Pow-
him
in tabulating
advised
that
the bids
der Horn’s conduct constituted a unilateral
he
found one item
had
in Powder Horn’s mistake,
material,
that
the mistake was
appeared
substantially
bid that
be
to
low
requiring
perform
that
Powder Horn to
the
view the other bids submitted. Gilbert
unconscionable,
contract would be
and that
suggested
might
that Powder Horn
want
Powder Horn had failed to establish that
particular
that
review
item.
City
the
prejudiced by
would not be
the
January
president,
On
Powder Horn’s
withdrawal
Powder Horn’s bid.
Donahue,
Cletus
informed Gilbert
tele-
In affirming the
judgment,
trial court’s
phone
mistakenly
that Powder Horn had
Appeals
recognized
the Court
that
$66,660,
omitted from its bid the sum of
some
per
circumstances a bidder
be
item,
representing
major
the
of one
cost
mitted to rescind a
for
bid submitted
being
and that
bid
was therefore
with-
public construction contract
because
day,
drawn. On that same
Donahue also
calculating
mistake in
the bid. The Court
wrote a letter tо
engineering
Gilbert’s
firm
Appeals
remedy
concluded that such a
is
in which he stated that a subtotal from one
only
proves by
available
when the bidder
inadvertently
worksheet
had been omitted
preponderance
“(1)
of the evidence that:
amount,
final bid
advised that the
the mistake relates to a material feature of
security
being
bid and the bid
were
with-
contract;
despite
it occurred
drawn and
offered meet with the con-
care;
exercise of reasonable
sulting engineers,
attorney
or oth-
public authority
placed
can
be
status
er officials to demonstrate that
omis-
quo.” City
Florence v. Powder Horn
sion was an honest error.
Constructors,
(Colo.
716 P.2d
February 1, 1982,
On
City, through
App.1985). It held that Powder Horn could
council,
city
its
voted to award the contract
not rescind the bid because it had
exer
not
$699,-
to Powder Horn
amount
preparing
cised reasonable care in
it. The
February
500. On
Donahue sent a letter
Appeals
pub
Court of
also observed that a
engineering
stating
Gilbert’s
firm
entity
changed
position
lic
which has
accept
Powder Horn would not
the award
reliance
a mistaken
has suffered
bid
the contract. The
then awarded the
damages
no
actual
able to maintain
contract to the second lowest bidder. That
quo merely by accepting
the status
accepted
the contract and com-
second
only
lowest bid “since it has lost
menced work.
sought
gain by taking
what it
advantage
against
filed this action
Powder
of the mistake.” Id. at 145.
Paul, asserting
Horn
right
and St.
agree
We
with the conclusion оf the
amount of
liquidated
the bid bond as
dam-
ages
Court of
that under certain cir-
Powder Horn’s failure to execute
submitting
cumstances a bidder
a bid for a
complaint
construction contract. The
alleged
although
City’s
permit-
construction contract
actual
damages equaled $54,830,
acceptance
ted
rescind the bid
to its
difference
between Powder Horn’s
if it reflects
bid and the second
a material mistake of fact.
bid,
liability
agree, however,
lowest
Powder Horn's
was lim- We do not
exer-
ited to the amount of the bid bond. Pow-
cise of
appropriate
reasonable care
$699,500
$34,975.
bond
for Powder Horn's
bid was
thus
addition,
right
bargain).
many
to condition
factor
which
courts,
legislative
rescission.
commentators
bodies
explicitly
implicitly recog-
have either
II
nized
a mathematical or clerical error
bid,
yields an unintended
while an error in
class of
falls into that narrow
This case
such as
judgment,
estimating
an error in
in which an
public construction
cases
when,
necessary
the number
hours of work
prior tó
mistaken
arises
issue of
project,
complete
yields precisely
public entity’s acceptance
is not
intended and
deemed a mistaken
that the bid contains
bid.
parties discover
E.g.,
College
error.
Boise Junior
Dist. v.
mathematical or clerical
material
Mattefs
Co.,
argues
such cir
Idaho
450 P.2d
Horn
that under
Constr.
Phelps
the bidder
be allowed
State v. Hensel
Constr.
cumstances
should
(Mo.1982); Jobeo,
pen
automatically
its bid
without
634 S.W.2d
withdraw
Inc. v.
Nassau,
supports
A.D.2d
alty.
body
County
A substantial
of law
*4
argument,
(1987);
in
con
108
Muncy
Horn’s
effect
N.Y.S.2d
Area School
Powder
Gardner,
406,
a bid
cluding that where a bidder submits
Dist. v.
91 Pa.Commw.
497
(1985);
containing
of
and
683
10
generally
a material mistake
fact
A.2d
see
E.
apparently accepted
McQuillin,
Municipal
there has not
The
Corpo-
the bid is
Law of
(3d
1981); Rudland,
any meeting of
minds
29.82
ed.
been
because
rations §
Rules,
public
accepted by
entity
Rationalizing
is not the
Mistake
bid
Bid
16
(1986);
446
E.g., Moffett,
bid
the bidder.
Pub.Cont.LJ.
see also
intended
M.F.
Rochester,
Kemper
178
Hodgkins
Ange-
Clarke Co. v.
Constr. Co. v.
Los
&
957,
696,
373,
(1900);
les,
(1951),
44
1108
37 Cal.2d
P.2d 7
super-
U.S.
20 S.Ct.
L.Ed.
235
statute,
No. 6 v. Aet
Cal.Pub.Cont.Code
Marana
School Dist.
seded
Unified
159,
(West
(where
1985)
P.2d
na
144 Ariz.
696
5103
mistake made
Cas. & Sur.
§
intended,
Dist.
(Ariz.App.1984); Regional
materially
711
School
different than
re-
hid
Co., Conn.App.
filling
4
v.
Pac. Ins.
out
No.
United
lief available
mistake
4
895,
denied,
175,
form,
196 Conn.
judgment);
493 A.2d
not for mistake in
but
certif.
(1985);
County
(1987)(if
813,
However,
analysis
Rules,
legal
ignores
(1986).
16 Pub.Cont.L.J. 446
courts,
important
emerged
has
distinction that
issue for these
as the Court of
assump-
public
Appeals recognized,
ques-
the law of
contracts —the
is reduced to the
construction con-
public
identifying
tion that bids for
tion of
the circumstances and
generally
are
considered to be irrev-
appropriate
tracts
support
factors
will
Jones,
upon opening.
The Law
request
ocable
bidder’s
for relief from the conse-
Bids, 48
&
U.Cin.L.Rev.
Mistaken
quences
agree
a mistaken bid. We
of
n.
principle
pro-
serves to
This
Appeals
the conclusion of the Court
bidding process by
integrity
tect the
responsible
thе more fair
policy
is to
encouraging
preparation
of accurate
recognize
public entity’s
bids, reducing possibilities of collusion and
acceptance
public
of a bid for a
construc-
bidding practices among contrac-
artificial
project
tion
a bidder
in some circum-
tors,
predictability promoting
cer-
equitable
stances obtain
relief from the
expending
tainty
process
consequences
containing
aof
a mathe-
funds.
matical or clerical error.
jurisdictions
Some
have determined
principally
Court
relied
adopting
policies by
further these
a rule
on the
case
John J. Calnan Co. v.
prohibits
generally
rescission of a bid
Builders,
Talsma
67 Ill.2d
for a
construction contract at
(1977),
Ill.Dec.
367 N.E.2d
opened. E.g.,
time
after
bids are
Anco
adopting
requirement
a test that includes a
Wichita,
Constr. Co.
Kan.
proof
non-negligence
justify
re
*5
(1983); City
Sfil
encouraging
con
bidding practices.
nan was not entitled to rescind the
fair
To the
contrary,
tract.
requirement
such
would in these
severely
limited circumstances
undermine
presents
This case
far different circum-
policies
fostering
dealing
fair
and cer
“possi-
stances. The
was aware
tainty among contracting parties essential
ble” mistake
Powder Horn’s bid before
negotiation
process. See
was,
Horn
and Powder Horn com-
Jones,
Bids,
The Law
Mistaken
municated its intention to rescind its bid
U.Cin.L.Rev. 43
immediately, prior
any change
posi-
by
City.
accept
tion
did not
The Court of
concluded that re-
until
later —at
time when it had
quiring
prove
Powder Horn to
it was not
knowledge
full
of both the mistake and the
negligent in
preparation
of its mistaken
fact that
because
mistake Powder
protect
bid served to
the integrity of the
Horn had withdrawn its bid. No contract
bidding process,
consistency
to foster
in bid
project
for construction
was ever preparation throughout
state,
and to
parties,
executed
and there
nowas
discourage
prevent
fraud and collusion.
delay,
surprise,
justifiable
no
and no
re- City
Florence v. Powder Horn Con-
liance
at the time it elected to
structors, Inc.,
362
(1983) (under
law,
ligence focuses
attention on the
substantial
federal
where
mistake;
question
cause of the
agency
or
is on actual
constructive notice
equitable
from
availability
relief
a mis of bidder’s unreasonable mistake and ac-
primarily
taken bid should focus
on
cepts bid
verifying
accuracy,
without
consequences of the mistake. Further
presumption
agency
arises that
acted
more,
three-part
test articulated in Cal-
attempt
bad faith in
to take advantage of
prove
require
nan would
bidder);
24-101-104,
(1982)
see
10 C.R.S.
magnitude
its mistake was of sufficient
good
(imрosing
faith standard
all
yet,
material to the contract
be considered
parties
procurement
involved
state
activ-
incongruously, that
the mistake was not
ities);
Corbin,
A.
see also
Corbin on Con-
Corbin,
negligence.4
the result
A.
process
(bidding
tracts
609
will
608,
609
Corbin on Contracts §§
stability by requiring
prove
retain
bidder to
(noting
computing
an
error
mistake).
recog-
substantial
approach
This
negligence).
invariably involves at least
nizes that bidder
should not
be allowed
Numerous
courts
commentators
if
rescind a mistaken bid the
made
bid were
have concluded that in
construction
emphasizes
desirability
faith and
bad
eq
contract cases which a bidder seeks
ensuring
public projects proceed
provi
uitable relief
bond forfeiture
the basis of accurate cost
A
estimates.
sions because of a
mistaken
funda
contrary
encourage manipu-
rule would
mental
issue whether
bidder made
bidding practices
lative
undermine
good
any ques
honest
faith mistake and
stability
bidding process.
Further-
of gross
negligence
tion
or extreme
more,
application
evenhanded
only
bidder should be considered
as evi
faith standard
fair
ensures
treatment of all
dence of the bidder’s lack of
faith.
dealings
municipal
involved in
E.g., Marana
Dist.
School
No. v.
Unified
authorities, thereby enhancing
integrity
Co.,
159,
Aetna
&Cas.
Sur.
144 Ariz. at
bidding process.
711; Naugatuck
696 P.2d at
Valley Dev.
Corp.
Corp.,
Conn.App.
v. Acmat
context,
In this
noteworthy
it is
(1987); Mississippi
See also Restatement of § Restitutiоn a material and then stated that a rea- (person mistakenly upon who conferred benefit sonable contractor should not have omitted precluded another is not from restitution where such "considerable amounts." 3-202(6) bidding process. cal parties commentary all Governments ment of (2), (3) (1979) Although (bidder See 24-101-102. the Code should not be allowed bidding apply process, does to this its opening to amend bid unless after mistake ensuring good negotiation faith policy of is not one of and intended judgment bid is degree is notable.5 The public contracts documents). clearly evident from bid may a bidder negligence exhibited well In reviewing competing policy good bear whether a bid was made here, presented considerations we conclude faith, respect an inquiry in that into and that, in controlling legisla absence of the mistake be material cause tion, a bidder for a construction con ultimate determination of whether containing tract who submits bid mis equitable relief from a mistaken bid should prior take rescind the to its accept bid However, granted.6 awhen contain- bid if the by prepon ance bidder establishes prof- or mathematical error is a clerical derance of the evidence that the mistake is faith, fered in the fact that the mis- nature, of a or mathematical clerical negligent take conduct resulted the, mistake faith was made ability not foreclose the rescind should aspect relates to a material prior acceptance if no bid thereof public аuthority rely did not to its harm from the results rescission. detriment on If a the mistaken bid. bidder argued require that failure to elements, proves all rescission these negli- to demonstrate freedom from bidder granted the bid becaúse the should be bid gent as a condition to the exercise conduct apparently accepted was not the bid intend any right to rescind bid mistaken and, therefore, If, ed was not a valid bid. preparation. would reward careless bid however, prove each bidder fails to However, competitive environment test, equitable the elements bid public contracting a invariably submitted deemed the bid must be intended compelling has incentive bid accurate- proven entity may and the recover ly a bid an amount lower submit —to damages to the extent the bidder fails to than at which the bidder real- can perform obligations its contractual —such istically perform the work tantamount to bargain public entity’s as the loss of Rudland, all. submitting no bid at being forego forced the valid low bid Rules, Rationalizing the Bid Mistake award the contract to the next lowest bid (1986) (observing Pub.Cont.L.J. der. Such undermine the in test will not gains nothing by withdrawing that a bidder promote tegrity process, will fair bid). being rewarded, Far from a bid- dealing process all to that prior any der to rescind its bid allowed promote certainty will contractual en acceptance possibility thereof loses couraging discovery and disclosure early reaping profit from fulfillment of the con- material mistakes in bids. contrast, struction contract. careless case, advеrtising for In this bids actually preparation rewarded where City’s consulting engineer estimated bidding process fails to closely circum- $890,000 ability project the total cost of the to be scribe a to amend its bidder’s $699,- E.g., acceptance. after —well above Powder Horn’s bid opening but before Moreover, alerted Model Procurement Code State and Lo- 500. *8 24-105-201, (1982), any requires 5. 10 C.R.S. the record However, indication of such. Section disclose equal percent involving allegations the execution of a bid bond to five even in cases of of of bid for all con- the amount construction question fraud the of whether an honest mis- procurement tracts where the the officer estimates take of a nature is clerical or mathematical price fifty to exceed contract thousand dol- present objective subject is determination to an However, City adopted has not lars. preparation on a doc- based review of the bid thus, Code; provision of the Procurement See, e.g., City Syracuse v. Sarkisian uments. Bros., Inc., of case, provision inapplicable to this trial as the 945, 984, 451 N.Y.S.2d 87 A.D.2d court found. 71, 618, aff’d, 439 N.Y.S.2d N.E. SI N.Y.2d 454 2d 880 City does not assert that Horn’s The Powder fraud, constituted nor does review of conduct 364 of possible 3-202(6)
Horn
mistake when it
(6) (1979) (a
re- ments
commentary
§
viewed
bids submitted and noted that
suspected
give
mistake
duty
can
rise
ato
$169,500,
on
item
Horn
one
Powder
had bid
on
part
authority
seek
$216,600
the next lowest
had
bidder
bid
bid;
confirmation of
bidder who demon-
remaining eight
bidders had bid from strates mistake should be
allowed
cor-
$230,000
$330,000. Furthermore,
Pow-
bid).7
rect or withdraw
City
der Horn notified the
of the nature of
undisputed
It is
City
did not
its
intent
mistake and its
to withdraw the
solicit
bids
new
when Powder Horn with
awarding
contract,
prior
and, therefore,
drew its bid
no
incurred
yet
when no action
been taken in re-
had
rebidding
administrative
of
costs
on
liance
Powder Horn’s
bid and
inaccurate
project.
Regents
Board
Murray
Cf.
of
of
when other bids were still available to the
Cole,
Ky. 761,
State Normal
School
209
City.
(1925)
273
(withdrawing
S.W. 508
bidder
These
circumstances reveal
absence
held
authority
liable
for costs of
policies
of
underlying
one
the basic
contract).
rebidding the
The City ultimate
party
enforcement of contracts —if one
cre-
ly
awarded
contract to the next lowest
expectations
ates reasonable
in the other
bidder,
was, assuming
which
rescission
party,
expectations
those
should be ful-
Horn’s
lowest valid bid.
filled,
by performance
either
award
change
Thus in this case the
did not
its
damages.
Dobbs,
D.
Handbook on
position in
reliance on
mistaken bid.
(1973). Here,
the Law Remedies
11.4
§
E.g., Regional School Dist. No. v. United
4
did
not act
reasonable
Co.,
175,
Conn.App.
Pac.
4
Ins.
493 A.2d
expectations,
sought
but rather
to take ad-
(public authority
895
is unharmed
mis
vantage of Powder Horn’s mistake and
take
notified
prior
where
of mistake
gain
profit.
a windfall
If Powder Horn
contract),
denied,
award of
196
acting
faith,
in good
was
requiring it to
certif.
813,
(1985);
494
Conn.
A.2d 907
Boise Jun
though
forfeit
bid bond even
the City
College
ior
Dist. v.
92
Constr.
accepting
knew of the mistake
Mattefs
757,
(1969) (same
Idaho
365
conclusion);
hi
(same
(1973)
City
see also
Co.,
De Luca-Davis Constr.
Baltimore v.
City argues
that whatever standard
518, 124
(1956)(observing
557
210 Md.
A.2d
might
applied
eq-
be
Powder Horn’s
virtually unanimous
that the courts were
claim,
parties agreed
if
uitable
permitting withdrawal of bids where
designated
Powder Horn was
the low bid-
of mistake
authority was notified
subsequently
der and
failed to execute a
Corbin,
contract);
see also A.
award
construction contract Powder Horn’s bid
(1960)(offeree
payable
liquidated damages.
Corbin
Contracts §
bond was
given
notice of mistake
argument unpersuasive.
is unharmed where
findWe
this
bid).
acceptance of
before
A
rule of
fundamental
course,
in other
the factual context
Of
law is that
court should strive to ascer
that the
may support
cases
the conclusion
tain and effectuate
mutual intent of the
change
position
its
in re-
public entity did
Enters.,
parties. Martinez v. Continental
example,
For
liance on the mistaken bid.
(Colo.1986); Pepcol Mfg.
BID BOND provided pertinent itself in part [W]e, undersigned, ... POWDER as follows: CONSTRUCTORS, HORN INC.... as
Principal, and ST. PAUL FIRE AND
BID
MARINE
COMPANY
INSURANCE
as
Surety,
hereby
firmly
are
held and
bound
compliance
your
with
Advertise-
FLORENCE,
unto CITY OF
COLORA-
Bids,
hereby
ment for
BIDDER
proposes
penal
DO as
OWNER the
sum Five
perform
all WORK for the construc-
(5%)
Percent
Total Amount Bid
tion of Florence-Coal Creek-Williams-
burg Regional
System
Water
—Schedule
obligation
Condition of the above
3 in strict accordance
CON-
Principal
such that
whereas
has sub-
DOCUMENTS,
TRACT
within the time
mitted
CITY
OF
COLO-
FLORENCE.
therein,
set forth
prices
and at the
stated
BID,
RADO a certain
attached hereto
below.
hereby
part
amade
hereof to enter
writing,
into a contract in
for the Flor-
agrees
hereby
BIDDER
to commence
Creek-Williamsburg Regional
ence-Coal
WORK under this contract on or before
System
NOW,
Water
—Schedule
specified in
a date to be
the NOTICE TO
THEREFORE,
fully complete
PROCEED and to
(a) If
rejected,
said BID shall be
PROJECT within 210 consecutive calen-
(b) If said BID
accepted
shall be
days
dar
thereafter. BIDDER further
Principal
shall execute and deliver
agrees
damages,
as
pay
liquidated
a contract
in the Form of Contract
of $200.00
sum
for each consecutive cal-
(properly completed
attached hereto
day
endar
thereafter....
BID)
accordance with said
and shall
Again, no
“liquidated
mention is made of
furnish a
per-
BOND for his faithful
damages”
bond,
in reference to the bid
contract,
formance of said
and for the
although
provides
clearly
the bid
payment
persons performing
of all
la-
pay liquidated damages
per
of $200
furnishing
bor or
materials
connec-
day
dilatory completion
project.
therewith,
tion
shall
all other
respects perform
agreement
cre-
The contract documents also included an
acceptance
BID,
ated by the
of said
informational document.9 This document
part
provided
pertinent
This
document
opening
after the actual
date of
thereof.
follows:
why
Should there
reasons
specified peri-
cannot be awarded within the
INFORMATION FOR BIDDERS
od,
may
the time
be extended
mutual
agreement
may
between the OWNER and the BID-
The OWNER
waive
informalities
DER.
reject any
or minor defects or
and all BIDS.
Any
satisfy
BID
BIDDERS must
be withdrawn
themselves of the
accuracy
opening
quantities
above scheduled time for
BIDS
estimated
postponement
or authorized
thereof....
No
BID Schedule
examination
site and
days
drawings
BIDDER
withdraw a BID within 60
specifications
a review of the
*11
suggest
percent
sixty days
the five
bid within
opening
does not
of the
repre
by
party
intended
either
bids,10
bond was
it also
authorizes the
to waive
liquidated dam
agreed
amount of
sent
reject any
minor defects
bids or to
ages
damages from a
or that
the actual
all
It
bids.
does not indicate that the bond
to execute a construction
bidder’s failure
liquidated damages
must be forfeited as
if
might
regarded
as the differ
be
any of its terms are not followed.
еnce between a withdrawn low bid and the
appears
It
from the terms of the bid
Borough
next lowest bid. Cf. Bellefonte
provisions
bond and from the
of the accom-
Co.,
Gateway Equip.
Supply
&
Auth. v.
panying
purpose
documents that the
(1971) (where
Pa.
277 A.2d
compel
bid bond is to
the execution of a
given
prospec
informational documents
by
construction contract
the threat of ex-
failing
tive bidders stated
acting
payment
the amount of the
execute construction contract would forfeit
punishment
as
bond
for failure to execute
liquidated damages,
amount of bid bond as
Palmer,
such a contract.
2See G.
The Law
liquidated damages
bid bond constituted
12.20,
(1978) (“the
Restitution
at
penalty). Although
rather
than
the doc
prohibit
purpose
ument does
the withdrawal of bids
of the contract formed
the bid
including
accompanying
proposal
ADDENDA. After BIDS have been
shall become the
submitted,
property
the BIDDER shall not assert that
of the OWNER.
misunderstanding concerning
there was
quantities
may
investigations
of WORK or of the
nature
The OWNER
make such
necessary
WORK to be done.
as he deems
to determine the abili-
WORK,
ty
perform
of the BIDDER to
The CONTRACTDOCUMENTS contain the
the BIDDER shall furnish to the OWNER all
provisions required
purpose
for the construction of
such information and data for this
request.
may
the PROJECT. Information obtained from an
the OWNER
The OWNER re-
officer, agent,
employee
right
reject any
or
of the OWNER or
serves the
BID if the evi-
of,
any
person
by,
investigation
other
shall not affect the risks or
dence submitted
such
obligations
satisfy
assumed
the CONTRACTORor
BIDDER fails to
the OWNER that such
fulfilling any
properly qualified
carry
relieve him from
of the condi-
BIDDER is
out the
obligations
Agreement
complete
tions of the contract.
and to
accompanied by
contemplated
Each BID must be
a BID
the WORK
therein.
payable
percent
bond
to the OWNER for five
respon-
of the total amount of the BID. As soon as
Award will be made to the lowest
prices
compared,
BID
have been
sible BIDDER.
laws, ordinances,
except
applicable
OWNER will return the BONDS of all
All
and the
responsible
having
regulations
the three
lowest
BIDDERS.
rules and
of all authorities
Agreement
jurisdiction
When the
is executed the
bonds
over
construction
remaining
apply
through-
the two
unsuccessful BIDDERS
PROJECT shall
to the contract
will be returned. The BID BOND of the suc-
out.
cessful BIDDER will be retained until
responsible
inspecting
Each BIDDER is
payment
performance
BOND and the
BOND
reading
being thoroughly
the site and for
approved,
have been executed and
after which
familiar with the CONTRACTDOCUMENTS.
may
it will be
A
returned.
certified check
be
any
The failure or omission of
BIDDER to do
used in lieu of BID BOND.
way
any
foregoing
shall in no
relieve
performance
payment
A
BOND and a
any
obligation
respect
BIDDER from
BOND,
percent
each in the amount of 100
his
BID....
PRICE,
corporate
the CONTRACT
awith
sure-
OWNER,
ty
approved
required
Although
given
will be
the informational document
performance
for the faithful
contract.
to bidders stated that bids could not be with-
days
opening,
provi-
such a
drawn within
not,
course,
party
preclude
to whom the contract is awarded
does
withdrawal
sion
required
Agreement
legally justifiable
E.g.
will be
to execute the
for a
reason.
Connecticut
Co.,
(D.Conn.
performance
payment
F.Supp.
obtain the
BOND and
v. F.H. McGraw &
law;
1941)
concluding
days
(applying
BOND within ten
calendar
from the
Connecticut
provision
date when NOTICE OF AWARD is delivered
that the effect of a
in bid documents
to the BIDDER. The NOTICE OF AWARD
that bid could not be withdrawn within a cer-
accompanied by
necessary Agree-
days
opening
be
de-
shall
tain number of
of bid
was
signed
ment and BOND
In
be relieved
forms.
case
failure
to assure that bidder would
Agreement,
obligation only
legally justifiable);
the BIDDER to execute the
where
of its
option
College
OWNER
at his
consider the BID-
Dist. v.
Constr.
Boise Junior
Mattefs
default,
result).
(1969) (same
DER in
BID
which case the
BOND
92 Idaho
IV
public authority.
City
with the
The
asserts
light
City
that in
argues
Coray
also
decision section
that under
(cid:127)
31-15-712,
terms
section
12B
require
C.R.S. 31-15-712
must
read to
a munic-
11.
(3d
1961).
The trial court sustained Powder Horn's ob-
Law
§§
Contracts
774-775A ed.
jection
contrast,
admissibility
testimony
penal
рursu-
where a
bond is executed
Decker,
Charles
statutory
Farmers Home
requirement,
obligee
Administra-
ant to a
engineer,
purpose
tion civil
toas
of a bid
upon
recover the full
amount
the bond
non-
evidence,
Although
bond.
not
into
admitted
performance regardless of whether actual dam-
City presented
proof
as an
ages
offer of
the testimo-
E.g.,
Barnard,
are shown.
Clark v.
108 U.S.
ny
understanding
436,
878,
of Decker to the effect
his
(1883);
2 S.Ct.
tional error. We cannot required competitive for all sealed bid- compels Coray necessarily decision ding such for construction contracts when the In Coray price conclusion. the Court of procurement estimated question did not have before it the officer to fifty exceed thousand dol- municipality properly put Nothing whether a lars which .... this subsection prevents project up requirement forego awarding for bids could of such bonds on construction fifty contracts under contract to a bidder on the common law thousand dollars. basis of mistake. County & Bowen, 315, 317, Denver security 67 Colo. 184 P. Bid shall be in an amount (1919). Moreover, equal to at least percent the General five Assembly amount of the bid. specifically provided has the construction of statutes the common law shall in full repealed remain force until (4) After the *13 opened, bids are they 2-4-211,
by legislative authority, 1B § shall be period speci- irrevocable for the (1980), C.R.S. and section 31-15-712 does bids, fied in the except invitation for purport repeal not its terms the com provided 24-103-202(6). in section If a respecting mon law in mistakes the forma permitted bidder is to withdraw his bid tion of award, contracts. before no action shall be had against security. bidder or the bid However, assuming is cor- 24-105-201, (1982). pro- 10 C.R.S. These § concluding rect in that the General Assem- visions of the Code demonstrate a clear bly initially intended to disallow with- legislative intent allow bidders who have drawals of bids for construction inadvertently in рreparation erred projects, legislative intent was altered their bids to withdraw those bids before prior to the bidding time of in this case. In award of the contract without loss of bid 1981, the Assembly General enacted the Although application bond. of the Code (the Code), Procurement Code 24-101- §§ provisions is mandatory only respect 24-112-101, (1982). 101 to 10 C.R.S. branch, to bodies of the state executive Code is based the American Bar Asso- 24-101-105(2) section specifi- of the Code ciation’s Model Procurement Code for State cally grants municipal pow- authorities the Governments, and published Local in 1979. apply any provisions er to or all Code, Section 24-103-202 detailing conclude, therefore, Code. We requirements competitive be met City’s compelled contention that it was bidding, provides sealed pertinent part statutory law award the contract to the as follows: lowest bidder even where that bid con- (6) Withdrawal of inadvertently erro- tained an inadvertent error is without mer- neous per- bids before the award it. pursuant mitted to rules if the bidder proof submits of evidentiary value which V clearly convincingly and demonstrates judgment Appeals the Court of is Except that an error was made. as oth- reversed, and the case is remanded to the rules, provided by erwise all decisions to Court of with directions to reverse permit the withdrawal of bids based on judgment of the trial court to re- such supported by bid mistakes shall be mand the case to the deter- trial court for a written determination made the mination of whether Powder Hоrn’s bid purchasing state director or the head of good was made faith. In the event the purchasing agency. trial court the mistake was determines 24-103-202(6), faith, C.R.S. More- judgment made in should be over, Code, section 24-105-201 of the against entered for Powder Horn and provision specifically dealing City. with bid In the event the trial court deter- good verely policies
mines the mistake was made in undermine fostering fair faith, judgment should be entered for the dealing certainty among contracting against Powder Horn on the basis to any negotia- essential of the bond. process.” tion Maj. op. major- at 361. The ity asserts that requiring negli- a lack of
ERICKSON, J., dissents.
gence “focuses substantial evidence on the
mistake,”
cause of
VOLLACK, J.,
primary
when
dissents;
focus
given
“consequences
should be
MULLARKEY, J., joins
dissent.
Maj.
op.
According-
mistake.”
at 362.
ERICKSON, Justice, dissenting:
ly, the majority concludes that
in order
view,
I respectfully
my
dissent.
In
once
to rescind
Powder Horn must estab-
opened,
a bid to
authority
“good
lish a
Maj.
faith
op.
mistake.”
at
irrevocable,
bid or offer becomes
see 10 E.
McQuillin,
Municipal
The Law
Corpo-
view,
my
simply requiring a contrac-
29.67,
(3d
1981),1
rations
at 383
ed.
and a
tor to
submit
bid in
faith compro-
unilateral mistake of a contractor does not
mises
integrity
bidding process
justify
showing
rescission absent a
by failing
penalize sloppy
prepara-
(1) the mistake relates to a material fea-
by failing
discourage
tion and
fraud
contract; (2)
ture of the
it occurred de-
contractors
seek
who
to rescind a bid that
spite
care;
the exercise of reasonable
product
not the
of clerical error but
public authority
placed
can be
rather
judgment
mistake
on the con-
quo.
in status
A
part.
jurisdictions
tractor’s
majority of
Florence v. Powder Horn Con
adopted
has
the requirement
that a con-
*14
structors,
(Colo.
716 P.2d
tractor demonstrate that he exercised rea-
App.1985) (relying upon
J.
John
Calnan
sonable care before he is
to
allowed
rescind
Builders, Inc.,
Co. v. Talsma
67 Ill.2d
McQuillin,
a bid. See 10 E.
The Law of
(1977)).
10 Ill.Dec.
VOLLACK, Justice, dissenting:
tion,
encompasses, among
and it
other
belief,
things, an honest
absence
agree
I
respectfully
I
dissent. While
design
malice and the absence of
to de-
majority
with the
that considerations
fraud or to seek an unconscionable ad-
require
rejection of the “firm
equity
vantage,
personal
and an individual’s
rule,
agree
majority’s
I
bid”
do not
good
concept
faith is
of his own mind and
bidder can demand
conclusion that
low
and, therefore,
spirit
inner
not con-
public
rescission of a
construction contract
clusively
protesta-
be determined
his
merely by
a result of a mistaken bid
intention,
Honesty
tions alone.
I
showing that he acted in
faith.
knowledge
freedom from
of circumstanc-
under such circumstances a
believe that
ought
put
es which
holder
escape liability
cannot
for the
low bidder
inquiry. An honest intention to abstain
simply by
consequences of his mistake
taking any
from
unconscientious advan-
faith,
showing
he acted in
but
another,
tage
through technicali-
even
prove
must
that his mistake occurred de-
law, together
with absence of all
ties
spite the exercise of reasonable care. The
information, notice, or
benefit
belief
give
adopted by
majority
rule
fails to
facts which render transaction uncon-
weight
due
character
usage
scientious.
common
term
bidding process.
rule serves to
Such a
ordinarily
to describe that state
used
undermine confidence
con-
denoting honesty
purpose,
of mind
bidding process
ignores
struction
defraud, and,
freedom
intention
enacting
Assembly
intent of the General
*15
being
generally speaking, means
faithful
its version of the Model Procurement Code.
obligation.
duty
to one’s
or
Honesty in
Law.
fact
Commercial
I.
the conduct or transactiоn concerned.
majority
The
concludes that
1-201(19).
In the case of a
U.C.C. §
controlling legislation,
in the absence of
merchant, honesty in fact and the observ-
public construction con-
a bidder for a
of reasonable commercial standards
ance
containing
a
a
tract who submits
dealing in
trade.
of fair
U.C.C.
mistake
rescind the bid
to its
2-103(l)(b).
§
acceptance
if
the bidder establishes
(5th ed.
Dictionary
Law
623-24
Black’s
preponderance of the evidence that the
1979) (citations omitted).
mistake is of a clerical or mathematical
nature;
element to the definition of
mistake was made in
The common
requires an
good
honesty,
is
which
and relates to a material as-
faith1
good faith
applied to service con-
whether the UCC
faith is also defined in the Uniform
mine
1. Good
(UCC).
goods.
Code
Article Two of the
Four-
Commercial
which included a sale
tract
applies expressly to contracts for transac-
UCC
to determine
were identified
useful
factors
goods
by analogy
to service con-
tions
and
predominates.
"goods" or "services”
whether
goods.
which include transactions in
See
tracts
They include:
Anderson,
(1978); 1 R.
Anderson
§UCC 2-102
(1)
par-
language
used
the contractual
(3d ed.
on the
Commercial Code 502
Uniform
ties;
Installation,
1981).
Carpet
Inc. v.
In Colorado
(2)
agreement involves one over-
whether the
Palermo,
(Colo.1983),
the administration of
business as
teen
days
the number of
Powder Horn had
as to insure
well
receives
to prepare its bid.
best
supplies
work or
at the most
price practicable.”
reasonable
project estimator,
The Florence
Michael
O’Clair, calculated the cost of
Constr.,
concrete and
Dillingham
Inc. v. Milwaukee
Dist,
406,
labor associated
wall
Sewerage
F.Supp.
forming
with
Metro.
(E.D.Wis.1986)
Nelson,
(quoting
project
page
Florence
Inc. v.
on
fifteen
of his
Comm’n,
400, 409,
Sewerage
72 Wis.2d
241 book. The bid book was a
ring
three
bind-
(1976)).
N.W.2d
permitted
er that
removal of all
its
pages. O’Clair testified that the estimates
majority recognizes
that Powder
page
on
completed
January
fifteen were
on
negligently prepared.
Horn’s bid was
It
twenty-four
more than
hours
the role
before
nevertheless minimizes
that rea-
plays
bidding
missing
care
erroneous bid was submitted.
sonable
process by stating
very
page
term
had been removed from the bid book
“[t]he
usually
degree
‘mistake’
connotes some
on January
though
changes
even
no
negligent
Maj. op.
conduct.”
at 361.
were
made to
subsequently
it.
Contrary
intimation,
majority’s
O’Clair
that he
admitted
failed to fill
equated
care
reasonable
has never been
preprinted
three of the
spaces
blank
on the
Rather,
absolute
with
blamelessness.
the missing page fifteen. These blanks includ-
question of whether mistake
constitutes
space
ed
for the estimator to fill in his
negligence depends
circumstances
initials,
estimate,
original
to recheck his
requires
objective comparison
page.
to total the costs on the
Neither
particular conduct
a reasonably
to what
Donahue,
he nor
Powder Horn’s other esti-
prudent person
would do
the same situa- mator,
page
had double-checked his
fifteen
light
recognized
tion
risk associat-
estimate of the cost
labor and concrete
Keeton,
ed
it.
See W.
Prosser and
project.
for the Florence
Keeton on the Law Torts
at 170-
trial,
Following
judge
a bench
the trial
(5th
1984);
(Second)
ed.
Restatement
up
found
two
waiting
pick
weeks to
Torts
In the area of
§§
specifications, removing pages
bids, I
mistaken
believe the most useful
bid book
need
that did not
last-minute revi-
determining
standard
whether a mis-
sion,
failing
to use the series of checks
negligence
take constitutes
is the standard
built into
made
system,
Powder Horn’s
practice or custom in
in-
the construction
product
negligence.
mistaken
bid a
dustry.2 It
undisputed
that failure to
suggested
fact
judge
the trial
that Powder
industry
observe
standards
reasonable
bidding procedure may
is evidence
Horn’s
consti-
negligence.
care
W.
have
*17
Keeton,
gross
Prosser
negligence.3
on the Law
tuted
Keeton
order,
sаy
compliance
judge
2. This is not to
that
with indus
3.
his
noted that
trial
try
negligence.
standards can never constitute
4,
large
relatively
as
the two
items in Number
737,
(2d Cir.),
Hooper,
The T.J.
60 F.2d
Page
to Item 4
of Exhibit
that were
on
Transp.
cert. denied sub nom. Eastern
Co. v.
omitted ...
I wonder about ...
it seems
Barge Corp.,
Northern
287 U.S.
53 S.Ct.
ordinary
just more than
ne-
to me that that’s
issue, however,
(1932).
III. contractor inadvertently to withdraw an er- majority correctly majority’s concludes roneous rule bid.5 would 24-103-202(6) prohibit require section does withdrawal of all erroneous bids faith, permitting Powder Horn to re- made in essentially which is analysis scind proposed by the contract. This neverthe- same standard that was important question rejected less the more Model by overlooks Procurement Code and Assembly.6 of whether in such circumstances General promulgated by Policy and this was the concrete and the Office. labor. After bid opening changes prices These were considerable amounts ... which I no in bid or other provisions prejudicial think a reasonable contractor should not have of bids to the interest of Nor, opinion, missed. in the Court’s would competition permit- or fair shall be [State] not, contractor a bid reasonable magnitude, of this by Except provided regula- ted. tion, as otherwise $700,000, go through almost permit all decisions to the correction or up figures add one more time. bids, withdrawal of or to cancel awards or added). (Emphasis He concluded mistakes, sup- contracts based on bid shall be here, think, you I think have a I combination ported by a written determination made courtroom, using papers spread as the Chief Procurement Officer or head of a system probably demonstrated defense Agency. Purchasing was, meаn, in and of itself I that was ludi- added). (Emphasis you crous to the Court. How could avoid an my way error did taxes ... if I income I "inadvertent," appears 6.The word which sec- just would be in Leavenworth now. It won’t tion 3-202 the Model Code Procurement way. work that 24-103-202(6) section of the Colorado Revised “inadvertently,” Statutes as is defined as "heed- 24-101-105(2) politi- 4. Section ’’[a]Il states that less, negligent, inattentive unintentional.” ... agencies cal subdivisions and local of this Dictionary New Webster’s Third International adopt any part state are authorized to or all (5th Dictionary Black’s Law accompanying this code and its rules.” The 1979) as ed. ness; defines "inadvertence” ”[h]eedless- adopted has not the Procurement Code. Never- attention; care; lack of want careless- theless, municipal- it is fair assume that other ness; person pay failure careful and Code, adopted ities have the Procurement there- prudent negotia- progress of attention to the by making relevant intent General proceeding rights tion or which his court Assembly applies policy it considerations text be affected.” Neither the nor the com- implicated by majority’s rule. 3-202(6) mentary to section resolves the ambi- 3-202(6) guity "inadvertently" Section of the Model Procurement created the word as to Code states: Model Code whether the Procurement intends Bids; adopt negligence faith or a standard Correction or Withdrawal of Cancel- permitting standard for rescission of an errone- lation of Awards. Correction withdrawal 24-103-202(6) inadvertently similarly ous si- before bid. Section erroneous bids or af- award, ambiguity prob- but ter or cancellation awards or lent. This underscores one con- mistakes, tracts based on such lem of Code’s effort to shall be the Model Procurement Rudland, permitted regulations codify in accordance with rules. See Ration- mistake *18 Requiring cost, Powder Horn to show that its resulting estimated in a net loss to despite error exercise occurred of rea- the bidder for that item. Yet a low bidder policy sonable care is faithful to the consid- corresponding has no bring incentive to erations that underlie the Colorado Pro- public the attention of the authority an curement Code. Section 24-101-102 recites resulting gain error in a net to the bidder underlying purposes policies of Col- he already because has been awarded the orado’s version of the Model Procurement contract. Accordingly, purchasing val- purposes policies Code. These are: public ue of funds can be diminished but (a) simplify, clarify, To and modernize by permitting not increased rescission of governing procurement by law carelessly computed bids. Colorado; state of Careless bids also public lower confi- (b) provide To public for increased con- procedures dence in the in public followed procedures fidence in the followed in procurement in violation of section 24-101- public procurement; 102(2)(b). A low bidder would receive the (c) equitable To ensure the fair and opportunity, bidders, denied to all other persons treatmеnt of all who deal with light reconsider his bid in competitors’ procurement system of the state of bids which are higher known to be than his Colorado; required and which are to remain available (d) provide economy To increased public and, inspection by custom procurement state activities and to max- municipalities those adopted have imize practicable to the fullest extent Code, by See, Procurement e.g., statute. purchasing public value of funds of the 24-103-202(4), (1982). 10 C.R.S. Re- Colorado; state of simply scission could then become another (e) To foster effective broad-based option business oppor- event that an competition within enterprise the free tunity larger profit to make a arises after system; and open. are possibility bids Even the (f) provide safeguards To for the main- option public such an would erode confi- procurement tenance of a system qual- public dence in the procurement process. ity and integrity. public authority prevent That the could not (1982). 10 C.R.S. by showing that rescission the mistake was Permitting bid withdrawal for mistakes negligence due to the bidder’s would fur- that occur the exercise of despite reason- ther public undermine that confidence. able care ensures fair treatment of low Finally, permitting contractors to rescind by relieving bidders them of burdens carelessly prepared bids would confuse they caused mistakes could not reason- simplify public procurement rather than ably prevented. Requiring have bidders to 24-101-102(2)(a) violation of section by in- conform bids to the industry standards of troducing greater uncertainty into the bid reasonable care maintains the integrity of bidding process, process. longer and in Public authorities could no turn increases public confidence in procedures process complete consider the bid fol- when the public procurement. lowed in opened. bids longer were Bids could no considered period irrevocable the time A good permits faith rule that rescission specified in the invitation for as re- bids bids, of contracts for careless errors in quired by parties, between the contrast, would undermine the policy con- industry, custom in the statute siderations outlined in the Procurement municipalities adopted those that have Code. purchas- Careless bids diminish the See, e.g., Procurement Code. public value of funds in violation of 24-105-201(4), (1982). The 24-101-102(2)(d). section A C.R.S. low bidder has majority bring adopted by economic incentive to faith rule to the atten- tion of authority any could conceivably error cause authorities given whose actual cost for a item acceptance process exceeds to accelerate the formal Rules, diking the Bid Mistake 16 Pub.Cont.L.J. *19 so as was opening product of bid to remove tractor s error not a of bad
to the time importantly, analysis faith. More good uncertainty the the faith rule weight places no significance the creates. requiring parties bid bonds. Private are required accept not the lowest IV. generally require do not bonds. But gives majority’s the insuffi- Finally, rule procedures, public these so vital to the public character cient consideration designed process, appear- are the avoid bidding process. in Unlike bids prac- ance that form of favoritism sector, public private in sector bids public procurement by awarding ticed in responsible to the lowest must be awarded the contract in all cases to the lowest re- 31-15-712, (1986).7 12B C.R.S. bidder. § sponsible way parties In this bidder. adopted Although has not the Pro- satisfy simply their duties not to them- Code, its curement contract public selves but to which demands in- Horn contains the same elements. The expenditures public funds be above provided formational document to all bid- reproach. incorporated by reference into the ders and Every obligates contract requires applicant bid contract each to sub- (Second) act in faith. Restatement mit not be a sealed bid which revoked (1979). By requiring Contracts § sixty days opening. after Each bid no more in of bidders than faith re- accompanied by must bond for be five contracts, scinding majority relieves percent of the total amount of the bid. higher obligations contractors of the at- opened publicly Bids must be and read tending management public funds. The aloud accordance with the advertisement question very rule calls existence into recog- As the Procurement Code bids. evidentiary of bid bonds because the bur- nizes, designed these elements are to main- den on the contractor is so minimal. bidding process. integrity tain the three-part I adopt would test John аddition, in- informational document Builders, Inc., J. Calnan v. Talsma Co. corporated into the bid contract states that Ill.2d N.E.2d 10 Ill.Dec. party to whom contract [t]he (1977), require a contractor show as required awarded will be execute the (1) precedent to rescission that condition performance Agreement and obtain the the mistake relates to a material feature of payment within BOND and BOND ten (2) contract; the mistake de occurred days calendar from the date when care; spite the exercise of reasonable OF NOTICE AWARD is delivered to the rescission could return the au BIDDER. The OF AWARD NOTICE thority quo. status I believe accompanied by necessary shall be the proper damages measure of when a Agreement prove entitled to and BOND forms. In case bidder fails to that he is rescission is the difference between the two of the BIDDER to failure execute the bids, lowest to exceed amount of Agreement, op- the OWNER at his the bid bond. default, tion consider the BIDDER the BID accompany- which case BOND appeals. I would affirm the court of proposal proper- shall become say I am MUL- authorized that Justice ty of the OWNER. joins LARKEY me this dissent. added). (Emphasis majority’s analysis defeats the ex- press provisions by per- the bid
mitting City’s option rescission not at the showing merely
but that the con- pertinent part: responsible open 7. Section 31-15-712 states tract bidder on to the lowest ample bids city after advertisement.... All work done in the construction added). (1986) (emphasis improvement of works of five 12B thou- C.R.S. sand dollars more shall done con-
